Resolved
Decision Agreed to note the contents of the report subject to:- Regular updates on progress to be provided to members. (Ref: Report by QIO Special Projects, dated 15 February 2011, submitted)
Helensburgh & Lomond Area Committee agreed this item on Tuesday 15 February 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Agreed to note the contents of the report subject to:- Regular updates on progress to be provided to members. (Ref: Report by QIO Special Projects, dated 15 February 2011, submitted)
2.1That the Area Committee note the report.
3.1Legal Position Following the meeting of the Council’s Executive on 4 November 2010, Legal Services contacted HDL’s (Helensburgh Developments Ltd) solicitors to settle the concluded contract. Settlement was not effected and, in accordance with the terms of the contract, the Council issued formal notice to HDL’s solicitors resiling from the contract.
3.2Demolition In regard to demolition, following the Council resiling from the contract, arrangements are being made, through Facility Services, to let a contract for the demolition of the building. Work is ongoing in this regard. Given the nature and scale of the building, Facility Services advise that a Pre – demolition type 3 Asbestos Survey is required and this is being sought, in the first instance, to inform the tendering process. Tendering for the main demolition contract will follow in March and subject to a satisfactory outcome contractors should be on site during May 2011.
The following dates are provided by Facility Services as an indicative timescale. It should be noted that these dates are subject to change, dependent on the proposed Tender process.
• PQQ issue 17th February 2011 • PQQ return 3rd March 2011 • Evaluation 3rd March – 17th March 2011 • Tender Issue 17th March 2011 • Tender Return 7th April 2011 • Evaluation 7th April - 21st April 2011 • 10 day Standstill Period 22nd April – 1st May 2011 • Award Contract 2nd May 2011 • 3 week Contractor Mobilisation Period 2nd May – 20th May 2011 • Site Start 23rd May 2011
1 These key dates will be monitored to assess progress to ensure that the matter of demolition is progressed as expeditiously as possible.
3.3Security The Council, through Facility Services, has now resumed direct responsibility for security arrangements. These arrangements have been reviewed by the Council’s Health and Safety section. The security company “Safe Estates” is currently providing security through a regime of electronic sensors within the building and a call out service with regular visits by Facility Services.
3.4Communication Members shall be updated as matters progress. Matters have been discussed with the Council’s Communications Team who are aware of the position and are prepared to provide an appropriate response in regard to any relevant press request.
3.5Marketing
Estates within the Council’s Facility Services are now reviewing the site in regard to its current valuation and marketability.
4. CONCLUSION
Steps are being taken to procure demolition in compliance with the previous instruction from the Council’s Executive and a review of the marketability and valuation of the site of the former Hermitage Academy is being undertaken.
5. IMPLICATIONS
Policy: Progression of demolition is in accordance with the instruction from the Executive.
Finance: The cost of demolition, once ascertained by tender process is expected to be offset against any eventual capital receipt.
Personnel: None at present
Legal: the Council is currently pursuing a process to facilitate the obtaining of tenders for demolition..
Equal Opportunities: None at present
Executive Director of Customer Services
For further information please contact; David Logan, QIO Special Projects – 01546 604322 Hugh Blake, Estates Surveyor – 01436 658963
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Former Hermitage AcademyReport | 64 KB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.