Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Contracts Manager dated 2 February 2016, submitted)
Bute and Cowal Area Committee noted this item on Tuesday 2 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Contracts Manager dated 2 February 2016, submitted)
1.1The purpose of this report is to advise Members of the roads revenue budget position at the end of the 3rd Quarter of financial year 2015/16.
1.22015/16 Budget - The overall roads maintenance budget for the 2015/16 year (excluding winter maintenance and coastal protection) is £3,912,226. The roads maintenance budget for the 2015/16 year (excluding winter maintenance, coastal protection and centrally allocated budgets) for the Bute and Cowal Area only, is £835,987, of which, £557,800 has been spent at the end of the 3rd Quarter – or 67%
1 ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 02 FEBRUARY 2016
ROADS REVENUE BUDGET - 2015 to 2016 – 3rd QUARTER UPDATE
2.1This report follows-on from the report presented earlier in the year at the December Area Committee, which provided information on road maintenance revenue activities being delivered in Q2 2015/16
3.1That the Committee notes this report.
4.0DETAILS
The Roads Operations Budget is proposed in line with the Roads Maintenance and Management Strategy and the Roads Maintenance and Asset Management Plan (RAMP). The available revenue budget is currently insufficient to allow all of the required works to be fully undertaken.
Roads revenue expenditure is closely monitored by separating types of work into different ‘activities’. This report is based solely upon financial information which has been collated through the ‘Total’ costing system. Budgetary figures provided in the Appendices to this report represent spends to the end of Q3 for the present financial year. Winter maintenance and coastal protection costs have been excluded from this report.
Appendix 1 shows the overall roads revenue maintenance budget for 2015 to 2016 for each area. The overall roads maintenance budget for the 2015/16 year (excluding winter maintenance and coastal protection) was £3,912,227 as indicated in the table.
Appendix 2 provides information on percentage spend at the end of Q3for 2015 / 16 for each area
Appendix 3 shows spend at the end of Q3 for all activities in the Bute and Cowal 2015/16.
Appendix 4 shows graphically Bute budget profiles. Profiles are set for each budget line and are used to manage actual expenditure against available budget. Appropriate action has been taken over the financial year to achieve a level of satisfactory performance, whilst ensuring that we work within the available budget. Graphs show ‘target’ spend versus ‘actual’ spend.
Appendix 5 shows graphically Cowal budget profiles. Profiles are set for each budget line and are used to manage actual expenditure against available budget. Appropriate action has been taken over the financial year to achieve a level of satisfactory performance, whilst 2 ensuring that we work within the available budget. Graphs show ‘target’ spend versus ‘actual’ spend.
5.0CONCLUSION
This report provides Members with a financial update on the roads revenue maintenance budget for Bute and Cowal at the end of Q3 2015/16. It indicates that 67% of the roads maintenance revenue budget has been spent and that spending profiles - that is actual spend v’s spend projections are reasonably aligned in Bute and Cowal. Squads in the Cowal domain are currently working on an externally funded project (Sustrans) – construction of new footway at Dalinlongart Sandbank but regular cyclic maintenance, house - keeping activities and reactive maintenance issues will ensure that we are on track to spend the revenue Budget in Bute and Cowal.
Further quarterly reports will continue to be presented to Members at future Area Committees.
6.0IMPLICATIONS
6.1Policy Works assessed and carried out under the current Roads Asset Management and Maintenance Plan.
6.2Financial The available Roads revenue budget is below that required in terms of the RAMP.
6.3Legal None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UPDATE ON DELIVERY OF ROADS REVENUE BUDGETReport | 246 KB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.