Resolved
Decision The Helensburgh and Lomond Area Committee noted the report. (Reference: Report by Executive Director of Development and Infrastructure Services dated May 2019, submitted)
Helensburgh & Lomond Area Committee noted this item on Thursday 20 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Helensburgh and Lomond Area Committee noted the report. (Reference: Report by Executive Director of Development and Infrastructure Services dated May 2019, submitted)
1.1Argyll and Bute Council are developing the waterfront at Helensburgh to replace the existing swimming pool and to provide environmental and amenity improvements in the area. Full planning permission is in place. The proposed Helensburgh Waterfront Development will have an impact on the current parking provision within the town centre both during construction and once the pool is operational.
1.2With the introduction of additional parking in Grant Street car park and on Station Road, together with other mitigation set out in the report, it is considered that there is sufficient parking capacity within Helensburgh to accommodate current parking demand during the construction phase (which will remove a number of parking spaces from the Pier Head to allow construction work to be carried out). It is also considered that there will be sufficient parking provision in the Town Centre once the waterfront development has been completed. This report provides detail of the existing provision and proposals to mitigate the impact of the development during the construction phase and post construction.
1.3Officers recommend that Members note that:
i. With the addition of Grant Street car park and further spaces on Station Road, the demand for parking can be met within the remaining town car parking capacity during the construction phase ii. and that parking demand and availability will be monitored during and post works. ARGYLL AND BUTE COUNCIL HELENSBURGH & LOMOND AREA COMMITTEE
DEVELOPMENT AND INFRASTRUCTURE SERVICES 20 JUNE 2019
HELENSBURGH WATERFRONT PROJECT
2.0INTRODUCTION
2.1This report provides Members with information on the proposed mitigation measures which are intended to address the parking issue, as far as practicable, during the Helensburgh Waterfront Development construction phase.
3.1Officers recommend that Members note that:
i. With the addition of Grant Street car park and further spaces on Station Road, the demand for parking can be met within the remaining town car parking capacity during the construction phase ii. and that parking demand and availability will be monitored during and post works.
4.0DETAIL
4.1The Council’s Planning Protective Services and Licensing Committee granted full planning permission, subject to conditions, for the Helensburgh Waterfront Development at its meeting held on the 23 January 2019. Condition 3 of the planning permission required that:
No development shall be commenced until the following plans and particulars have been submitted to and approved in writing by the Planning Authority in consultation with the Head of Roads and Amenity Services. Thereafter the development shall be implemented in accordance with the approved details. Such details shall incorporate:
(i) A detailed construction method statement including the construction phasing and the material delivery plan. (ii) The interim car parking arrangements to address the loss of existing parking provision during the construction phases. This report provides detail on the proposed interim parking arrangements during the construction phase.
4.2The current facility at the Pier Head has capacity to accommodate 336 car parking spaces and 9 coach/HGV bays. To support the planning application a report was prepared to consider the implications this reduction would have on Helensburgh as a whole.
4.3The following should be considered:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HELENSBURGH WATERFRONT PROJECTReport | 105 KB | DownloadRead as text |
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... | Noted | Open |
| 8 Sep 2026 | Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... | Noted | Open |
| 8 Sep 2026 | Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... | Noted | Open |
| 8 Sep 2026 | Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... | Noted | Open |
| 8 Sep 2026 | Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.