CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Jan17Tuesday

Rothesay CHORD Project Board

Argyll and ButeHeldPapers from www.argyll-bute.gov.uk
Tuesday 17 January 2012, 11.00amHeld 5423 days ago.
Eaglesham HouseMountpleasant Road, Rothesay. Open to the public.
10 items, 3 papersAbout 173 KB, led by Highlight / Progress report - THI.
No exempt items listedEvery item is due to be heard in public.
This meeting was held17 January 2012
10items
3papers
5decisions
–exempt
Running order, sized by papersItem 1 to 10
ReportsProcedureExempt parts

The agenda, item by item

What the committee will consider, in order, with every paper attached to its item.

1
Procedure

Apologies

2
Procedure

Declarations of Interest

4
Report

Highlight / Progress report - Rothesay Pavilion

Decision: Decision The Board noted the information provided. (Reference: Report by Jane Robertson, Prince’s Regeneration Trust – submitted) Decision page

ReportHighlight / Progress report: Rothesay Pavilion58 KBDownload
5
Procedure

Rothesay Pavilion funding bids - verbal update

Decision: Decision The Board noted the information provided. Decision page

6
Report

Highlight / Progress report - THI

Decision: Decision The Board noted the information provided. (Reference: Report by Audrey Martin, Senior Planning Development Manager – submitted) Decision page

ReportHighlight / Progress report: THI59 KBDownload
7
Procedure

Any Other Competent Business

Decision: Decision The Board agreed John McGhee would be invited to meetings as an advisor. Proposed: Councillor L Scoullar Seconded: Councillor I Strong Decision page

8
Procedure

Exempt Paragraph

The Committee resolved in terms of Section 50A(4) of the Local Government (Scotland) Act 1973, to exclude the public for the following item of business on the grounds that it was likely to involve the disclosure of exempt information as defined in Paragraph 9 of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. E1

8
Procedure

Rothesay THI grants

Decision: Decision The Board agreed:- i. That each small grant application is further developed over the next three months in order that these may meet the validity requirements of Rothesay THI, and thereafter assessed against the relevant scoring criteria and brought back to the Board for award decision. ii. That only a quarter of the small grant fund is made available between now and March, allowing the remainder to be held back in the hope that all seven grant applicants will eventually come forward...

10
Procedure

E1

- Paragraph 9 Any terms proposed or to be proposed by or to the authority in the course of negotiations for a contract for the acquisition or disposal of property or the supply of goods or services.

Read inside all 3 papersPro opens every page, searches every appendix, and keeps the papers if the council removes them.

Every paper for this meeting

All 3 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.

PaperSizeOur copy
Minutes of Meeting of 16th May 2011Item 3, Minutes of Meeting of 16th May 2011
56 KB
Kept 5 Oct
Highlight / Progress report: Rothesay PavilionItem 4, Highlight / Progress report - Rothesay Pavilion
58 KB
Kept 5 Oct
Highlight / Progress report: THIItem 6, Highlight / Progress report - THI
59 KB
Kept 5 Oct

Last time, and what carried over

The committee last met on 16 May 2011. 3 of its items lead into this meeting. Point at any item to follow a thread. Procedural items are left out.

May16
16 May 20119 items, 4 papers
Held
carried over
Jan17
17 January 201210 items, 3 papers
Held
3
Minutes of Meeting of 30th March 2011
4
Governance Arrangements - Rothesay THI
6
Highlight / Progress Report - Rothesay Pavilion
7
Rothesay Pavilion Full Business Case
3
Minutes of Meeting of 16th May 2011
4
Highlight / Progress report - Rothesay Pavilion
6
Highlight / Progress report - THI

The threads

  • Minutes of Meeting of 30th March 2011 leads to item 3, Minutes of Meeting of 16th May 2011
  • Highlight / Progress Report - Rothesay Pavilion leads to item 4, Highlight / Progress report - Rothesay Pavilion
  • Highlight / Progress Report - Rothesay Pavilion leads to item 6, Highlight / Progress report - THI
  • Rothesay Pavilion Full Business Case leads to item 4, Highlight / Progress report - Rothesay Pavilion

Not carried over

Governance Arrangements - Rothesay THI do not return this time.

See the 16 May meeting

This committee over time

Every Rothesay CHORD Project Board meeting we have read, the dates it has set for the future, and each time those dates have changed.

11 meetings, 2009 to 2014Dot size shows the number of papers
200920102011201220132014
HeldThis meeting
MeetingItemsPapers
14 Jan 2014Tuesday
4items
1papers
HeldOpen
20 Mar 2013Wednesday
12items
5papers
HeldOpen
6 Mar 2012Tuesday
6items
1papers
HeldOpen
17 Jan 2012Tuesday, this meeting
10items
3papers
16 May 2011Monday
9items
4papers
HeldOpen
30 Mar 2011Wednesday
6items
3papers
HeldOpen
19 Apr 2010Monday
8items
5papers
HeldOpen
10 Feb 2010Wednesday
6items
5papers
HeldOpen
19 May 2009Tuesday
8items
1papers
HeldOpen
21 Apr 2009Tuesday
4items
0papers
HeldOpen
18 Feb 2009Wednesday
9items
2papers
HeldOpen

Follow the Rothesay CHORD Project Board

Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.

What should we tell you?

Argyll and Bute, Rothesay CHORD Project Board

Rothesay CHORD Project Board: 3 kinds of updateArgyll and Bute, sent the same day
PDF
3 papers published for 17 JanuaryHighlight / Progress report - THI and 2 more papers
DAT
Meeting dates updatedAny date added, moved or dropped
DEC
Decisions from 17 JanuaryThe committee's resolutions, the day they are recorded
ABC
"highlight" found in 2 papersHighlight / Progress report: Rothesay Pavilion and Highlight / Progress report: THI
Each update links to the paper and the council's own copy
Free: one weekly alert. Pro: every option, the same day. Pro Plus: straight into your own systems.

Free

One alert, sent weekly, on titles and decisions.

£0for good
  • 1 alert, weekly summary
  • Titles and decisions
  • Link to every official paper
Save this alert free
Most chosen

Pro

Unlimited alerts the same day, searching every page.

£99per user a month
  • Unlimited alerts, same day
  • Matches inside every page and appendix
  • Every council, not just this one

Pro Plus

Your team, with every match pushed into your own tools.

£449a month, 3 users included
  • Everything in Pro, for 3 users
  • Alerts as webhooks into Slack or a CRM
  • API key and bulk export of this council

Data licence

Every council's records in your own products and research.

£12,000a year, from
  • Unlimited API and full archive delivery
  • Rights to use the data in your products
  • Back to 2000, every council
Talk to us

Never miss what this committee decides

Papers, decisions and date changes for the Rothesay CHORD Project Board, and every other committee you follow, the day they appear.

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies