Decision The Committee: 1. Noted the contents of the briefing paper. 2. Noted the actions being carried out by officers and; 3. Agreed an update report would be brought back to the June 2018 Bute and Cowal Area Committee meeting. (Ref: Briefing note by Traffic and Development Manager, dated 3 April 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL Bute & Cowal Special Area Committee
Development & Infrastructure Tuesday 3 April 2018
UC33 Auchenlochan Back Road Timber Transport Management Plan - Briefing
1.0Background to the Argyll Timber Transport Group and Timber Transport Management Plans
1.1The Argyll Timber Transport Group (ATTG) is a voluntary body supported by the timber industry, Forestry Commission and Local Authority as a means of minimising problems arising from timber haulage on public roads. The ATTG was formed in 1997 and meets at least twice per year. Agreements are made in a spirit of co-operation to sustain the network to allow access by the majority of users. The role of the ATTG has become particularly significant in recent years following extensive freeze/thaw damage suffered to the local road network during winter; which has highlighted the fragility of the roads and the need for timber traffic management to sustain the roads essential for access by the wider community. The ATTG has championed best practise and the use of technology such as central tyre inflation (CTI) which has resulted in local hauliers making considerable investments to their fleet with a view to sustaining the local road network.
1.2Where it is necessary to extract timber via a fragile public road, this is controlled by use of a Timber Traffic Management Plan (TTMP). The TTMP will normally include: Detail of the route; The lorry configuration (e.g. tyre type, CTI, trailer/cab type); Frequency of haulage; Seasonal and weather restrictions; Speed limits and requirement for drive awareness; Monitoring – this will include not only inspections by Council staff but also puts responsibility for reporting defects on other relevant parties (i.e. haulier, land owner).
1.3The TTMPs are voluntary agreements; they are not legally binding contracts, however; there are enforcement options open to both the ATTG and to the Council as an individual organisation. Through the ATTG; if a particular land owner or haulier, for example, consistently breached the TTMP the enforcement could be that they may not be granted future felling licences (by the Forestry Commission), or forestry companies may advise a Haulage Contractor that if they continued breaching a TTMP that they would not be awarded any future contracts. The Council could suspend the TTMP and warn that any future TTMP requests may not be granted.
In the event that the aforementioned informal approaches are unsuccessful then the Council, as the Roads Authority, could introduce a Traffic Regulation Order (TRO) on a route restricting vehicle width, vehicle length and maximum gross weight permitted. It should also be noted that if a public road is damaged due to use by HGVs, then costs can be recovered via the Roads (Scotland) Act 1984, s96. The TTMPs do not in any way prejudice the use of s96.
There are currently thirty-seven TTMPs in operation across the Argyll and Bute Council area; of which seven are for routes within Bute & Cowal.
1.4The timber industry is the only industry that have accepted control of their business activities by way of voluntary traffic management plans. It is worth noting that this is not done by farming (aqua or agri-cultural), quarries or any delivery company.
1.5The use of TTMPs has largely been a success within Argyll and Bute in protecting a sometimes fragile network. As a member of the ATTG, the Council has also been able to secure additional capital funding for road improvements through the Strategic Timber Transport Scheme. An example of one such successful scheme in Bute and Cowal is the B836 Glen Lean Improvements. Appendix 1 provides detail in regards to the project type and the success of Argyll as a whole in achieving project award. The table and graphs are from the Forestry Commissions “Strategic Timber Transport Fund Update Report April 2016”.
1.6The Argyll Timber Transport Group has representation by the following organisations:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.