Argyll and Bute HSCP Integration Joint Board (IJB) noted this item on Wednesday 26 January 2022. Below is the council's own wording, with the papers it was decided on.
Decision The Integration Joint Board – 1. Noted that management had reviewed the Strategic Risk Register. 2. Approved the proposed changes to the Strategic Risk Register. 3. Noted that the HSCP was operating on an Emergency Response basis which had an impact on Risk and mitigations throughout the HSCP. 4. Noted that it was intended to arrange a separate development session to facilitate a more detailed review of the Strategic Risk Register and Risk Appetite. (Reference: Report by Head of Finance and Transformation dated 26 January 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Argyll and Bute HSCP Integration Joint Board (IJB)
Executive summary
1.1An important element of the HSCP approach to Risk Management is to regularly review its Strategic Risk Register. This report confirms that this process has been undertaken in November 2021 and recommends some suggested changes to the Risk Register. An earlier version of this report was considered by the Audit and Risk Committee on 10 December.
1.2Overall there are number of environmental factors which are resulting in relatively high levels of risk and uncertainty at the present time. In particular there is the on-going impact of covid-19, the high levels of pressure currently being faced by the NHS and social care services and in particular the ability to recruit and retain the required staffing resource to deliver services.
1.3This report provides members of the Integration Joint Board with an opportunity to review the Strategic Risk Register in line with the 6 monthly review timetable. It is intended that a separate development event will be organised to enable members to review the Risk Register in detail.
1.4It is highlighted that the Health and Social Care Sector was placed on an emergency footing on 10th December 2021. The implications of this are wide ranging and impact throughout the Risk Register for a variety of reasons. These include the direct and indirect implications of Covid-19 along with decisions to stand down or delay services and pieces of work. Some of these decisions are likely to impact on service users while others represent delays or reductions in mitigating actions which contribute to risk management. There are separate governance and decision making arrangements in place in respect of this and these are not repeated in this report. These arrangements have risk
1 management and the minimisation of harm at their core. The situation is being reviewed on a daily basis by management as part of the response arrangements. Extensive liaison with partners also forms part of the way in which the situation is being managed.
2. INTRODUCTION
2.1The purpose of this report is to provide members of the IJB with the opportunity to review the Strategic Risk Register and consider suggested changes. The Risk Register is due to be reviewed by the IJB every 6 months. The regular consideration of Risk and how risks are mitigated is an important aspect of management and governance arrangements. It is appreciated that this is in the context of the HSCP being placed on an emergency response footing. The implications of this are not fully understood at present and it is likely that there will be an impact upon risk management in the coming months. There are separate governance and decision making processes in place in respect of the risk management and the wider implications of this.
3. DETAIL OF REPORT
3.1The Risk Register is an important tool for identifying risks and assessing their perceived likelihood and impact. It is important that the Risk Register is viewed as a dynamic document and is reviewed and updated regularly. The Risk Register is also considered along with the Risk Appetite and is scheduled to be reviewed by the IJB twice per year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Argyll and Bute HSCP Integration Joint Board (IJB) at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.