Helensburgh & Lomond Area Committee approved this item on Thursday 21 June 2018. Below is the council's own wording, with the papers it was decided on.
Decision The Area Committee:- Approved the End Stage Report; Approved the submission of the formal planning application by the project team; Approved the commencement of the next stage of project development as set out in Section 8 of the Report; and Thanked the Officers for their enormous efforts and hard work in getting the Helensburgh Waterfront Project to this stage. (Ref: Report by Helensburgh Regeneration Project Manager dated 18 th June 2018, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Helensburgh Waterfront Development project is all about creating a vibrant and attractive waterfront for the town. The main feature of the project will be a new leisure facility incorporating a swimming pool, with associated parking and public realm works to meet the needs of the local community. At the same time the flood defences will be increased to address current flooding issues in the area. The new leisure facility will be run on behalf of the council by the newly formed trust LiveArgyll.
1.2The principle aims and objectives for the project are to:
Develop Helensburgh as a great place to live, work and visit, by delivering a new state-of-the-art leisure facility and swimming pool which meets the needs of the Helensburgh and Lomond community Add to what has been achieved through other projects such as CHORD and Hermitage Park regeneration, which have created an attractive, vibrant and contemporary town Centre that is attracting residents, businesses and visitors to the area. Encourage additional private sector investment in the waterfront area and town centre Through the steps above, support the Helensburgh and Lomond economy with increased opportunities for existing and new businesses
1.3This report provides a progress update on the delivery of the Helensburgh Waterfront Development Project, following the completion of the current stage of design development; and seeks the Committee’s approval to move the project forward by submitting a formal planning application in respect of the design proposals; and by commencing the next stage of project development.
1.4Project Programme and Milestones – the project remains on schedule to deliver a new operational leisure centre in July 2021, and to have completed the demolition of the existing leisure facility and the completion of all associated public realm works by December 2021.
1.5Design Development – key points of progress for the design development through this stage are listed below for the elements of the project, which are set out in the approved Helensburgh Pierhead Masterplan Addendum (HPMA) 2012, they are:
2 flood defence improvements public realm improvements reconfigured and adjusted car parking and bus/coach drop-off the provision of a new purpose built leisure centre, including swimming pool the demolition of the existing leisure centre building, subsequent to the new facility being brought into operation the safeguarding of specified areas for future developments, by others, including: retail; and landscaping / skate park / play park
1.6Public contribution. Feedback from local people has played a key part in developing the design for the new facilities. To reach this stage, we undertook a further round of public consultations, and targeted forums with key user groups and stakeholders. The designs are based on what people have said overall that they want, taking account of feasibility and cost e.g. providing catering facility, safeguarding an area for future development of facilities such as a skate park. We would like to thank everyone who took time to get involved and give their views.
1.7Costs / Funding – The project has a current budget of £18,181,080, including £5million awarded from the UK Government Libor Fund, as well as forecast funds arising from the future retail development within the northern end of the site. The current cost plan is challenging, but we consider it to be robust, with the costs for approximately 70% of the designed elements having already been subjected to market testing during this stage, and with the remainder of market testing on-going as the design develops further in the next stage. Within the current cost plan significant allowances have been made for Inflation, Risk and Contingency.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.