Resolved
Decision The Committee noted the report. (Ref: Report by Head of Facility Services, dated 25 February 2016, submitted)
Performance Review and Scrutiny Committee noted this item on Thursday 25 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the report. (Ref: Report by Head of Facility Services, dated 25 February 2016, submitted)
1.1As part of the programme of continuous improvement the Strategic Asset Management Board carries out post completion reviews of capital projects to look for good practice which can be replicated across project delivery as well as aspects of delivery which could be improved.
1.2This report summarises the findings and lessons learned from carrying out reviews of capital projects which completed during 2014-15. ARGYLL AND BUTE COUNCIL PERFORMANCE REVIEW AND SCRUTINY COMMITTEE STRATEGIC ASSET MANAGEMENT 25 FEBRUARY 2015 BOARD
POST COMPLETION REVIEWS AND LESSONS LEARNED
2. INTRODUCTION
2.1As part of the programme of continuous improvement the Strategic Asset Management Board carries out post completion reviews of capital projects to:
Identify good practice Identify areas for improvement
2.2The purpose of this report set out the learning points identified by the reviews.
3.1To note the contents of the report.
4. DETAIL
4.1The Audit Scotland report on Major Capital Investment in Councils recommended that Councils carried out post completion reviews of capital projects and reported the findings in conjunction with any lessons learned.
4.2In respect of capital projects completed during 2014-15 reviews were carried out which looked at project performance covering the following:
Completed on time Completed on budget Contractor Performance Lessons Learned
4.3In terms of asset sustainability projects these were considered at the programme level as that is how they are managed with any learning points being identified. In respect of service development and strategic change projects each project was looked at individually with a template being completed.
4.4The key findings from the reviews undertaken were that in general projects were completed on time. There were variations between budgets and actuals at individual project level, but the overall programme, in terms of asset sustainability projects was managed to deal with these variations. The overall performance of contractors was good, but there were instances of poor performance which should be addressed when selecting the contractor and this will in the future inform the Council’s Vendor Rating System. 4.5 The main lessons learned were that it is important to have communication, early agreement and engagement with clients. Collaborative working has been a success and areas of this type of working need to be communicated to all services. Consideration of programming a number of jobs at the same facility can lead to reductions in disruption to users of the facility and to reduced overall costs in respect of the projects. The Council purchased materials in respect of a number of jobs and this was beneficial in terms of the contract delivery.
4.6In terms of areas for improvement it was identified that there needs to be clear brief of the client’s requirements before proceeding with a contract. Where a number of areas of work were combined this led to benefits but added to the complexity of managing the programme of jobs. In respect of property works more detailed surveys should be considered to gain a better understanding of the work required which would assist with more accurate costing of the job.
4.7Appendix 1 illustrates the nature of the findings from the review how they will be addressed while appendix 2 shows details of project performance.
5. CONCLUSION
5.1The carrying out of the post completion reviews has highlighted a number of lessons which if implemented should result in improved performance in the delivery of future capital projects.
6. IMPLICATIONS 6.1 Policy – None 6.2 Financial - None 6.3 Legal - None. 6.4 HR - None 6.5 Equalities - None. 6.6 Risk - By applying the lessons learned this should reduce the risks associated with delivery of capital projects in the future. 6.7 Customer Service - None.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
POST COMPLETION REVIEW LESSONS LEARNEDAgenda | 314 KB | DownloadRead as text |
Follow Performance Review and Scrutiny Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Mar 2017 | Treasury management monitoring reportDecision The Committee noted the report. (Reference: Report by Head of Strategic Finance dated 3 March 2017, submitted) | Noted | Open |
| 3 Mar 2017 | Treasury management strategy statement and annual investment strategyDecision The Committee agreed to refer to Council; 1) the proposed Treasury Management Strategy Statement and Annual ... | Agreed | Open |
| 3 Mar 2017 | Quarterly performance reports and scorecardsDecision The Committee noted the contents of the report. (Reference: Report by Chief Executive dated 3 March 2017, su... | Noted | Open |
| 3 Mar 2017 | Maximising attendanceDecision The Committee noted; 1) the content of the report; and 2) the measures the Council has put in place to manag... | Noted | Open |
| 3 Mar 2017 | Succession planningDecision The Performance Review and Scrutiny Committee noted the presentation. (Reference: Presentation by Head of Im... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.