Decision Argyll and Bute Council – 1. noted that the audit was complete and Mazars had issued an unqualified opinion on the Council’s Accounts for the year ended 31 March 2023; 2. approved for signature the Council’s audited annual accounts for 2022-23; 3. noted Mazars Annual Audit Report and follow up letter for 2022-23; 4. approved for signature the ISA 580 letter of representation; and 5. noted that the Audit of the Charitable Trusts was expected to be completed in April and the Charitable Trust Accounts would be submitted to Council and Audit and Scrutiny Committee thereafter. (Reference: Report by Section 95 Officer dated 18 March 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1It is recommended that the Council: • Note that the audit is complete and Mazars have issued an unqualified opinion on the Council’s Accounts for the year ended 31 March 2023. • Approve for signature the Council’s audited annual accounts for 2022-23. • Consider Mazars Annual Audit Report and follow up letter for 2022-23. • Approve for signature the ISA 580 letter of representation. • Note that the Audit of the Charitable Trusts is expected to be completed in April and the Charitable Trust Accounts will be submitted to Council and Audit and Scrutiny Committee thereafter.
3. DETAIL
3.1Mazars have been appointed as our external auditors from financial year 2022-23 for a period of 5 years.
3.2There has been a significant delay in the completion of the audit. Mazars initially cited difficulties in recruitment as the primary cause of the delay, with resourcing being identified as a sector wide issue, particularly within the public sector. Audit work would normally commence in July each year but this was delayed until late September/early October. The key audit partner from Mazars was also absent during January and much of February 2024. Mazars have outlined their reasons for the delay on page 19 of their Audit Report.
3.3The audit of the accounts for 2022-23 is complete and Mazars have issued an unqualified opinion.
3.4The full draft External Audit report is included at Appendix 3 with a follow up letter detailing the conclusion of any outstanding matters at the time the audit report was prepared included at Appendix 4. The key messages contained within the report are as follows:
• Financial Management - The Council has an appropriate financial management culture in place. It reviews its system of internal financial control annually. - The Council has appropriate budget monitoring and reporting arrangements in place. - The Council has appropriate arrangements to prevent and detect fraud and corruption.
• Financial Sustainability - The Council has effective financial planning with an established process to ensure there is early engagement of budget proposals.
• Vision, leadership and Governance - The Corporate Plan sets a clear vision for the Council for the four-year period. - The Corporate Plan sets out objectives, measures of success and key commitments under each priority. - The Council has appropriate governance arrangements in place. - The Council provides councillors with sufficient information to allow scrutiny of its finances and performance.
• Use of Resources - The Council’s resource plans are aligned with its strategic plan. - The Council has identified how services will contribute to achievement of its strategic priorities and objectives. - The Council consults regularly with service users to understand how it can meet their needs. - The Council has clear priorities and suitable arrangements in place to measure improvement.
• Best Value - The Council has a clear vision. - The Council has appropriate Governance arrangements in place. - The Council’s annual business plans, and workforce and digital strategies are aligned with its corporate plan. - The Council knows it needs to work effectively with citizens and communities to achieve its strategic objectives. - Actions to reduce inequalities and combat climate change underpin the Council’s priorities and objectives. - Elected Members and officers worked together to agree clear strategic priorities, objectives and measures of success.
3.5The main adjustments, in addition to some presentational changes, are summarised below and further detail is provided in Appendix 1:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies