Decision The Committee: 1. Noted the contents of the briefing paper and; 2. Agreed a press release highlighting the works being carried out by the Council to ensure continuity of service should be released by the Area Committee. (Ref: Briefing note by Marine Operations Manager dated 6 th March 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The Council has a maintenance contract in place with ‘Stannah Lift Services’ which was initiated in early 2008. Currently Stannah visit Rothesay six times per year to carry out maintenance checks; this includes any adjustment and lubrication of the lift mechanism.
2. Detail
Stannah and their sub-contractor ‘GF’ attended site at Rothesay Pier on several occasions, late last year and into this year, to address problems with both of the passenger lifts; one of the lifts became inoperative late last year and, whilst work was ongoing by Stannah and their sub-contractor to trace the fault and resolve the situation, the second lift developed faults in mid-January of this year. Council officers have liaised closely with Stannah to resolve this latest series of faults. Currently, one lift is back in operation. Until the hydraulic ram unit is replaced in the lift which is currently inoperative, this lift will remain out of service.
Annual maintenance costs over the last few years, including unforeseen costs due to breakdowns, are as detailed in the appendix to this report. Lift availability figures are also provided in the attached appendix. Figures indicate that maintenance costs have increased over recent years, whilst availability of the lifts has decreased – although current works planned should reverse this trend.
It is worth noting that the lifts at Rothesay are located in a challenging environment for this type of equipment (weather/tides etc), and similar problems are experienced by other harbour operators. It is understood that the Calmac lifts at Wemyss Bay have developed similar problems in the past - although details of historical break- downs are currently unavailable. 3. Future Actions
Stannah has, of late, advised that, although rams seals were replaced last year, the remaining lift now requires a complete replacement of the main hydraulic ram. Currently, marine staff are awaiting a quotation from Stannah (including a programme) for the replacement of hydraulic rams for both lifts. The hydraulic ram will be replaced on the lift, currently still in service, as a precautionary measure; this will improve service resilience and reduce the risk of future failures of the hydraulic mechanism. Programme details and likely costs will be made available to Members once received.
Stewart Clark Marine Operations Manager 01546 604893
22 February 2018
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.