Decision The Council – 1. Noted the results of the consultation that Argyll & Bute will implement 3 hours 10 minutes sessions. 2. Noted Argyll & Bute’s plans for implementation of 600 hours, including new eligibility for 3 year olds and vulnerable 2 year olds and in addition noted the impact on staff contracts. 3. Noted the delay in Preschool Registration Week 2014 from the beginning of February to week beginning 3rd March to accommodate the changes to Early Learning and Childcare provision. 4. Agreed the increase to partner and private provider payments from £3.86 to £4.20 per capita per hour. 5. Noted the initial list capital expenditure required to support increased flexible provision and ongoing work being undertaken to prepare for 600 hour provision. (Reference: Report by Executive Director – Community Services dated March 2014, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Children and Young People Bill was published on 18 April 2013. By August 2014, local authorities will be required to increase provision from the 475 hours of funded pre-school education currently delivered, to 600 hours of free early learning and childcare. The increased provision is also to be extended to two year old children who are, or have been, looked after by the local authority. In January 2014 the Scottish Government announced that provision for two year olds should also increase to those two year old children in workless households, with further provision for two year old children from families who are eligible for free school meals in August 2015.On 21st February the Bill passed Stage 3 in the Scottish parliament.
Recommendations
2.1To note results of consultation that Argyll & Bute will implement 3 hours 10 minutes sessions.
2.2To note Argyll & Bute’s plans for implementation of 600 hours, including new eligibility for 3 year olds and vulnerable 2 year olds. In addition note the impact on staff contracts.
2.3To note the delay in Preschool Registration Week 2014 from the beginning of February to week beginning 3rd March to accommodate the changes to Early Learning and Childcare provision
2.4Agree the increase to partner and private provider payments from £3.86 to £4.20 per capita per hour.
2.5Note initial list capital expenditure required to support increased flexible provision and ongoing work being undertaken to prepare for 600 hour provision
3.0DETAIL
3.1Due to the short timescale for initial implementation, the Scottish Government has acknowledged that it is not going to be possible to fully expand choice and flexibility of provision from August 2014. However in subsequent years, additional flexibility will be introduced in consultation with parents and within the overall resources made available by the Scottish Government. 3.2 Local authorities have the flexibility to provide services differently in the future to meet local needs, incorporating the views of parents. There is no expectation that councils will have to put in place a set range of standard delivery models. Through extensive consultation of parents, one model has been identified to deliver 600 hours of early learning and childcare within local authority units in Argyll and Bute. In addition to this, partner and private provider nurseries will provide a range of alternative options for parents to choose. Increased flexibility will be offered to parents over the next three years
3.3The report to DMT in September 2013 indicated that parents were being consulted on two options for the delivery of 600 hours of early learning and childcare in Argyll and Bute:
Option A To increase early learning and childcare provision during term time to 15 hours per week, amounting to 570 hours per year. The remaining 30 hours per year to be allocated to outdoor learning and play opportunities through an external provider during a holiday period.
Option B To increase early learning and childcare provision during term time to 600 hours- increasing single sessions from 2.5 hours to 3 hours and 10 minutes
3.4As part of the consultation process, local authority staff were also consulted on their preferred option, as both models would result in an increase in working hours.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.