Decision The Board agreed:- 1. to note the contents of the report and approve the approach to long listing and the long list of options as detailed at appendix 1 of the report; 2. to delegate the arrangements for the Reference Group to the Head of Adult Care; 3. that support arrangements should be put in place for the Learning Disability Members; 4. that preparations should be made for a presentation to be given at the next Board meeting and Reference Group meeting and that this presentation would also be given to members of the public at a later date; 5. to note that future reports will be presented to the Reference Group in a user friendly format with appropriate support. (Reference: Report by Executive Director – Customer Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1The Project Board is asked to note the report and approve the approach to long listing and the long list of options as detailed in the report at appendix 1 hereto.
3. DETAIL
3.1The Project Board previously tasked the Project Team to carry out an options appraisal of service delivery options in relation to Learning Disability Services and, in particular, to report back on the long listing of options.
3.2The project team have carried out the long listing in accordance with the report at appendix 1 hereto. In accordance with the agreed process, adult services are constituting a reference group to act as a consultation body to comment on the long and short listed options generated by the Project Team and within the context of the previously agreed objectives. The reference group is scheduled to meet on 20 April 2010. The consultation process will be moderated by Adult Services. The comments generated from the Reference Group, as a result of the consultation, will be communicated to the Project Team in order that they may have regard to the comments in determining the short listed options for recommendation to the Project Board. The reference group will be consulted further on the short list and the results of this will be reported to the Project Board at its meeting in June 2010.
1 4. CONCLUSION The Project Team, having: undertaken the long listing of options; constituted the reference group; consulted with the reference group and reported on the short listing to the Project Board are currently on schedule to provide the Project Board with the relevant final business case part of the review as required by the Board.
5. IMPLICATIONS
Policy: None at present Finance: None at present Legal: None at present Personnel: None at present Equal Opportunities: None at present For further information please contact:
David Logan Jim Robb QIO Special Projects Head of Adult Services Customer Services Community Services Argyll and Bute Council Argyll and Bute Council Kilmory Kilmory Lochgilphead Lochgilphead
Tel: 01546 60 4322 Tel: 01546 604323
Douglas Hendry Executive Director of Community Services
2 Appendix 1
Learning Disability - Long Listing Workshop Project Team 19 March 2010
Summary of Approach
1. This stage of the process involved the identification of a long list of options for delivery of the Learning Disability service. This was achieved by the Project Team in a workshop session by reference to the agreed objectives.
2. In generating the long list of options the Team followed the accepted practice, utilised in similar reviews, of identifying the first option as continuing with the current delivery of the service. The Team then, through discussion and application of professional judgement, applied the detailed approach below in order to generate a long list of options for delivery of the service which, without critical analysis at this stage, are expected to have the potential to meet, in some respect, the objectives set.
3. The long list of options will be commented on by the learning disability Reference Group which will be constituted as reported to the Project Board on 26 February 2010. Comments on the long list will be considered by the Project Team when determining the shortlist.
Detailed considerations
4. The detailed approach was based on the following considerations:
a. Segmentation of the service – The Team agreed to segment the service based on the categorisation of need identified by the Service at the Development Day on 19 November 2009. Upon discussion it was considered appropriate to combine categories 2 and 3 as they covered similar need characteristics. The categories of need used were:
Category Description
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Market test: previous market test 2011Decision The Committee noted the detail of the report. (Report by Executive Director – Community Services dated Janua...
Update on eadar glinn care home, obanDecision The Committee agreed to - 1. Note the content of the report. 2. Undertake a market test as outlined in the d...
Update on struan lodge care home, dunoonDecision The Committee noted the cost analysis with respect to Struan Lodge, noted the excess capacity in the indepen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.