The main purpose of this report is to advise Members of the roads revenue budget position for the 3rd Quarter of financial year 2014/15.
The overall roads maintenance budget for the 2014/15 year (excluding winter maintenance and coastal protection) is £4,145,227. Spend at the end of the third quarter of the financial year is £3,133,803; this equates to a 76% spend, with 24% remaining for the last quarter of the financial year.
Spend to date in Bute and Cowal is £640,085 against an overall budget for the Area of £871,752 i.e. 73% spend to date.
That the Committee notes this report.
1 ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 3 FEBRUARY 2014
ROADS REVENUE BUDGET 2014 TO 2015 – 3rd QUARTER UPDATE
2.1This report is the third of four reports which will provide Members with information on road maintenance revenue activities being delivered in 2014/15.
3.1That the Committee notes this report.
4.0DETAILS
4.1Members were presented with four reports for each quarter of the 2013 to 2014 financial year which provided information on the roads maintenance revenue budget. This third, of four reports in the series, provides financial information on roads maintenance spend for the third quarter of the 2014 to 2015 financial year.
4.2The table at Appendix 1a) provides details of spend in the Bute and Cowal Area. Actual costs to date are provided, along with spend for the 2nd and 3rd quarters, to allow comparisons to be made between the two periods. This table indicates that, for an overall budget for the Area of £871,752, spend to date is £640,085 i.e. 73% spend to date. Appendix 1b), indicates the overall roads revenue maintenance budget for each area; the total roads maintenance budget for the 2014/15 year (excluding winter maintenance and coastal protection) is £4,145,227 as indicated in the table.
4.3Appendix 1c) provides information on percentage spend for all areas. The spend for Cowal is currently at 64% whist the Bute spend is 100% spend. Overall, the spend sits comfortably at 73%. Clearly, funding will require to be transferred from the Cowal budget to the Bute budget – the figure for transfer is £50,000 to ensure that revenue maintenance commitments on the island can be met. The capital allocation this financial year is £357,000 for Bute and £1,008,000 for Cowal. This split is based on need, as identified by the prioritisation system. The level of capital investment in Cowal also enabled a contribution from the Timber Transport Group of some £800,000 which has enabled a significant upgrade of the trans-Cowal Glen Lean route, benefiting both Bute and Cowal residents/business who travel between Bute and Dunoon. The additional capital spend on Cowal has removed the need for some reactive maintenance funding allowing a nominal revenue transfer to be made to Bute from the Cowal budget.
4.4In Appendix 1d) the budget spent for each activity has been divided by the estimated unit rate for that activity to give the amount of work that would be expected to have been achieved within that budget spend. In future, actual quantities of works carried out in each area will be correlated with costs to provide average unit rates for each area.
2 4.5 Appendix 1e) shows graphically how some of the main work activities have progressed in the first quarter of the year in financial terms. Budget profiles are set for each budget line and are used to manage actual expenditure against available budget. Graphs show ‘target’ spend versus ‘actual and re-profiled’ spend. The last two graphs indicate the overall position.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROADS REVENUE BUDGET 2014 TO 2015: FQ3Report | 578 KB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.