Area Community Planning Group Governance Arrangements
ApprovedPlanning3 papers
AI summaryBute and Cowal Area Community Planning Group adopts unchanged Terms of Reference, agrees membership and sets four meeting dates up to February 2027.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoth to be reviewed annually
MoneyNot stated
What happens nextNot stated
Who it affectsNot stated
What was decided
The group adopted the Terms of Reference at Appendix 1 with no changes proposed and agreed they be reviewed annually. Report 3.1, P5
The group agreed the membership at Appendix 2 and agreed it be reviewed annually, with provision for additional organisations to join at any stage. Report 3.3, P6
The group noted the four future meeting dates: 28 April 2026, 11 August 2026, 3 November 2026 and 2 February 2027. Report P12
Why
The Terms of Reference and membership were last reviewed in February 2025 and are now being confirmed by the group. Report 3.1
Meeting dates are scheduled roughly halfway between programmed meetings of the Community Planning Partnership Management Committees to allow effective reporting. Report 3.4
What happens next
Both the Terms of Reference and membership will be reviewed on an annual basis to ensure they remain appropriate as the group's work develops. Report 3.3, P5, P6
The group will next meet on Tuesday 28 April 2026, with further dates in August, November 2026 and February 2027. Report P12
Options considered
Chosen: Adopt the Terms of Reference as submitted with no changes. No changes or amendments were proposed; last reviewed February 2025 Report 3.1, P5
Chosen: Agree the membership as attached at Appendix 2. Last reviewed February 2025; annual review retained with provision for new organisations to join as needed Report 3.3, P6
Chosen: Note the four future meeting dates for 2026/27. Dates are timed to fit between Community Planning Partnership Management Committee meetings Report 3.4, P12
Implications
Governance: Annual reviews of Terms of Reference and membership are built in to keep the group's governance current. Report 3.3, P5, P6
Other: The report states that equalities outcomes are not applicable as it relates to administration of the Area CPG. Report P16
Who and where
Members and partner organisations of the Bute and Cowal Area Community Planning Group Report 1.1, P19
Argyll and Bute Community Planning Partnership Management Committee, which receives reports from the Area CPG Report 3.4
Timeline
February 2025: Terms of Reference and membership last reviewed and agreed Report 3.1
Tuesday 28 April 2026: Next scheduled meeting of the Bute and Cowal Area CPG Report P12
Tuesday 11 August 2026: Scheduled meeting of the Bute and Cowal Area CPG Report P12
Tuesday 3 November 2026: Scheduled meeting of the Bute and Cowal Area CPG Report P12
Tuesday 2 February 2027: Scheduled meeting of the Bute and Cowal Area CPG Report P12
Plain English for the jargon
Area CPG: Area Community Planning Group, in this case the Bute and Cowal Area Community Planning Group, a local partnership body.
Terms of Reference: A document setting out the group's purpose, scope and how it operates.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5a
Resolved
Decision The Bute and Cowal Area Community Planning Group: 1. adopted the Terms of Reference submitted in this report (Appendix 1) and agreed that these be reviewed on an annual basis to ensure their ongoing currency and appropriateness for the work of the Area CPG as it develops over time. 2. agreed the membership of the group as attached (Appendix 2) and agreed that the membership of the group be reviewed on an annual basis to ensure currency and appropriateness for the work of the group as it develops over time; and 3. noted the future meeting dates of the Group as: · Tuesday 28 April 2026 · Tuesday 11 August 2026 · Tuesday 3 November 2026 · Tuesday 2 February 2027 (Reference: Report by Committee Manager, Argyll and Bute Council, dated January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Bute and Cowal Area Community Planning Group
Summary
The report asks the Bute and Cowal Area Community Planning Group to review the current Terms of Reference, the membership of the Group and also asks members to note the dates for meetings up until February 2027.
1. Purpose
1.1The purpose of this report is to confirm the governance arrangements of the Bute and Cowal Area Community Planning Group (Area CPG) specifically the Terms of Reference, membership and note future meeting dates.
Recommendations
2.1Area CPG members are requested to:
• Consider and adopt the Terms of Reference submitted in this report (Appendix 1) and to agree that these be reviewed on an annual basis to ensure their ongoing currency and appropriateness for the work of the Area CPG as it develops over time.
• Consider and agree the membership of the group as attached (Appendix 2) and to agree that the membership of the group be reviewed on an annual basis to ensure currency and appropriateness for the work of the group as it develops over time.
• To note the future meeting dates submitted in this report.
3. Detail
3.1The Area CPG Terms of Reference were last reviewed and agreed in February 2025, these are attached at Appendix 1. Please note that no changes or amendments are proposed for the Terms of Reference. 3.2 The membership of the Area CPG was last reviewed in February 2025. The Area CPG are asked to consider whether any changes should be made to the membership, details of which are attached at Appendix 2.
3.3The membership will be reviewed on an annual basis to ensure currency and appropriateness for the work of the group as it develops over time, however there is provision for additional organisations to join the group at any stage to accommodate local circumstances.
3.4Historically meeting dates for Area Community Planning Groups are scheduled approximately half way between the programmed meetings of the Community Planning Partnership Management Committees to enable effective and timeous reporting of matters to that committee. Members are therefore asked to note that the meeting dates for the Bute and Cowal Area CPG for 2026/27 will be:-
• Tuesday 28 April 2026 • Tuesday 11 August 2026 • Tuesday 3 November 2026 • Tuesday 2 February 2027
4. Conclusion
4.1The Area Community Planning Group is asked to review and agree the attached Terms of Reference and the current membership.
5. ABOIP Outcomes
Not applicable. The report relates to the administration of the Area CPG.
For further information please contact:
Stuart McLean, Committee Manager, Argyll and Bute Council Tel 01436 658 717
Appendix 1 – Terms of Reference Appendix 2 – Membership list
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bute and Cowal Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Scottish Fire and Rescue Service UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Scott...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.