Proposed Carriageway Reconstruction Works 2012-13

Agreed Committee 3 papers

Helensburgh & Lomond Area Committee agreed this item on Tuesday 12 June 2012. Below is the council's own wording, with the papers it was decided on.

Item6b

Resolved

Decision Agreed to note the Scheme list, sequence and progress to date on the planning, consultation and implementation of the works programme. (Ref: Report by Roads Performance Manager, dated 12 June 2012, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee

Helensburgh & Lomond APPENDIX 1

Provisional Scheme Revised BoQ Scheme Budget (£7m/yr Measured Route Location Scheme Details Cost Estimate (£5m estimate Comments Comment Allocation) scheme value Budget) (except #) 8th June 2012 update In Progress A814 Iona Stables Resurfacing £102,434 £110,000 £97,162 TBA prepared by 1st June In Progress A814 Ardmore Resurfacing £62,441 £70,000 £92,003 TBA prepared by 1st June In Progress A814 Moss Road Resurfacing £59,678 £60,000 £73,782 TBA prepared by 7th June In Progress A814 Geilston Resurfacing £53,527 £60,000 £66,430 TBA in progress 8th June Planned A814 Cardross Village Resurfacing £186,750 £190,000 £162,896 TBA Sept / Oct Planned A814 Ardoch Resurfacing £64,181 £70,000 £103,694 TBA prep work 11th onwards Planned A814 Dumbarton Resurfacing £57,067 £60,000 £10,000 # TBA PATCHING for S/D 2013

Planned B872 Faslane Resurfacing £40,876 £50,000 £46,080 TBA Autumn 2012 tbc Planned U241 Queens Crescent Resurfacing £29,105 £30,000 £26,685 TBA Autumn 2012 tbc In Progress A814 Garelochhead Bypass Surface dressing £78,310 £70,000 £53,760 TBA Started 7th June - Rain delay

Completed Uc15 Argyll Road, Kilcreggan Surface dressing £30,000 £32,400 TBA Completed 6th June Completed B833 Garelochhead to Clynder Surface dressing £40,000 £32,400 TBA Completed 7th June Includes works in Cove / Succoth In Progress B833 Peaton to Coulport Resurfacing £100,000 £100,000 # TBA and Helensburgh tbc

Works in progress, Earthworks and Realignment and In Progress B833 Millbrae £200,000 £200,000 # TBA Drainage May - June . Surfacing July Resurfacing ( £166k est)

Planned A814 Westerhill Farm Surface Dressing £14,016 TBA delayed from 7th June - Rain

Completed var Surface dressing sites Scrub & pre-patch £40,000 £28,000 scrub clearance S/C payments

Helensburgh to Re-lining and anti skid repairs to Planned A814 Lining and HFS £75,000 # TBA exiting design ( EO reconst) Dumbarton £734,369 £1,140,000 £1,226,308 £28,000

Works defered until 2013 Capital programme Planned A814 Hermitage - Iona Stables Surface Dressing budget tbc On completion of Ph 1 Cycleway 2012 Planned A814 Ardarden - Geilston Surface Dressing budget tbc Pre-patched June 2012 Planned A814 Ardoch - Cats Castle Surface Dressing budget tbc Pre-patched June 2012

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2HL Capital programme 2012Report 76 KB DownloadRead as text
PDF
3A814 Roadworks NoticeReport 68 KB Download
PDF
Proposed Carriageway Reconstruction Works 2012-13Report 80 KB Download

At this meeting

Whole meeting

Who was there

10 of 11 attended
MC
Councillor Maurice CorryMember, apologies
VD
Councillor Vivien DanceChair, present
GF
Councillor George FreemanMember, present
DK
Councillor David KinniburghMember, present
RG
Councillor Robert Graham MacIntyreMember, present
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonMember, present
GM
Councillor Gary MulvaneyMember, present
JR
Councillor James RobbChair, present
BR
Belinda RuthvenClerk, present
RT
Councillor Richard TrailVice-Chair, present

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies