Decision The Committee:- 1. Agreed to Option 2, that is to keep the current 35 public conveniences open until the end of October at an additional cost estimated to be £20,796 and then revert to only a core set that remain open that can be managed within the normal budget. The additional cost will be include within the in-year budget gap that will be considered by the informal working group. 2. Noted that the future provision of public conveniences will be part of the amenity services themed review and will be brought forward as part of the budget proposals. (Ref: Report by Interim Executive Director for Roads and Infrastructure dated 30 July 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1Following the national lockdown announcement at the end of March 2020, all Council operated public conveniences across the area were closed. Working with other local authorities, SCOTS, COSLA and the Scottish Government, national guidance was developed and published on 27 June and the Council agreed, following consultation with all area committees, a phased re-opening plan on 2 July.
1.2The Leadership Group asked for a report to be brought back to the Business Continuity Committee in August to further consider the approach to the remobilisation of public conveniences from 1 September.
1.3Of the 59 public conveniences, 3 were opened on 3 July, 11 were opened on 6 July and a further 21 were opened on 15 July. Calgary Bay public convenience in Mull has now been transferred over to Mull and Iona Community Trust and this leaves 23 that are closed. Further information is attached in Appendix 1.
1.4The additional expenditure for the remobilisation agreed up until 30 August is estimated to be £25,518. The ongoing cost to keep the existing arrangements in place is estimated to be £10,398 per month. It should be noted there will continue to be a reduction in other services such as street cleansing and grounds maintenance as some staff are being used from these services areas to support the enhanced cleaning.
1.5Officers have given consideration to 3 options for the provision of public conveniences for the remainder of this financial year and it is recommended that Members agree to Option 2 that is to continue to keep the current 35 public conveniences open until the end of October and then revert to only a core set that remain open that can be managed within the normal budget. Although this has a further additional cost of £20,796 it would ensure that there is a provision up until the end of the main tourism season. ARGYLL AND BUTE COUNCIL BUSINESS CONTINUITY COMMITTEE
ROADS AND INFRASTRUCTURE 13 AUGUST 2020
PUBLIC CONVENIENCES REMOBILISATION
2. INTRODUCTION
2.1Following the national lockdown announcement at the end of March 2020, all Council operated public conveniences across the area were closed. Working with other local authorities, SCOTS, COSLA and the Scottish Government, national guidance was developed and published on 27 June and the Council agreed, following consultation with all area committees, a phased re-opening plan (see Appendix 1) on 2 July.
2.2The Leadership Group asked for a report to be brought back to the Business Continuity Committee in August to further consider the approach to the remobilisation of public conveniences from 1 September.
Recommendation
3.1The Business Continuity Committee are asked to:
a) Agree to Option 2, that is to continue to keep the current 35 public conveniences open until the end of October at an additional cost estimated to be £20,796 and then revert to only a core set that remain open that can be managed within the normal budget. The additional cost will be included within the in-year budget gap that will be considered by the information working group.
b) Note that the future provision of public conveniences will be part of the amenity services themed review and will be brought forward as part of the budget proposals.
4. DETAIL
Background
4.1.1 Public conveniences were closed across Scotland in March 2020 as the result of COVID-19. The Health Protection (Coronavirus) (Restrictions) (Scotland) Regulations 2020 (the Regulations) introduced strict requirements for opening public conveniences and about protecting public health, with the result that local authorities across the country moved to close their public conveniences.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2021-22 to 2025-26Decision The Committee noted the current estimated budget outlook position for the period 2021-22 to 2025-26. (Ref: R...
Budget planning 2021-22 and beyondDecision The Committee:- 1. Agreed to the overall budget approach for 2021-22 and the themed reviews as identified in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.