Report to Bute and Cowal Area Community Planning Group
Putting Tenants First
Bute and Cowal Local Area Committee Planning Group Argyll Community Housing Association Update 14th March 2012 Alastair MacGregor C f Executive Chief 1 Putting Tenants First
Investment Programme from Transfer to 29/02/2012 Elements Bute and Cowal
Windows & Doors 824
Kitchens & Bathrooms 2002
Heating & Rewire 1106
g Roof & Roughcast 119
Total Elements 4051
Stock Numbers 1414
Total Expenditure (exc VAT) £14,276,707
2 Putting Tenants First
Bute and Cowal Investment Programme Elements 2011/12 Expenditure Projected 2012/13 Windows & 54 £272 477 £272,477 222 Doors Kitchens & 129 £689,314 400 B h Bathrooms Heating & 515 £1,358,974 489 Rewire Roof & 7 £363,238 165 Roughcast Refurbishment £361,250 Total 705 £3,045,253 £5.2million 1276 The above Th b is i the th currentt and d ongoing i investment i t t programme to t improve i ACHA’s properties in Bute and Cowal to meet the Scottish Housing Quality3 Standard by 2015 Putting Tenants First
O Ongoing i Initiatives I iti ti • 24 units affordable housing g at Ardenslate,, completion December 2012. • 4 units affordable housing at Lochgoilhead, Lochgoilhead completion this week. • Total modernisation on site at Massan View, View Sandbank and Colintraive for 20 Dorran properties
4 Putting Tenants First
Ongoing Initiatives (continued) • The Th Association A i ti will ill b be going i on site it shortly h tl ffor modernisation in 18 properties at Regent and S li b Salisbury T Terrace, Dunoon. D • Roof and roughcast contracts on site in Rothesay and Dunoon. • Broxwood Place and Douglas g Cottages, g , Dunoon; roughcast replacement and cavity wall insulation to take p place. Going g on site shortly. y 5 Putting Tenants First
Ongoing Initiatives (continued) • ACHA ACHA’s s Board have approved purchase of the Salvation Army Hall in Ladeside Street, Rothesay for offices subject to planning consents offices, consents. • Ballochgoy Resource Centre; discussion ongoing with the Bute Family Project and Bute FM regarding utilising the facilities. • Lift, Alarm and Legionella upgrades at our sheltered housing complexes completed; Cragroy, Dunoon, Wallace Court,, Sandbank,, Ferfadd Court,, Rothesay; y; Investment £85,000 6 Putting Tenants First
Ongoing Initiatives (continued) • The Association has introduced the Allpay system for our tenants. • The Good Garden and Good Neighbour Schemes will now become permanent. p • Obtained eviction for anti social behaviour in Rothesay. Rothesay
7 Putting Tenants First
Ongoing Initiatives (continued) • We believe the site at Victoria Park Park, Dunoon will be prioritised in the SHIP submission to the Scottish Government. Government • ACHA will continue with Welfare Rights Service; i income tto date d t for f tenants, t t £2.3million. £2 3 illi
8 Putting Tenants First
Wid ACHA IInitiatives Wider iti ti • Building our own In House Repairs Team across Argyll and Bute. • Energy efficiency investment; ongoing £4million programme completing 1st year. • The Th Association A i ti will ill continue ti it its £10 £10,000 000 Community Action Fund. • ACHA is now a charity.
9 Putting Tenants First
Wider ACHA Initiatives (continued) • The Th Association A i ti intends, i t d ini partnership t hi with ith th the Scottish Government, to continue to invest aroundd £600 £600,000 000 per annum iin Aid Aids and d Adaptations in tenants’ homes. • Pressured Area Designation now in place. • Rural R lH Housing i D Development l tFFund. d
10 Putting Tenants First
Wider ACHA Initiatives (continued) • Scottish Government has now reintroduced 3 year investment programme.
• Scottish Government now consulting on greater flexibility to landlords on allocations allocations.
• Housing H i bbudget d t £360 £360million illi over th the nextt 3 years. 11
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bute and Cowal Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Scottish Fire and Rescue Service UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Scott...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.