Argyll and Bute HSCP Integration Joint Board (IJB) noted this item on Wednesday 25 March 2020. Below is the council's own wording, with the papers it was decided on.
Decision The Integration Joint Board – 1. Noted the management/operational savings amounting to £4.157m approved by the IJB on 29 January 2020 in 2020-21. 2. Approved the changes to the Management & Operational savings set out at 3.2.4 to 3.2.5 amounting to £85k for 2020-21 and the revised list of savings now presented at Appendix 1 totalling £4.242m. 3. Approved the removal of previously agreed saving 1920-6 £25k relating to ferry ticketing as set out at 3.2.6. 4. Approved the policy savings at Appendix 2 amounting to £1.463m in 2020-21. 5. Approved the proposed investment in financial sustainability totalling £318k in 2020/21 and 2021/22 set at 3.3.8. 6. Noted that in endorsing the management/operational savings and approving the policy savings this will deliver a balanced budget in 2020-21. 7. Instructed the Chief Officer to accept the funding from NHS Highland and Argyll and Bute Council and issue formal Directions (see drafts at Appendix 3) delegating resources back to the Partners. 8. Noted the high level timetable for the budget preparation 2021-22 set out at 3.5.1. 9. Noted that there would be additional costs due to Covid-19, which should be recoverable from the Scottish Government, and that therefore the savings may need to be flexed accordingly. (Reference: Report by Head of Finance and Transformation dated March 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Argyll and Bute HSCP Integration Joint Board (IJB)
Executive summary
1.1This report presents savings proposals identified by the Strategic Leadership Team in order to deliver a balanced budget in 2020-21.
1.2There is a separate report on the agenda that details the budget outlook over the period 2020-21 to 2022-23. The budget gap in 2020-21 amounts to £5.362m.
1 1.3 Savings proposals have been classified into management/operational savings and policy savings. Management/operational savings proposals totalling £4.157m were approved by the IJB on 29 January 2020. This report proposes some amendments to these (amounting to £55k) and the new total of £4.212m is presented along with £1.493m of policy savings. It should be noted that a budget consultation has been carried out in respect of Policy savings proposals and there is a separate report on the agenda with the results of this consultation. The results of this consultation should be taken into account when making decisions on the policy savings. Equality Impact assessments (EQIAs) have been carried out for all the policy savings and there is a summary of these presented in a separate report on the agenda. Wherever possible, negative impacts have been mitigated but there are still some negative impacts which need to be considered when making decisions on these savings proposals.
1.4In addition a proposal is made for an investment in financial sustainability totalling £318k in 2020/21 and 2021/22.
1.5There is still a significant estimated budget gap over the next two years and work will need to commence immediately on identifying savings proposals to balance the budget in 2021-22. A high level timetable for the budget process 2021-22 is noted in the report.
2. INTRODUCTION
2.1This report presents savings proposals identified by the Strategic Leadership Team in order to deliver a balanced budget in 2020-21.
3. DETAIL OF REPORT
3.1Budget Outlook 2020-21 to 2022-23
3.1.1 There is a separate report on the agenda that details the budget outlook over the period 2020-21 to 2022-23. The budget gap in 2020-21 amounts to £5.362m.
3.1.2 The budget outlook for future years, has been prepared using three different scenarios, best case, worst case and mid-range. The budget gap over 2021-22 and 2022-23 across each scenario is summarised in the table below.
Budget Gap 2021-22 2022-23 Total £000 £000 £000 Best Case (361) 1,806 1,445 Mid-Range 5,136 5,282 10,418 Worst Case 11,139 9,550 20,689
3.2Savings Proposals
3.2.1 The Senior Leadership Team have been working over the last few months to identify savings to deliver a balanced budget in 2020-21. The IJB on 29 January 2020 approved certain management / operational savings, and
2 agreed to consult on identified policy savings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Argyll and Bute HSCP Integration Joint Board (IJB) at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.