What the committee will consider, in order, with every paper attached to its item.
1
Procedure
The Chair ruled, and the Committee agreed, to consider an
urgent recommendation from Bute and Cowal Area Committee in respect of the refurbishment of Castle Lodge Gate House as Capital Funding may be required which would require a recommendation from the Policy and Resources Committee to the April Council meeting when the Capital Programme will be considered. This report is dealt with at item 17 of this Minute. The Chair ruled, and the Committee agreed, to consider...
1
Procedure
APOLOGIES FOR ABSENCE
2
Procedure
DECLARATIONS OF INTEREST
3
Report
MINUTES
Policy and Resources Committee held on 5 February 2015
Reports by Head of Strategic Finance Revenue Budget Monitoring Report as at 31 January 2015 Monitoring of 1% Savings for 2014-15 and 2015-16 Monitoring of Financial Risks Reserves and Balances Capital Plan Monitoring Report as at 31 January 2015 Treasury Monitoring Report as at 31 January 2015
Decision: Decision The Committee noted the – 1. R evenue budget monitoring report as at 31 January 2015 2. Progress towards the 1% savings target for 2014-15 and 2015-16 and approved the policy option referenced EDUC07. 3. Current assessment of the Council’s financial risks. 4. Overall level of reserves and balances and note the monitoring of the earmarked reserves. 5. Change in profiles as noted in paragraphs 3.3.6 to 3.3.11 in the reserves and balances report. 6. Capital plan monitoring report as at 31... Decision page
ReportFINANCIAL MONITORING PACK AS AT 31 JANUARY 20154.5 MBDownload
5
Report
PERFORMANCE REPORT FQ3 2014-15
Report by Executive Director – Customer Services
Decision: Decision The Committee noted the performance information for financial quarter 3 2014/15. (Reference: Report by Executive Director – Customer Services dated March 2015; Financial Quarter 3 Performance Report and Scorecard – Customer Services; and Financial Quarter 3 Performance Report and Scorecard – Strategic Finance) Decision page
ARGYLL AND BUTE COUNCIL EQUALITIES MAINSTREAMING REPORT AND PROGRESS ON EQUALITY OUTCOMES 2015
Report by Executive Director – Customer Services
Decision: Decision The Committee – 1. Noted that the content of the report meets the requirement of the Act. 2. Noted the positive progress being made by the Council to deliver on the Equality Outcomes. 3. Noted that the Council operates an equal pay environment. (Reference: Report by Executive Director – Customer Services dated March 2015, submitted) * Decision page
Decision: Decision The Committee – 1. Noted the rationale for amending the Policy. 2. Noted that the revised Policy has been discussed with the Trade Unions. 3. Approved the revised Policy. 4. Referred the Policy to Council for noting the revisions. Having moved an Amendment which failed to find a seconder, Councillor James Robb required his dissent from the foregoing decision to be recorded. (Reference: Report by Executive Director – Customer Services dated February 2015, submitted) Decision page
ReportREVISED REDUNDANCY POLICY AND PROCEDURES65 KBDownload
ReportRedundancy Policy and procedure version 2 June 2014115 KBDownload
8
Report
INFORMATION MANAGEMENT STRATEGY
Report by Executive Director – Customer Services
Decision: Decision The Committee approved the draft Information Management Strategy for Argyll and Bute Council. (Reference: Report by Executive Director – Customer Services dated 5 February 2015, submitted) Decision page
Decision: Decision 1. Noted the results of the customer consultation attached at Appendix 1 to the report by the Executive Director. 2. Considered the draft 2015-2019 Customer Service Strategy including revised Customer Service Charter and associated action plan attached at Appendix 2 to the report by the Executive Director and approved this. 3. Approved the outline business case for replacement customer contact systems attached at Appendix 3 to the report by the Executive Director and associated revenue... Decision page
Report2015: 2019 CUSTOMER SERVICE STRATEGY114 KBDownload
AppendixCS Strategy 2015-19 v 1.1 Appendix 2 P&R Mar 2015306 KBDownload
AppendixCS Strategy Appendix 1 P&R Feb 2015322 KBDownload
AppendixCS Strategy Appendix 3 (OBC 2.2) P&R Mar 2015236 KBDownload
10
Report
SCOTTISH GOVERNMENT FUNDING FOR WELFARE REFORM AND DISCRETIONARY HOUSING PAYMENTS - REPORT ON SPEND TO DATE AND FUTURE PROPOSALS
Report by Executive Director – Customer Services
Decision: Decision The Committee – 1. Noted the information provided in respect of progress made, and the estimate of projected expenditure to 31 March 2015 of £138.7k from the balance of Scottish Government funding for DHPs of £550,390 received in March 2014. 2. Approved the continued carry forward of the balance of this as earmarked funds estimated at £411.7k and approved the proposals for their use as summarised at paragraph 4.20 of the report by the Executive Director. 3. Approved the carry forward... Decision page
ReportSCOTTISH GOVERNMENT FUNDING FOR WELFARE REFORM AND DISCRETIONARY HOUSING PAYMENTS: REPORT ON SPEND TO DATE AND FUTURE PROPOSALS103 KBDownload
12
Procedure
Having previously declared an interest in the following item,
Councillor Alistair MacDougall left the room.
11
Report
COUNCIL TAX ON EMPTY PROPERTIES
View the declarations of interest for item 11. Report by Executive Director – Customer Services
Decision: Decision The Committee – 1. Noted the decision by the Valuation Appeal Committee on 10 December 2014 attached at Appendix 1 to the report by the Executive Director. 2. Approved an amendment to the policy for charging double council tax on long term empty properties so that where major repairs are underway which require planning permission and/or building warrant, the double charge is only applied after a property has been empty for 2 years. (Reference: Report by Executive Director – Customer... Decision page
ReportCOUNCIL TAX ON EMPTY PROPERTIES200 KBDownload
14
Procedure
Councillor MacDougall returned to the meeting.
12
Report
COUNTER FRAUD TEAM - BUSINESS CASE
Report by Executive Director – Customer Services
Decision: Decision 1. Noted the residual responsibilities for preventing and detecting fraud following the transfer to Single Fraud Investigation Service. 2. Approved the formation of a new Counter Fraud Investigation Team from 1 October 2015 within existing budgetary resources. (Reference: Report by Executive Director – Customer Services dated 5 February 2015, submitted) Decision page
ReportCOUNTER FRAUD TEAM: BUSINESS CASE180 KBDownload
13
Report
DIRECT PAYMENTS POLICY AND PROCEDURAL GUIDANCE FOR STAFF AND MANAGERS 2014
Report by Executive Director – Community Services
Decision: Decision The Committee approved the changes to the Direct Payment Policy and Procedures which reflected new regulations. (Reference: Report by Executive Director – Community Services dated 14 October 2014, submitted) Decision page
ReportDIRECT PAYMENTS POLICY AND PROCEDURAL GUIDANCE FOR STAFF AND MANAGERS 201482 KBDownload
AppendixDP Policy and Guidance: App 1770 KBDownload
14
Report
MEMBERSHIP OF THE PROPOSED SCOTTISH LOCAL AUTHORITY BUSINESS LOAN FUND
Report by Executive Director – Development and Infrastructure Services
Decision: Decision The Committee – 1. Endorsed the proposal to join the Scottish Local Authority Business Loan Fund. 2. Confirmed approval for Argyll and Bute’s allocation of funds within the West of Scotland Loan Fund (currently £183,702) to be transferred to the Scottish Local Authority Business Loan Fund. 3. Endorsed the estimated demand for loans over the initial three year period at £300k. (Reference: Report by Executive Director – Development and Infrastructure Services dated March 2015, submitted) Decision page
ReportMEMBERSHIP OF THE PROPOSED SCOTTISH LOCAL AUTHORITY BUSINESS LOAN FUND107 KBDownload
15
Procedure
ASSESSMENT PROCESS FOR ADDITIONAL FUNDING REQUESTED AS PART OF REVENUE BUDGET 2015/16
15a
Report
Assessment Process for Additional Funding
Report by Head of Strategic Finance
Decision: Decision The Committee – 1. Agreed the proposed process for assessing ad hoc funding requests subject to the first sentence of paragraph 11 of Appendix 1 to the report being amended to read “SMT submit report in the political process reporting through Policy Leads and to the Policy and Resources Committee for a decision. 2. Agreed that should any of these funding requests be agreed following assessment that the Committee identify how the cost can be contained within available resources to avoid... Decision page
ReportAssessment Process for Additional Funding80 KBDownload
15b
Report
Assessment of External Financial Request - Kilmartin Museum
View the declarations of interest for item 15b Report by Executive Director – Development and Infrastructure Services (Copies of the Business Case will be made available for Elected Members’ perusal in the Members Room)
Decision: Decision The Committee – 1. Noted the assessment of the project and associated business plan by Officers. 2. Agreed to support in principle the request for a maximum of £400,000 subject to i. A successful stage 1 application to HLF ii. A further detailed assessment of the Full Business Case as set out in the report entitled “Request for Grant Funding” also before this Committee, in advance of the stage 2 submission to HLF and that this business case fully meets the Council’s own criteria iii.... Decision page
ReportAssessment of External Financial Request: Kilmartin Museum121 KBDownload
21
Procedure
Councillor Vivien Dance left the meeting at this point.
16
Report
POLICY AND RESOURCES COMMITTEE WORKPLAN
Report by Executive Director – Customer Services
Decision: Decision Noted the outline work plan and agreed that the frequency of when the Financial Reporting packs are brought to the Committee should be reviewed. (Reference: Report by Executive Director – Customer Services dated March 2015, submitted) Decision page
ReportPOLICY AND RESOURCES COMMITTEE WORKPLAN64 KBDownload
23
Procedure
Councillor Rory Colville left the meeting at this point.
17
Report
CASTLE LODGE GATE HOUSE
Decision: Decision Agreed to refer this proposal for consideration by Council in April as part of the Capital Budget setting process and noted that the Executive Director – Development and Infrastructure will draw up costs for this Project to feed into the Capital Programme process. (Reference: Extract from Minutes of Bute and Cowal Area Committee of 3 February 2015, tabled) Decision page
Decision: Decision The Committee – 1. Approved the drawdown of borrowing for a total of £238,100 for the development of a Full Business Case for Lorn Arc Project 1 – Lorn Road/Kirk Road Improvements at Dunbeg noting that these resources will be held in a defined budget and managed as detailed in the Lorn Arc Programme PID. 2. Noted the Full Business Case for Project 1 will be reported to a future Oban, Lorn and the Isles Area Committee and subsequent Policy and Resources Committee before moving to the...
ReportProject 1 Lorn Road Kirk Road Dunbeg start up P & R committee report 23-02-15 v2.183 KBDownload
27
Exempt parts
The Committee
resolved in terms of Section 50(A)(4) of the Local Government (Scotland) Act 1973 to exclude the public for the following 4 items of business on the grounds that they were likely to involve the disclosure of exempt information as defined in Paragraphs 8; 8; 8 and 9; and 6 respectively of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. E2
19
Procedure
MAJOR CAPITAL REGENERATION PROJECTS - UPDATE REPORT AS AT 20 FEBRUARY 2015
Report by Executive Director – Development and Infrastructure Services
Decision: Decision The Committee – 1. Noted the current progress and agreed allocation of budget resources to date against each of the major capital regeneration projects. 2. Instructed Officers to bring progress reports to the Policy and Resources Committee on a quarterly basis. 3. Approved the Business Case (Interim Use) for Phase 1 works in respect of the Wooden Pier and the draw down of the remaining element of Argyll and Bute Council capital funds from the projects budget. 4. Agreed the terms of...
20
Procedure
NEW SCHOOLS REDEVELOPMENT PROJECT- CAMPBELTOWN, OBAN, KIRN, DUNOON
Report by Executive Director – Community Services (A3 copies of the associated appendices will be available for Elected Members’ perusal in the Members Room. Members may also request a copy to be emailed to them on a confidential basis through Committee Services)
Decision: Decision The Committee agreed the recommendations detailed in both reports. (Reference: Report by Executive Director – Community Services dated 23 February 2015, submitted and Report by Executive Director – Community Services dated 19 March 2015, tabled) E4
21
Procedure
HELENSBURGH OFFICE PROJECT UPDATE
Report by Executive Director – Customer Services
Decision: Decision The Committee agreed the recommendations detailed in the report. (Reference: Report by Executive Director – Customer Services dated 11 February 2015, submitted) E5
22
Procedure
COASTAL EROSION AT FURNACE
Report by Executive Director – Development and Infrastructure Services
Decision: Decision The Committee agreed the recommendations detailed in the report. (Reference: Joint report by Executive Director – Community Services and Executive Director – Development and Infrastructure Services dated January 2015, submitted)
32
Procedure
E1&E4 Paragraph 8 The amount of any expenditure proposed
E1&E4 Paragraph 8 The amount of any expenditure proposed to be incurred by the authority under any particular contract for the acquisition of property or the supply of goods or services.
33
Procedure
Paragraph 9 Any terms proposed or to be proposed by
Paragraph 9 Any terms proposed or to be proposed by or to the authority in the course of negotiations for a contract for the acquisition or disposal of property or the supply of goods or services.
34
Procedure
E2&E3 Paragraph 8 The amount of any expenditure proposed
E2&E3 Paragraph 8 The amount of any expenditure proposed to be incurred by the authority under any particular contract for the acquisition of property or the supply of goods or services.
35
Procedure
E5 Paragraph 6 Information relating to the financial
E5 Paragraph 6 Information relating to the financial or business affairs of any particular person (other than the authority).
Read inside all 24 papersPro opens every page, searches every appendix, and keeps the papers if the council removes them.
All 24 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
ARGYLL AND BUTE COUNCIL EQUALITIES MAINSTREAMING REPORT AND PROGRESS ON EQUALITY OUTCOMES 2015Item 6, ARGYLL AND BUTE COUNCIL EQUALITIES MAINSTREAMING REPORT AND PROGRESS ON EQUALITY OUTCOMES 2015
SCOTTISH GOVERNMENT FUNDING FOR WELFARE REFORM AND DISCRETIONARY HOUSING PAYMENTS: REPORT ON SPEND TO DATE AND FUTURE PROPOSALSItem 10, SCOTTISH GOVERNMENT FUNDING FOR WELFARE REFORM AND DISCRETIONARY HOUSING PAYMENTS - REPORT ON SPEND TO DATE AND FUTURE PROPOSALS
DIRECT PAYMENTS POLICY AND PROCEDURAL GUIDANCE FOR STAFF AND MANAGERS 2014Item 13, DIRECT PAYMENTS POLICY AND PROCEDURAL GUIDANCE FOR STAFF AND MANAGERS 2014
The committee last met on 5 February 2015. 5 of its items lead into this meeting; 12 items are new. Point at any item to follow a thread. Procedural items are left out.
MINUTESPolicy and Resources Committee 18 December 2014
4
STRATEGIC RISK REGISTER - 6 MONTHLY REVIEWReport by Head of Strategic Finance
5a
Pack 1 Service Plans
5b
Pack 2 Revenue BudgetSection A – Introductory Report and Recommendations for Budget papers...
6
TREASURY MANAGEMENT STRATEGY STATEMENT AND ANNUAL INVESTMENT STRATEGYReport by Head of Strategic Finance
7
EXECUTIVE SUMMARY AND INTRODUCTORY REPORT - FINANCIAL REPORT MONITORING PACK - DECEMBER 2014Report by Head of Strategic Finance Revenue Budget Monitoring Report...
8
REVIEW OF ALL WEATHER PITCH CHARGESView the declarations of interest for item 8. Report by Executive...
9
AUDIT SCOTLAND/ACCOUNTS COMMISSION ACTION PLAN UPDATEReport by Executive Director – Customer Services
10
POLICY AND RESOURCES COMMITTEE WORK PLAN 2014 - 15Report by Executive Director – Customer Services
11
REVIEW OF THE ARGYLL AND BUTE GUIDANCE ON COMMUNITY BENEFITS FROM ONSHORE RENEWABLE ENERGYReport by Executive Director – Development and Infrastructure Services
12
DIGITAL INFRASTRUCTURE UPDATEReport by Executive Director – Development and Infrastructure Services
13
LORN ARC TAX INCREMENTAL FINANCING (TIF) ASSET PROJECT 9 - EXISTING ACCESS IMPROVEMENTS AND BUSINESS PARK ENABLEMENT, OBAN AIRPORT START UP PROJECT
3
MINUTESNew this time
4
FINANCIAL MONITORING PACK AS AT 31 JANUARY 2015Reports by Head of Strategic Finance Revenue Budget Monitoring Report...
5
PERFORMANCE REPORT FQ3 2014-15New this time
6
ARGYLL AND BUTE COUNCIL EQUALITIES MAINSTREAMING REPORT AND PROGRESS ON EQUALITY OUTCOMES 2015Report by Executive Director – Customer Services
7
REVISED REDUNDANCY POLICY AND PROCEDURESNew this time
8
INFORMATION MANAGEMENT STRATEGYReport by Executive Director – Customer Services
9
2015 - 2019 CUSTOMER SERVICE STRATEGYReport by Executive Director – Customer Services
10
SCOTTISH GOVERNMENT FUNDING FOR WELFARE REFORM AND DISCRETIONARY HOUSING PAYMENTS - REPORT ON SPEND TO DATE AND FUTURE PROPOSALSNew this time
11
COUNCIL TAX ON EMPTY PROPERTIESNew this time
12
COUNTER FRAUD TEAM - BUSINESS CASENew this time
13
DIRECT PAYMENTS POLICY AND PROCEDURAL GUIDANCE FOR STAFF AND MANAGERS 2014New this time
14
MEMBERSHIP OF THE PROPOSED SCOTTISH LOCAL AUTHORITY BUSINESS LOAN FUNDNew this time
15a
Assessment Process for Additional FundingNew this time
15b
Assessment of External Financial Request - Kilmartin MuseumNew this time
16
POLICY AND RESOURCES COMMITTEE WORKPLANReport by Executive Director – Customer Services
TREASURY MANAGEMENT STRATEGY STATEMENT AND ANNUAL INVESTMENT STRATEGY leads to item 8, INFORMATION MANAGEMENT STRATEGY
TREASURY MANAGEMENT STRATEGY STATEMENT AND ANNUAL INVESTMENT STRATEGY leads to item 9, 2015 - 2019 CUSTOMER SERVICE STRATEGY
EXECUTIVE SUMMARY AND INTRODUCTORY REPORT - FINANCIAL REPORT MONITORING PACK - DECEMBER 2014 leads to item 4, FINANCIAL MONITORING PACK AS AT 31 JANUARY 2015
POLICY AND RESOURCES COMMITTEE WORK PLAN 2014 - 15 leads to item 16, POLICY AND RESOURCES COMMITTEE WORKPLAN
REVIEW OF THE ARGYLL AND BUTE GUIDANCE ON COMMUNITY BENEFITS FROM ONSHORE RENEWABLE ENERGY leads to item 6, ARGYLL AND BUTE COUNCIL EQUALITIES MAINSTREAMING REPORT AND PROGRESS ON EQUALITY OUTCOMES 2015
REVIEW OF THE ARGYLL AND BUTE GUIDANCE ON COMMUNITY BENEFITS FROM ONSHORE RENEWABLE ENERGY leads to item 8, INFORMATION MANAGEMENT STRATEGY
LORN ARC TAX INCREMENTAL FINANCING (TIF) ASSET PROJECT 9 - EXISTING ACCESS IMPROVEMENTS AND BUSINESS PARK ENABLEMENT, OBAN AIRPORT START UP PROJECT leads to item 18, LORN ARC TAX INCREMENTAL FINANCING (TIF) ASSET PROJECT 1 - LORN ROAD/KIRK ROAD IMPROVEMENTS - DUNBEG START UP REPORT
Not carried over
STRATEGIC RISK REGISTER - 6 MONTHLY REVIEW, Pack 1 Service Plans, Pack 2 Revenue Budget, REVIEW OF ALL WEATHER PITCH CHARGES and 2 more do not return this time.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
What should we tell you?
Argyll and Bute, Policy and Resources Committee
Policy and Resources Committee: 3 kinds of updateArgyll and Bute, sent the same day
PDF
24 papers published for 19 MarchFINANCIAL MONITORING PACK AS AT 31 JANUARY 2015 and 23 more papers
DAT
Meeting dates updatedAny date added, moved or dropped
DEC
Decisions from 19 MarchThe committee's resolutions, the day they are recorded
ABC
"financial" found in 2 papersFINANCIAL MONITORING PACK AS AT 31 JANUARY 2015 and Assessment of External Financial Request: Kilmartin Museum
Each update links to the paper and the council's own copy
// POST to your endpoint, signed, the moment it happens
{
"event": "papers.published",
"council": "argyll-and-bute",
"committee": "Policy and Resources Committee",
"meeting": "2015-03-19",
"papers": 24,
"items": 35,
"source": "www.argyll-bute.gov.uk"
}
Free: one weekly alert. Pro: every option, the same day. Pro Plus: straight into your own systems.
PlanProPrice£99 per user a monthStartsToday, full access straight away
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.