East Kintyre Windfarm Trustees

Agreed Committee 3 papers

Argyll and Bute Windfarm and Renewables Trust agreed this item on Tuesday 8 September 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

The Argyll and Bute Windfarm and Renewables Trust agreed to note the detail provided. (Reference: Annual Report and Audited Accounts by East Kintyre Community Council Windfarm Trust, submitted.)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Windfarm and Renewables Trust

East Kintyre Windfarm Trust Annual Report 2020

Throughout the reporting period 2019/20 , East Kintyre Community Council (EKCC) con- sisted of 6 elected members and 2 co-opted member. These members, along with 3 in- dependent trustees, make up East Kintyre Windfarm Trust.

During the financial year ending 31 March 2020, EKWFT received £55,795 in grant pay- ments from Argyll & Bute Council in relation to Beinn an Tuirc 1 & 2 and Deucheran Wind- farms. In addition, EKWFT received £2983 from SSE in relation to Tangy 2 Windfarm.

A total of 28 applications for grant funding were received during the year with 22 being approved and 6 refused. All grants agreed, totalling £43,861, were funded in full. Howev- er, by the end of the financial year, only £29,575 had been paid out in grants as two larger projects remained unpaid until into the next financial year (Seneval Composting Project and the Hub/Shop consultant’s fees).

EKCC owns a significant area of land that includes football and cricket pitches, a play park and fields rented for the grazing of horses.The upkeep of this land and the communi- ty facilities built on it requires continuous maintenance and occasional capital costs. Dur- ing the year a refurbished sit-on mower was purchased and much of the fencing sur- rounding the fields was replaced. The trust also met the cost of cutting the grass on the pitches and play park.

Although sitting on private land, the trust also funded the building of a new footbridge to connect local footpaths to Carradale Bay, after the existing one was washed away during a storm tide. The beneficiaries of this small project are local residents and visitors who would have difficulty accessing the beach from the East side of Carradale without the bridge.

With 44% of the East Kintyre community over the age of 65, many of the grants made were targeted at this group. Grants made included ones to Shopper-Aide, Carradale Surgery Patient Group, Carradale Medical Equipment Fund, the local Tai Chi Group and Carradale Community Trust First Responders for the installation of a defibrillator box.

The younger generation were also supported with grants made to the Baby & Toddler Group keep fit classes, the local football club, the Play Park Group organised fireworks display and Carradale Music Festival.

Important and popular community assets such as Campbeltown Picture House, which is well frequented by the residents of East Kintyre, and local village halls were also support- ed with grants. With an eye to the future funding of larger legacy community projects, the trust also made a grant to the East Kintyre Renewable Energy Group, who look to explore options for community shared ownership in new renewable developments in kintyre. This is very much in line with recently published Scottish Government guidance which strongly encourages communities to engage with developers to secure such partnerships. As grant funding has increased, trustees of EKWFT have sought to support larger projects which are more likely to deliver long term benefits to the community. A development fund, to help finance such community projects, was established in 2016 and currently has a balance of £59,074. Trustees have recently agreed to a grant of £40,000 towards the refurbishment of a community shop, which is conditional on the Scottish Land Fund agreeing to the purchase of the proposed premises to be renovated and adjacent land. If this goes through, it will be the largest grant ever made by EKWFT.

Each year, 10% of all community benefit funds received are transferred into a retention fund (2 bank term deposit accounts) for use by future generations. At 31 March 2020 it had a balance of £55,387.

Wherever possible, trustees look for evidence of match funding from applicants, although a degree of flexibility is often necessary as it becomes increasingly difficult for them to obtain such funding.

NOTE - This report should be read in conjunction with the attached audited accounts.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
East Kintyre Windfarm TrusteesReport 31 KB DownloadRead as text
PDF
Independent Examiners Report Accounts 201920Report 173 KB Download
PDF
Signed EKWFT Account 201920Report 1 MB Download

At this meeting

Whole meeting

Who was there

2 of 2 attended
AH
Councillor Anne HornChair, present
ST
Councillor Sandy TaylorMember, present

On this subject at Argyll and Bute

Search all
  1. East Kintyre Windfarm TrusteesThis decision
  2. East Kintyre Windfarm TrusteesAgreed
  3. East Kintyre Windfarm TrusteesAgreed
  4. Mowi scotland ltd: formation of fish farm (atlantic salmon) incorporating twelve 120m circumference circular cages and siting of feed barge: north kilbrannan fish farm, north of cour bay, kilbrannan sound, east kintyre (ref: 20/01345/mff)Agreed
  5. Mowi scotland ltd: formation of fish farm (atlantic salmon) incorporating twelve 120m circumference circular cages and siting of feed barge: north kilbrannan fish farm, north of cour bay, kilbrannan sound, east kintyre (ref: 20/01345/mff)Agreed
  6. East Kintyre - Planning for RegenerationNoted

More from Argyll and Bute Argyll and Bute Windfarm and Renewables Trust

All decisions
MeetingDecisionOutcome
29 Sep 2026 East Kintyre Windfarm TrusteesDecision The Argyll and Bute Windfarm and Renewables Trust agreed to note the detail provided. (Reference: Annual Rep... Agreed Open
29 Sep 2026 West Kintyre Windfarm TrusteesDecision The Argyll and Bute Windfarm and Renewables Trust agreed to note the detail provided. (Reference: Annual Rep... Agreed Open
29 Sep 2026 Inveraray Windfarm TrusteesDecision The Argyll and Bute Windfarm and Renewables Trust agreed to note the detail provided. (Reference: Annual Rep... Agreed Open
29 Sep 2026 ALIenergy Overview 2025/26Decision The Argyll and Bute Windfarm and Renewables Trust agreed to note the information provided. (Reference: Repor... Agreed Open
29 Sep 2026 SSE Renewables UpdateDecision The Argyll and Bute Windfarm and Renewables Trust agreed to note the information provided. (Reference: Repor... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies