Resolved
Decision The Oban, Lorn and the Isles Area Community Planning Group agreed to note the information provided. (Ref: Report by Service Improvement Officer dated 8 May 2019, submitted)
Oban Lorn & the Isles Area Community Planning Group agreed this item on Wednesday 8 May 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Oban, Lorn and the Isles Area Community Planning Group agreed to note the information provided. (Ref: Report by Service Improvement Officer dated 8 May 2019, submitted)
Argyll and Bute Community Planning Partnership
Oban, Lorn and the Isles Area Community Planning Group
8th May 2019
Oban & Lorn Care Homes & Housing Update Report
The Eadar Glinn Project Group started meeting in Feb 2018 to develop plans for the replacement/re-provision of Eadar Glinn as outlined in the HSCP Quality & Finance Plan. At this stage this was a standalone project although there was a similar project in Mid Argyll for the replacement/re-provision of Ardfenaig.
In July 2018 John Dreghorn was appointed as Service Improvement Officer for Care Homes & Housing, and the Eadar Glinn Project became part of the wider Argyll & Bute Care Homes & Housing Project (A&B CH&H). As the local project was now wider that simply the re-provision of Eadar Glinn. It was renamed as the Oban & Lorn Care Homes & Housing Project.
The A&B CH&H project is split into 4 phases:
Phase 1: Review and profile current care home & housing services Phase 2: Needs Assessment, including the development of a care homes modelling tool Phase 3: Modelling Future Demand. Utilising the modelling tool and other relevant data. (see page 3) Phase 4: Planning for the Future. Using the outputs from phase 3 to plan future care home and extra care housing requirements producing a range of options for consideration
At the time writing this report we are well into phase 4 which includes a 2 stage community engagement process:
Stage 1: Inform and consult This stage involves a review of the long list of service delivery options developed by the project group. Community representatives are brought together in a workshop to review the options and eliminate those which do not meet the required service delivery criteria (see page 10). The format of the workshop combines SWOT analysis with a mini option appraisal scoring system. Based on the outputs from the workshop the Project Group will shortlist the options which will then be fully worked up for options appraisal. The Oban & Lorn workshop took place on 29th March 2019.
Stage 2: Engagement This stage includes one or more “conversation cafe” events at which the worked up shortlisted options will be presented and discussed with members of the public. Outputs from those discussions will be taken forward to a formal options appraisal workshop to assist in the appraisal process.
The ultimate aim of this project is to produce a single preferred option which meets the care home and specialist housing needs of the local older population, which can then go forward for approval and eventual implementation. The Oban & Lorn workshop took place on 29th March 2019 and was attended by 24 community representatives, including elected members, 3rd sector, voluntary orgs, independent providers, trade union and staff reps.
The following options were considered (see pages 4 - 9 for summary of each option):
1. Refurbishment of Eadar Glinn 2. New Care Home 3. Progressive Care Centre 4. Core & Cluster Development in Oban 5. Core & Cluster Developments in Oban and Lorn 6. West Argyll & Bute Care Home Re-provision
The outputs from the workshop are as follows:
Option 1: Scoring range of 10 - 33, with an overall average score of 21.3 (42.6%). This option had the 6th highest score
Option 2: Scoring range of 27 - 50, with an overall average score of 37.2 (74.6%). This option had the 3rd highest score
Option 3: Scoring range of 13 - 44, with an overall average score of 29.3 (58.6%). This option had the 4th highest score
Page 2 of 11 Option 4: Scoring range of 29 - 47, with an overall average score of 39.3 (78.6%). This option had the highest score (1st)
Option 5: Scoring range of 26 - 49, with an overall average score of 37.5 (75%). This option had the 2nd highest score
Option 6: Scoring range of 16 - 38, with an overall average score of 28.5 (57%). This option had the 5th highest score
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Eader Glinn UpdateReport | 194 KB | DownloadRead as text |
Follow Oban Lorn & the Isles Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Aug 2026 | Community focusDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Prese... | Noted | Open |
| 12 Aug 2026 | Argyll and bute improvement plan - priorities updateDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Prese... | Noted | Open |
| 12 Aug 2026 | Community planning partnership management committee meeting highlightsDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Repor... | Noted | Open |
| 12 Aug 2026 | Police Scotland UpdateDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Repor... | Noted | Open |
| 12 Aug 2026 | Scottish Fire and Rescue UpdateDecision The Oban, Lorn and the Isles Area Community Planning Group noted the information provided. (Reference: Repor... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.