What the committee will consider, in order, with every paper attached to its item. THE SCOTTISH GOVERNMENT ON BEHALF OF BLARGHOUR WIND FARM LIMITED: ELECTRICITY ACT SECTION 36C AND ELECTRICITY GENERATING STATIONS (APPLICATIONS FOR VARIATION OF CONSENT) (SCOTLAND) REGULATIONS CONSULTATION FROM THE ENERGY CONSENTS UNIT FOR is the main business.
Report by Head of Development and Economic Growth
Decision: Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - Approved Details & Standard Notes – Non EIA Development The development shall be implemented in accordance with the details specified on the application form dated 8/7/22; , supporting information and, the approved drawings listed in the table below unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of... Decision page
Report by Head of Development and Economic Growth
Decision: Decision The Committee agreed to refuse planning permission for the following reasons: 1. Argyll and Bute Local Development Plan – Adopted 2015 Policy LDP 8 and SG LDP BAD 1 – Bad Neighbour Development and the emerging Proposed Argyll and Bute Local Development 2 Policy 14 serves to resist any proposal that would have an unacceptable adverse impact upon the amenity of neighbouring land uses resulting from noise, vibration, etc. In addition Policy LDP 9 – Development Setting, Layout and Design... Decision page
joined the meeting during consideration of the foregoing item.
Report by Head of Development and Economic Growth
Decision: Decision The Committee agreed to grant planning permission in principle subject to the following conditions and reasons: Standard Time Limit Condition (as defined by Regulation) Additional Conditions 1. PPP – Matters Requiring AMSC Submission Plans and particulars of the matters specified in conditions 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14 and 15 below shall be submitted by way of application(s) for Approval of Matters Specified in Conditions in accordance with the timescales and other... Decision page
PROPOSED VARIATION TO BLARGHOUR WIND FARM (CONSENTED 29 OCTOBER 2021). THE S36C VARIATION PROPOSES TO VARY THE S36 CONSENT FROM 17 WIND TURBINES, 136.5M IN HEIGHT TO BLADE TIP TO 14 WIND TURBINES, 180M IN HEIGHT TO BLADE TIP: LAND APPROXIMATELY 7KM NORTH WEST OF INVERARAY AND 4.5KM SOUTH OF PORTSONACHAN (REF: 23/00537/S36) Report by Head of Development and Economic Growth
Decision: Decision The Committee agreed:- 1. that the Energy Consents Unit be notified accordingly that: Argyll and Bute Council DOES NOT OBJECT to this application, subject to the inclusion of the conditions recommended by consultees in any consent granted by the ECU. These should also include the condition proposed by the Applicant to allow the lighting scheme to be revisited in the future to take account of emerging technological solutions which would reduce the impacts of visible lighting, such as... Decision page
Committee agreed, to take a short break at this point. The Committee reconvened at 1.15 pm with all those present as per the sederunt with the exception of Councillor Paul Kennedy and Councillor Luna Martin.
View the declarations of interest for item 8. Report by Head of Development and Economic Growth
Decision: Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard Time Limit Condition (as defined by Regulation) Standard Condition on Soil Management During Construction Additional Conditions 1. PP - Approved Details & Standard Notes – Non EIA Development The development shall be implemented in accordance with the details specified on the application form dated 19.05.2023 supporting information and, the approved drawings listed in the table... Decision page
to the meeting during consideration of the foregoing item.
Report by Head of Development and Economic Growth
Decision: Decision The Committee noted the content of the report and requested that a step by step guidance note outlining the technical aspects of the extraction and restoration process alongside information on supply and demand of peat be submitted with the Planning Application. (Reference: Report by Head of Development and Economic Growth dated 1 December 2023, submitted) Decision page
Report by Head of Development and Economic Growth
Decision: Decision The Committee noted the content of the report and requested that a step by step guidance note outlining the technical aspects of the extraction and restoration process alongside information on supply and demand of peat be submitted with the Planning Application. (Reference: Report by Head of Development and Economic Growth dated 1 December 2023, submitted) Decision page
Report by Executive Director with responsibility for Development and Economic Growth
Decision: Decision The Committee agreed to note the content of the report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 7 December 2023, submitted) Decision page
Report by Executive Director with responsibility for Development and Economic Growth
Decision: Decision The Committee agreed to note the content of the report and publicise the positive feedback from the Scottish Government. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 8 December 2023, submitted) Decision page
Report by Head of Development and Economic Growth
Decision: Decision The Committee noted the contents of the report. (Reference: Report by Head of Development and Economic Growth dated 20 December 2023, submitted) Decision page
Report by Executive Director with responsibility for Legal and Regulatory Support
Decision: Decision The Committee noted the updated position. (Reference: Report by Executive Director with responsibility for Legal and Regulatory Support dated 20 December 2023, submitted) Decision page
Item 7 is where most of this meeting's papers sit: 3 papers, about 2.2 MB.
PROPOSED VARIATION TO BLARGHOUR WIND FARM (CONSENTED 29 OCTOBER 2021). THE S36C VARIATION PROPOSES TO VARY THE S36 CONSENT FROM 17 WIND TURBINES, 136.5M IN HEIGHT TO BLADE TIP TO 14 WIND TURBINES, 180M IN HEIGHT TO BLADE TIP: LAND APPROXIMATELY 7KM NORTH WEST OF INVERARAY AND 4.5KM SOUTH OF PORTSONACHAN (REF: 23/00537/S36) Report by Head of Development and Economic Growth
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 30 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 28 November 2023. 1 of its items lead into this meeting; 7 items are new. Point at any item to follow a thread. Procedural items are left out.
Every Planning, Protective Services and Licensing Committee meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Argyll and Bute, Planning, Protective Services and Licensing Committee
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Planning, Protective Services and Licensing Committee, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.