CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Helensburgh & Lomond Area Committee, Tuesday 14 January 2014 at 12.00pm

Kilmahew/St Peters Project

Decided Committee 1 paper

Helensburgh & Lomond Area Committee decided this item on Tuesday 14 January 2014. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

The Motion was carried by 8 votes to 2 and the Committee resolved accordingly. (Ref: Report by Executive Director of Development and Infrastructure Services, dated 14 January 2014.)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee

Summary

1.1The Kilmahew/St Peter’s Project near Cardross aims to transform the derelict site of the former St Peter’s Seminary buildings and the surrounding woodlands of Kilmahew which has lain abandoned for more than thirty years. Whilst the building and site is of national significance due to its Category A listing, it is currently inaccessible due to being a dangerous building.

1.2The project has been ongoing for 5 years and is well advanced in the development stages. The project has recently secured a stage 1 funding approval from Heritage Lottery Fund Scotland (HLF) for £565,000 development funding to allow the development of a second stage submission for £3m in 2015. The project is also the subject of a funding application to Creative Scotland for £2m.

1.3The total capital value of the works is approximately £7m. The total value of funding applications to HLF and Creative Scotland will be £5.5m. In addition, Historic Scotland has already granted £500,000 towards eligible capital works.

1.4NVA, a Scottish Arts charity ‘who are driving the project’ have requested £25,000 from the Council specifically to create an Audience Development Strategy which is required for stage 2 bids to both the Heritage Lottery Fund and Creative Scotland.

1.5NVA seek the strategic support of the Council to assist in securing the necessary funding to deliver the project and will be making a presentation to the Helensburgh and Lomond Area Committee on the 14 January 2014. Strategic support will be in the form of political support and officer time, NVA will not be making an immediate request to Argyll and Bute Council for financial assistance towards capital works but would request this is kept under review if in the future appropriate opportunities arise.

1.6The benefit of the project is to safeguard and bring back into productive use a Category A listed building of international repute for the purpose of cultural educational activities. Currently a dangerous building, failure to safeguard the building may in time result in its demolition for reasons of public safety. 2.0 RECOMMENDATIONS

2.1That members agree to the following recommendations on the presumption that NVA are successful in their stage 1 application to Creative Scotland.

2.2That members agree to the payment of £25,000 to NVA solely for the development of an Audience Development Strategy with regards to the Kilmahew/ St Peter’s Project, and that members then agree which of the following four options for funding they wish to adopt. The four options are as follows:

• To earmark £25,000 from the General Fund Reserve. • To ask the Council to recognise the £25,000 as a cost pressure for D&I in the revenue budget during 2014-15. • To ask H&L Area Committee to allocate £25,000 from its share of additional council tax on empty homes to this project. • To advance money from the General Reserve Fund on the basis the first £25,000 of any underspend in Economic Development is used to fund the request. . 2.3 The payment totalling £25,000 will be phased over 2 consecutive financial years as follows; 2013/14 – £12,500, 2014/15 - £12,500.

2.4That members agree to support the project in principle and the provision of officer support to assist with securing the necessary financial capital monies to deliver the project.

3.0DETAIL

3.1A Project Business Case has been submitted to the Council to secure support for the Kilmahew/ St Peter’s project. Paragraphs 3.2 – 3.16 below contains extracts and summaries from the Business Case to provide an overview on the purpose, approach, costs, timescales and benefit of the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kilmahew/St Peters ProjectReport 83 KB DownloadRead as text

At this meeting

Whole meeting
3Kilmahew/St Peters ProjectThis decision
4Local Development PlanAgreed

Who was there

16 of 16 attended
MC
Councillor Maurice CorryMember, present
VD
Councillor Vivien DanceMember, present
GF
Councillor George FreemanVice-Chair, present
LI
Lynsey InnisSecretary, present
DK
Councillor David KinniburghMember, present
ML
Mark LodgeOfficer, present
RG
Councillor Robert Graham MacIntyreMember, present
SM
Shirley MacLeodSecretary, apologies, sent representative
AM
Audrey MartinOfficer, present
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonMember, present
GM
Councillor Gary MulvaneyChair, present

All 16 on the meeting page

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies