Decision The Bute and Cowal Area Committee: 1. noted the breakdown of engagement and consultation responses in each area with the majority of responses focussing on new/replacement equipment; and 2. agreed that officers make arrangements for a Business Day to discuss how the funding would be spent in Bute and Cowal . (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services, dated August 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1In August 2022, the Scottish Government confirmed a full 5 year funding package to all Scottish Local Authorities from 2020/21 through to 2025/26. Argyll and Bute Council will receive a total of £938k for Play Park funding.
1.2In December 2022, the Environment, Development and Infrastructure Committee noted the priority list of play parks in each area, based on inspections and feedback from Youth Forums. A copy of this can be found in the following link:-
Environment, Development and Infrastructure Committee 1 December 2022
1.3The March 2023 Environment, Development and Infrastructure Committee agreed a process for further engagement with other groups, including youth forums and relevant Community Councils.
1.4This report outlines the response from the engagement exercise and seeks agreement for an Area Business Day to take forward how the funding will be spent in the Bute and Cowal area.
Recommendations
It is recommended that the Bute and Cowal Area Committee:
Note the breakdown of engagement and consultation responses in each area with the majority of responses focussing on new/replacement equipment; Agree that officers make arrangements for a Business Day to agree how the funding will be spent in Bute and Cowal. ARGYLL AND BUTE COUNCIL BUTE AND COWAL AREA COMMITTEE
ROAD AND INFRASTRUCTURE September 2023 SERVICES
PLAY PARK ENGAGEMENT – UPDATE REPORT
2.0INTRODUCTION
2.1This report provides an update to the Play Park engagement responses for the Bute and Cowal Area Committee.
3.1It is recommended that the Bute and Cowal Area Committee:
Note the breakdown of engagement and consultation responses in each area with the majority of responses focussing on new/replacement equipment; Agree that officers make arrangements for a Business Day to agree how the funding will be spent in Bute and Cowal.
4.0DETAIL
4.1In August 2022, the Scottish Government confirmed a full 5 year funding package to all Scottish Local Authorities from 2020/21 through to 2025/26. Argyll and Bute Council will receive a total of £938k for Play Park funding.
4.2The below table highlights the funding split for each area as well as the number of play parks, as per previous Environment, Development and Infrastructure Committee agreement, the funding was an indicative £33,500 per play park which, when the engagement process has been fully reviewed, this can be amended by the local Area Committee.
Area Number of Play Funding Total Parks Helensburgh and 11 £368,500 Lomond
Mid Argyll, Kintyre and 11 £368,500 the Islands Bute and Cowal 5 £167,500 Oban Lorn and the Isles 1 £33,500
TOTAL 28 £938,000
4.3The March 2023 EDI Committee agreed a process for further engagement with other groups, including youth forums and relevant Community Councils.
4.4Area Committee Business days with Elected members took place in 2022. A full engagement process has since taken place and the online engagement for adults and youths closed on Friday 14 July 2023 with the following update:-
1054 Adult Responses 408 Youth Responses
This was a remarkable return for the play park engagement process and highlights the depth of feeling play parks have on our communities who are clearly keen to express their views.
4.5The responses were broken down as follows:
A Total of 1054 adult responses:
Area New/Replacement Health and Safety Access for ALL Equipment Bute and 146 35 64 Cowal Helensburgh 226 74 54 and Lomond Mid Argyll, 215 40 37 Kintyre and Islands Oban Lorn 9 3 4 and the Isles
Out of the 1054 adult responses there were a total of 147 which were void either due to referring to a non-council play park or being unable to assess the correct location from the comments.
A Total of 408 Youth Responses:
Area New/Replacement Health and Safety Access for ALL Equipment Bute and 68 7 5 Cowal Helensburgh 101 7 4 (Plus 2 don’t and Lomond know) Mid Argyll, 129 5 8 (plus 1 Don’t Kintyre and Know) Islands Oban Lorn 1 0 0 and the Isles
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.