The Argyll Islands Strategic Group agreed to note the details of this paper and the award of an interim contract to Hebridean Air Services Ltd covering the period 16 May 2019 until 15 September 2019. (Reference: Report by Executive Director of Development and Infrastructure Services, dated 28 May 2019, submitted.)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The current contract for the provision of Air Services between Oban and the Islands of Coll, Colonsay and Tiree is operated by Hebridean Air Services Ltd (HASL) on behalf of the Council at a cost of £720,756 per annum. This contract will expire on 15 May 2019.
1.2Following a non-compliant tender submission for the next Argyll Air Services Public Service Obligation (PSO) contract, the procurement had to be abandoned. Given the delay in securing a new operator there was a risk of a break in service from one contract finishing to the next starting.
1.3Following the Council’s budget decision of 18/19 the funding available for the new PSO contract is £512,207 per annum.
1.4An interim contract has been awarded to Hebridean Air Services Ltd for the provision of scheduled air services between Oban and the islands of Coll, Colonsay and Tiree covering the period of 16 May 2019-15 September 2019.
1.5The interim timetable includes commercial flights between Islay and Colonsay/Oban and scholar flights at the weekend term time.
1.6This funding is awarded under the Commission Regulation (EU) No 1407/2013 on the application of Articles 107 and 108 of the Treaty on the Functioning of the European Union to de minimis aid. Full details of the Regulation can be found at: http://ec.europa.eu/competition/state_aid/legislation/de_minimis_regulation_ en.pdf ARGYLL AND BUTE COUNCIL Argyll Islands Strategic Group
DEVELOPMENT AND 28 May 2018 INFRASTRUCTURE SERVICES
Update on Argyll Air Services
2.0INTRODUCTION
2.1The current contract for the provision of Air Services between Oban and the Islands of Coll, Colonsay and Tiree is operated by Hebridean Air Services Ltd (HASL) on behalf of the Council at a cost of £720,756 per annum. This contract will expire on 15 May 2019.
2.2Following a non-compliant tender submission for the next Argyll Air Services Public Service Obligation (PSO) contract, the procurement had to be abandoned. Given the delay in securing a new operator there was a risk of a break in service from one contract finishing to the next starting.
2.3An interim contract has been awarded to Hebridean Air Services Ltd for the provision of scheduled air services between Oban and the islands of Coll. Colonsay and Tiree covering the period of 16 May 2019-15 September 2019. The details of the amended timetable is enclosed in Appendix 1.
Recommendations
3.1It is recommended that Members consider
(i) The details of this paper and the award of an interim contract to Hebridean Air Services Ltd covering the period 16 May 2019 until 15 September 2019.
4.0DETAIL
4.1Following a non-compliant tender submission for the next four year Argyll Air Services Public Service Obligation (PSO) contract further engagement with market operators has taken place. This was to ensure that the second tender round included a contract and specification that was as attractive as possible to market operators.
4.2The deadline for submissions to the second tender was the 2 May 2019 and the procurement process for the four year PSO contract is now at the evaluation stage. 4.3 Given the delay in securing a new operator there was a risk of a break in service from one PSO contract finishing to the next PSO starting.
4.4An interim contract has been awarded to Hebridean Air Services Ltd for the provision of scheduled air services between Oban and the islands of Coll, Colonsay and Tiree covering the period of 16 May 2019-15 September 2019. The details of the amended timetable is enclosed in Appendix 1.
5.0CONCLUSION 5.1 The deadline for submissions to the second tender round was the 2 May 2019 and the procurement process for the four year PSO contract is now at the evaluation stage. An interim contract has been awarded to Hebridean Air Services Ltd for the provision of scheduled air services between Oban and the islands of Coll, Colonsay and Tiree covering the period of 16 May 2019-15 September 2019.
6.0IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Vessel Replacement and Deployment PlanThe Argyll Islands Strategic Group agreed to note the contents of the update. (Ref: Update by Transport Scotland, dat...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.