Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Contracts Manager dated 4 th April 2017, submitted).
Bute and Cowal Area Committee noted this item on Tuesday 4 April 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the contents of the report. (Ref: Report by Contracts Manager dated 4 th April 2017, submitted).
1.1The purpose of this report is to advise Members of the roads revenue budget position at the end of the 3rd Quarter of financial year 2016/17. It also provides a commentary of the main operational activities undertaken in the quarter.
1.22016/17 Budget - The overall roads maintenance budget for the 2016/17 year (excluding winter maintenance and coastal protection) is £3,972,055. The roads maintenance budget for the 2016/17 year (excluding winter maintenance, coastal protection and centrally allocated budgets) for the Bute and Cowal area, is £851,900. £666,641 has been spent at the end of the 3rd Quarter – 78%
1 ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 04 APRIL 2017
ROADS REVENUE BUDGET AND ROADS ACTIVITIES - 2016/17 – 3rd QUARTER UPDATE
2.1This report follows-on from the reports presented to earlier Area Committees and provides information on road maintenance revenue activities being delivered in Q3 2016/17.
3.1That the Committee notes this report.
4.0FINANCIAL POSITION
4.1The Roads Operations Budget is proposed in line with the Roads Maintenance and Management Strategy and the Roads Maintenance and Asset Management Plan (RAMP).
4.2Roads revenue expenditure is closely monitored by separating types of work into different ‘activities’. This report is based solely upon financial information which has been collated through the ‘Total’ costing system. Budgetary figures provided in the Appendices to this report represent spends to the end of Q3 for the present financial year. Winter maintenance and coastal protection costs have been excluded from this report.
4.3Appendix 1 provides information on percentage spend at the end of Q3 for 2016/17 – the Cowal and Bute Area is Highlighted in yellow
4.4Appendix 2 shows spend at the end of Q3 for all activities in the Bute and Cowal area this financial year 2016/17.
5.0OPERATIONAL ACTIVITIES THIS QUARTER
OCTOBER
Bute Ditching Potholing Drainage repairs Permanent Patching Rock Armour UC19 Coustonn Road (Coastal Protection)
2 Verge repairs Road sign repairs Culvert weekly checks Preparing, filling and installing grit bins Mount Stuart surfacing (Recharge to Hanson) Winter Maintenance
Cowal New layby at former Innellan shops Gerhallow street lighting Culvert weekly checks Gully emptying program Preparing, filling and installing grit bins Cromlech Road culvert inlet improvement Road signs installation Drainage investigation @ Creggans Ditching Lochgoilhead Supply 2 roadmen for Roadmaster in Helensburgh Winter Maintenance
NOVEMBER
Bute Drainage Boundary wall repairs Permanent patching Pothole patching CPC training Road signs and poles Ditching Culvert weekly checks Winter Maintenance
Cowal Permanent patching A880 Kilmun, C9 Ardentinny, B839, B828, C6 & Lochgoilhead Road markings Footway crossings Dunoon Drainage improvement Ardentinny Resurface Dalinlongart Landfill Access road (Recharge to Shanks) Rock Armour UC44 St Catherines Service Rd (Coastal Protection) Scrub cutting - A885 High Rd, A815 Bullwood Culvert weekly checks Gully repairs Hand Ditching Victoria Park surfacing (Recharge to MacLeods) Rankins Brae Culvert Replacement (A40 Flood Prevention) Hand Patching B8000 Winter Maintenance Alexander St drainage Safety inspection pothole patching Footway Patching
3 DECEMBER
Bute Scrub cutting Gully cleaning Seawall toe repairs Mount Stuart Rd (Coastal Protection) Culvert weekly checks Ditching Flooding clean up Drainage Winter Maintenance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROADS REVENUE BUDGET AND ROADS ACTIVITIES 2016/17: 3rd Quarter UpdateReport | 137 KB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.