Decision The Council noted the current status of the UK Government Mobile Infrastructure Project and the commitment by Vodafone to upgrade all existing Argyll and Bute 2G cells to 3G over the next 12 months. The Council recognises the importance of mobile connectivity to the future development of the local economy in Argyll and Bute and the importance of basic service for the safety of individuals and requests that the Executive Director of Development and Infrastructure makes provision within the draft Economic Development Action Plan to formulise Council policy, strategy and actions with regard to 2G, 3G & 4G mobile connectivity and coverage, and in particular working with communities, mobile communication providers and Ofcom to: a) Identify the location of mobile not spots for 2G and 3G signals across Argyll and Bute . b) Identify the impacts of various mobile providers development plans on coverage across Argyll and Bute . c) Develops plans with partner organisations to work with the industry to maximise coverage across Argyll and Bute . (Ref: Report by Executive Director of Customer Services dated 11 January 2013, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
That members note the current status of the UK Government Mobile Infrastructure Project and the commitment by Vodafone to upgrade all existing Argyll and Bute 2G cells to 3G over the next 12 months.
3. DETAIL
3.1Ofcom published their first full review of the UK Communications Infrastructure in November 2011. The report looked at various aspects of the national communications infrastructure and, in particular, the quality and availability of existing mobile coverage. Across the UK there are some 80,000 “not spots” – officially defined as “An area which is not covered by any mobile networks”.
3.2The report confirms the following about mobile coverage in Argyll and Bute: • 19.1% of the geographic area within Argyll and Bute has no reliable mobile telephone signal (third highest in the UK behind The Highland and Angus Councils) • 1.6% of the premises in Argyll and Bute have no reliable mobile telephone signal • Only 17.5% of the geographic area of Argyll and Bute but 69.8% of all premises can pick up a signal from all of the national operators • There is no reliable 3G signal available in 82% of Argyll and Bute (fourth highest in the UK behind Scilly Isles, Dungannon and Moyle) • 22.4% of all premises in Argyll and Bute have access to 3G networks
3.3The Council is contracted to Vodafone for mobile telephony under the PSN Services framework agreement (RM1498 Lot6) administered by the Government Procurement Service. A recent tender exercise under the framework confirmed Vodafone has the widest coverage of all operators in Argyll and Bute. The Council has issued approximately 1140 phones but considers the lack of 3G across the region as a major inhibiter towards achieving more with a truly flexible, mobile, and adequately equipped workforce. Other Councils operating in areas of the UK with better coverage or where 3G is more readily available have been able to adapt services and systems to work on mobile devices and ultimately benefit from better, faster, and, in many cases, cheaper services in the community. Barnsley MBC is one of the flagship organisations in the Mobile & Flexible Working National Project, and has completed some ground breaking work in the area of Regulatory Services, transforming Environmental Health, Trading Standards and Licensing.
3.4In an official return to the Improvement Service in 2009 the Council cited “poor coverage” as the principal reason for the lack of success when trialling a mobile Benefits Change in Circumstances service. The Council also implemented a Vehicle Tracking system which has developed into a credible service since 2009 but the system’s functionality has been limited by the lack of 3G.
3.5The Planning Service recently introduced mobile access to site plans and associated documentation for planners and although partially successful, more could be done if the mobile network was more readily available. Further pilots in building standards, environmental and trading standards services have proved to be partially successful but were restricted by the lack of coverage. All services working within communities have expressed an interest in developing mobile services and are willing to consider further service improvements once the mobile network offers better data coverage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.