Decision The Committee noted the contents of the report; and The Committee noted that the next update on Older Peoples Care at Home Service on FQ4 would be at the June Area Committee and an update on Learning Disabilities Day Services would be at the August Area Committee. (Ref: Report by Area Manager, Adult Care dated 1 April 2014, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The purpose of this report is to update the Area Committee on the findings of the 3nd quarterly evaluation of the Care at Home provision within the Bute and Cowal area.
This report has been broken down to show the progress and joint working that has been put into place to ensure that a high quality service is provided, as it is recognised that this service is provided to vulnerable individuals, predominately by lone workers, in the home environment.
Recommendations
The remit of the Procurement and Commissioning Team together with the Homecare Procurement Officers is to ensure best value, contract compliance, quality of services and customer satisfaction. This will support Community Services to commission quality Care at Home services via the formal procurement and commissioning procedures.
3. DETAIL
OUTCOME OF TENDER
Within the Bute and Cowal locality, almost 70% of the service has historically been provided by the independent sector. The three providers successful in the framework in Cowal are Care UK, Allied and Carr Gomm. A separate framework contract was awarded on Bute and the providers are Allied, Carr Gomm and Carewatch. 3.5 FTE Homecare Procurement Officers are now in post to ensure the robust review/monitoring of the services to ensure a high quality is maintained.
A condition of the tendering exercise was that all services within the framework would have an electronic call monitoring system to log visits to service users which would minimise missed/late visits and allow the Council to monitor continuity of care. These are now all in place, and operational. This will enhance the service monitoring visits carried out by the Homecare Procurement Officers due to the reports provided by these systems
CARE AT HOME PROVISION
As at 31st December 2013 an approximate total of 1867 hours are being provided to 235 older people within the Cowal area by external providers. A breakdown of the provision is detailed in the table below:
COWAL
Providers on Framework from tender Weekly hours commissioned exercise
Hours at Hours at 31st Dec 30th Sept 1st preferred Care UK 553 617 provider 2nd Allied 384 439 preferred provider 3rd Carr Gomm 73 86 preferred provider
Weekly Hours Existing Providers Commissioned Hours at 30th Hours at sept 31st Dec Mears Care 382 380 Cowal Carers 273 345 Total Hours 655 725 Direct Payments 110 110 Total Hours 765 835
As at 31st December 2013 an approximate total of 2321 hours are being provided to 164 Older People within the Bute area by external providers. A breakdown of the provision is detailed in the table below: BUTE
Providers on Framework from tender Weekly hours exercise commissioned
Hours at Hours at 30th Sept 31st Dec 1st Allied 1289 1387 preferred provider 2nd Carr Gomm 49 77 preferred provider 3rd Carewatch 82 82 preferred provider
Weekly Hours Existing Providers Commissioned Hours at 30th Hours at 31st Sept Dec Care Plus 884 775 Total Hours 884 775 Direct Payment 14 14 Total Hours 898 789
Staff recruitment is an on-going issue in Cowal. This issue is not new to this locality, due to the rural areas involved, however it means the Council continues to purchase services off contract to meet demand. Recruitment is an on-going problem we are facing across the Council area and the Procurement and Commissioning Team, Adult Services and the Independent Providers are working in partnership to identify alternative ways to attract people into the sector. CONTRACT MANAGEMENT PROCESS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.