Milton Burn Flood Prevention Scheme

Noted Committee 1 paper

Bute and Cowal Area Committee noted this item on Tuesday 1 February 2011. Below is the council's own wording, with the papers it was decided on.

Item7a

Resolved

Decision The Committee noted the contents of the report by the Principal Engineer. (Reference: Report by the Principal Engineer dated 11 th January 2011 – submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Bute and Cowal Area Committee

Summary

The purpose of this report is to advise on the status of the project.

Recommendations

That the contents of the report are noted.

3. DETAILS

Tenders for the proposed works were received on 1 December 2010. After consideration of the returned tenders, it was determined that acceptance of any of the tenders would leave the Council and wider public with a considerable risk were the appointed contractor to run into construction or financial difficulties. As a result it was decided that none of the returned tenders should accepted and it is now proposed to proceed with the works in two separate contracts. The first tender will be for the works in John Street which can be done at a time of the Council’s choosing i.e. as soon as due process will allow, and this to be followed by a tender for the walls in the burn itself and the chamber below the supermarket car park. The various details and permissions that were agreed for the combined scheme will need to be checked for the new timescale associated with the separate contracts.

Assuming that there are no issues from any of the affected parties, the project will now proceed on the basis of two contracts and the initial timescale as shown below:-

Item John Street Pipe Milton Burn Works PQQ issued Jan 2011 Aug 2011 but depends on Morrisons’ response PQQ returned Feb Sept Tenders Issued Feb Oct Tenders returned April Nov Standstill letter April Nov issued Award Contract April Dec Start on site May Jan 2012 Completion Dec 2011 Sept 2012

It has been assumed that the supermarket will sign up for the same deal but 12 months on i.e. entry for January 2012. To date there has been no indication from them yet on this and how this deal is concluded will have a big impact on when the scheme will be completed.

The cost is expected to be at the limit of the existing (£2.3m) budget. For further information, please contact:-

Arthur McCulloch (01546 604632) Principal Engineer 11 January 2011

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Milton Burn Flood Prevention SchemeReport 49 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
JD
John DuncanOfficer, expected
RM
Councillor Robert MacintyreMember, present
DM
Dinah MackayOfficer, expected
BM
Councillor Bruce MarshallChair, present
AM
Councillor Alister McAlisterMember, present
AM
Councillor Alex McNaughtonMember, present
JM
Councillor James McQueenMember, apologies
LS
Councillor Len ScoullarVice-Chair, present
RS
Councillor Ron SimonMember, present
IS
Councillor Isobel StrongMember, present
DW
Councillor Dick WalshMember, apologies

On this subject at Argyll and Bute

Search all
  1. Milton Burn Flood Prevention SchemeThis decision
  2. Verbal update on Milton Burn Flood Prevention SchemeNoted
  3. Verbal update on the Milton Burn Flood Prevention SchemeNoted
  4. Milton Burn Flood Prevention SchemeNoted
  5. Milton Burn Flood Prevention SchemesNoted
  6. Update on Milton Burn Flood Prevention SchemeNoted

More from Argyll and Bute Bute and Cowal Area Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... Noted Open
1 Sep 2026 Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... Noted Open
1 Sep 2026 Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... Agreed Open
1 Sep 2026 Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... Noted Open
1 Sep 2026 Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... Noted Open