AI summaryArgyll and Bute Council noted an options report on a major landslip on the A816 at Carnasserie and agreed a funding proposal for the remedial works will come forward with the February 2026 budget.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFunding proposal to follow with budget
MoneyNot stated
What happens nextWorks expected to June 2026Funding proposal due February 2026
Who it affectsA816 road usersRoad open with traffic light controls
What was decided
The Council noted the options report that was attached as Appendix 1. Report P10
The Council agreed to bring forward a proposal on funding the remedial works as part of the February 2026 budget. Report P11
Why
A major landslip happened below the A816 at Carnasserie north of Kilmartin between 28 and November 2025, after heavy rainfall and freeze-thaw conditions, with debris reaching the river below. Report 1.1, 3.1
Officers used an emergency delegation under the Constitution, advising the Leader, the Policy Lead for Roads, Transport and Amenity Services, the Area Chair and Ward Councillors on 10 December 2025. Report 1.3, P7, P8
What happens next
Carry out works on site immediately to secure the integrity of the A816; works are currently expected to last until June 2026 and monitoring of the slip will continue. Report 3.7
Bring forward a funding proposal as part of the budget process in February 2026. Report P11, 5.0
Implications
Financial: Funding for the remedial works will be considered as part of the February 2026 budget process. Report 5.0
Who and where
Road users on the A816 at Carnasserie north of Kilmartin Report 3.1
Timeline
28-November 2025: Major landslip below the A816 at Carnasserie Report 1.1, 3.1
10 December 2025: Executive Director advised the Leader, Policy Lead, Area Chair and Ward Councillors Report P8
29 January 2026: Council meeting considered the report Report P1
February 2026: Funding proposal to come forward with the budget Report P11, 5.0
June 2026: Works currently expected to finish Report 3.7
Plain English for the jargon
A816: A road in Argyll
Carnasserie: An area north of Kilmartin in Argyll
SEPA: Scottish Environment Protection Agency
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
Decision The Council – 1. noted the Options Report attached as Appendix 1 to the submitted report; and 2. agreed that a proposal on how the remedial works would be funded would be brought forward as part of the budget proposals in February 2026. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated December 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL COUNCIL ROADS AND INFRASTRUCTURE 29 JANUARY 2026
A816 MILLBRAE LANDSLIP
1.0INTRODUCTION
1.1A major landslip occurred below the A816 at Carnasserie (north of Kilmartin) between 28-30 November 2025 following heavy rainfall and freeze-thaw conditions. Geotechnical specialists inspected the slope and provided an options report which is attached as Appendix 1.
1.2Due to the severity of the landslip and the high probability of further slippage, as well as the location being on a strategic route, it was essential to commence work on site as soon as possible.
1.3Officers utilised a delegation within the Constitution to deal with the emergency situation. The relevant section from the Constitution is Part C, Section 3.2.5 that states:
“The Chief Executive and the Executive Directors of Service are authorised to take such measures as may be required to enable the Council to respond to an emergency situation, subject to advising as appropriate (a) the Leader, (b) the relevant Policy Lead, and where the emergency is likely to affect significantly a particular part of the Council’s area (c) the Chair of the relevant Area Committee and (d) Ward Councillors, reporting to the Council as soon as possible thereafter, on any items of expenditure for which approval would normally be necessary.”
In line with the Constitution the Executive Director advised the Leader, the Policy Lead for Roads, Transport and Amenity Services, the Area Chair and the Ward Councillors on 10 December 2025. 2.0 RECOMMENDATIONS
2.1It is recommended that the Council -
a) Consider and note the Options Report attached as Appendix 1; and
b) Agree that a proposal on how the remedial works will be funded will be brought forward as part of the budget proposals in February 2026. 3.0 DETAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.