Argyll and Bute Climate Action: developing a Climate Change Strategy and Action Plan for Argyll and Bute

Noted Planning 3 papers

AI summaryBute and Cowal planning group noted progress on a draft climate action plan and the business case for an Argyll and Bute Climate Ready Region, and asked members to feed back by end of May 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
Money£443,000 over 5 yearsTotal five-year cost for the proposed Climate Ready Region partnership.
What happens nextEnd of May 2026Deadline for feedback on the draft climate action plan and resilience priorities.
Who it affectsBute and Cowal areaCommunities, CPP member organisations and the wider Argyll and Bute region.

What was decided

Noted overall progress and the timeline to the end of the CPP funded period (July 2026) and beyond.

Agreed members will return feedback on the draft climate action plan to the CPP Climate Change Project Manager by the end of May 2026.

Noted that the CPP Management Committee supports the business case recommendations for an Argyll and Bute Climate Ready Region, which have been submitted to the Scottish Government.

Why

The Argyll and Bute region could face an annual economic loss of between £35 million and £73 million from climate change by 2050, against a five-year partnership cost of £443,000. Report P21, P17

Climate change could reduce regional GDP by 1.2% to 2.5% each year by 2050, and collaboration offers opportunities for economies of scale to limit that loss. Report P17

Existing structures (the CPP, ACT and ABCAN) provide a foundation, but long-term funding is uncertain and climate risks are growing in scale and complexity. Report P21, P18

What happens next

Members to send feedback on the draft climate action plan to the CPP Climate Change Project Manager by the end of May 2026.

A sub meeting may be held to identify leads for actions that fall across the remits of CPP member organisations.

Members to suggest priority groups or actions for Bute and Cowal on community resilience (emergency) plans to the project manager.

The money

  • £35 to £73 million Possible annual economic loss to the Argyll and Bute region from climate change. Report P17, P21
  • £443,000 Total cost of establishing and operating the Partnership over five years. Report P21
  • £71,500 per annum Phase 1 (Years 1-2) partnership costs for secretariat, revenue and staff. Report P21, P19
  • £100,000 per annum Phase 2 (Years 3-5) partnership costs under the expanded Status Quo+ model. Report P21, P19
  • 1.2% to 2.5% Possible annual reduction in regional GDP by 2050 from climate change. Report P17

Options considered

  • Chosen: Status Quo. Minimises setup costs, protects prior investment and allows early delivery of quick-win adaptation actions; selected as the starting point for Phase 1. Report P19, P20
  • Chosen: Status Quo+. Offers additional benefits through wider partner engagement and funding; selected as the target for Phase 2 (Years 3-5). Report P19, P20
  • Rejected: New Partnership. Not selected as the preferred way forward. Report P19

Implications

  • Financial: Total five-year programme cost estimated at £443,000, with no capital expenditure and no identified regional contribution in Phase 1; core funding sought primarily from the Scottish Government and competitive grants. Report P21
  • Risk: Commercial risks are described as low and manageable through phased delivery, flexible contracts and clear accountability. Report P21
  • Staffing: Day-to-day coordination will be led by a dedicated secretariat hosted by ACT, with delivery steered by a small core Steering Group and strategic oversight through the CPP. Report P21
  • Climate: Six high-priority areas for climate action have been identified in the Argyll and Bute CPP's Climate Change Strategy, requiring collaborative response at scale. Report P15
  • Legal: The proposed approach is aligned with public sector procurement requirements and statutory duties on public bodies to help deliver national adaptation plans. Report P21, P14

Who and where

  • Communities in the Bute and Cowal area, including those developing resilience (emergency) plans. Report P21
  • Member organisations of the Argyll and Bute Community Planning Partnership.
  • Argyll Countryside Trust (ACT), which would host the partnership secretariat. Report P18, P21
  • Argyll and Bute Climate Action Network (ABCAN), through which community involvement would be embedded. Report P18, P21
  • Argyll and Bute Council, via its Climate Change Board and CPP structures. Report P21
  • The Scottish Government, to whom the business case has been submitted. Report P14

Timeline

  • April 2026: Report submitted to the Bute and Cowal Area Community Planning Group by the CPP Climate Change Project Manager.
  • End of May 2026: Deadline for members to return feedback on the draft climate action plan and to suggest priority groups or actions for Bute and Cowal on resilience plans.
  • July 2026: End of the current CPP funded period.
  • Years 1-2 (Phase 1): Initial set-up of the Climate Ready Region partnership using the Status Quo model at £71,500 per annum. Report P21, P19
  • Years 3-5 (Phase 2): Move towards the expanded Status Quo+ model at £100,000 per annum, subject to Phase 1 success and funding. Report P21, P19
  • 2029: Scottish Government ambition, under SNAP3, to have regional adaptation partnerships in place across all regions of Scotland. Report P14
  • By 2050: Projected annual regional GDP reduction of 1.2% to 2.5% from climate change, equivalent to £35m to £73m per year for Argyll and Bute. Report P17

Plain English for the jargon

  • CPP: Community Planning Partnership, the regional coordination body for Argyll and Bute.
  • ACT: Argyll Countryside Trust, the intended host of the partnership secretariat.
  • ABCAN: Argyll and Bute Climate Action Network, an existing community involvement mechanism.
  • SNAP3: Scottish National Adaptation Plan (third iteration), the national policy framework cited as a driver for regional adaptation partnerships.
  • Status Quo+: An enhanced version of existing partnership arrangements, offering wider partner engagement and additional funding potential; the target model for Phase 2.
  • Business Case (five-case model): A document prepared in line with HM Treasury Green Book Guidance, structured around strategic, economic, financial, commercial and management dimensions.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10a

Resolved

Decision The Bute and Cowal Area Community Planning Group: 1. noted overall progress and timeline to the end of the CPP funded period (July 2026) and beyond, 2. agreed to return any feedback on the draft climate Action Plan by the end of May to Andy Macpherson, CPP Climate Change Project Manager andy@act_now.org.uk; 3. noted that the CPP Management Committee had approved the Action Plan for the CPP Climate Change Strategy and that a sub meeting may be necessary to identify leads for actions that fall across the remits of member organisations; 4. noted that the CPP Management Committee supports the recommendations in the business case for an Argyll and Bute Climate Ready Region which had been submitted to the Scottish Government; and 5. noted progress and limitations with supporting communities in developing resilience (emergency) plans and agreed to return suggestion’s of priority groups or actions for Bute and Cowal to Andy Macpherson, CPP Climate Change Project Manager. (Reference: Report by Climate Change Project Manager, Argyll and the Isles Coast and Countryside Trust, dated April 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Bute and Cowal Area Community Planning Group

Argyll & Bute Climate Ready Region

Business Case – Executive Summary

March 2026 Waterman Infrastructure & Environment Ltd 180 St Vincent Street, 6th Floor (South), Glasgow G2 5SG www.watermangroup.com Client Name: Argyll Countryside Trust (ACT) Document Reference: 21491100-WAT-XX-XX-RP-N-780001_P03 Project Number: WIE21942

Quality Assurance – Approval Status This document has been prepared and checked in accordance with Waterman Group’s IMS (BS EN ISO 9001: 2015, BS EN ISO 14001: 2015 and BS EN ISO 45001:2018)

Revision Status Date Prepared by Checked by Approved by

P01 DRAFT 17/2/2026 Cara Labuschagne; Richard White Dave Allen Nancy Unger

Comments First draft issued for review by ACT

PO2 DRAFT 19/2/2026 Cara Labuschagne Dave Allen Dave Allen

Comments Minor edits incorporated, issued for review to wider stakeholders

P03 FINAL 13/03/2026 Cara Labuschagne Dave Allen Dave Allen

Comments Final version addressing stakeholder comments

Revision Status

Pnn Preliminary (shared; non-contractual) S1 Coordination Cnn Contractual S2 Information S3 Review & Comment S4 Review & Authorise S5 Review & Acceptance A0, A1, An Authorised & Accepted (n=work stage if applicable) Disclaimer This report has been prepared by Waterman Infrastructure & Environment Ltd, with all reasonable skill, care and diligence within the terms of the Contract with the client, incorporation of our General Terms and Condition of Business and taking account of the resources devoted to us by agreement with the client. We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above. This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies on the report at its own risk. Executive Summary This report sets out the Business Case for establishing a regional climate change adaptation partnership in Argyll & Bute, in line with the Scottish Government aspiration to see Climate Ready Regions established throughout Scotland. It defines a clear case for securing long-term support and funding for the Partnership and sets out the actions required over the next five years to implement an effective and sustainable partnership. The Business Case has been developed in collaboration with Argyll Countryside Trust and has been supported with widespread engagement with key stakeholders in the region. The Business Case has been prepared in accordance with HM Treasury Green Book Guidance following the five-case (dimensions) model, and the report is structured around the five dimensions, with the key findings as follows: Strategic Dimension The strategic case and rationale for the Partnership is clear:

• Strong policy drivers. Clearly supports the Scottish National Adaptation Plan (SNAP3) ambition to establish regional adaptation partnerships in all regions of Scotland by 2029, and statutory duties on public bodies to help deliver national adaptation plans.

• Regional climate challenges. The Argyll and Bute Community Planning Partnership’s Climate Change Strategy for the region identified six high priority areas for climate action. The scale of response required will necessitate collaboration to share expertise, tools, approaches and resources for a climate resilient Argyll and Bute region.

• Evidenced success of place-based approaches. Place-based approaches recognise that localised climate impacts, risks and responses will be different. Existing partnerships are already demonstrating the power of regional adaptation approaches.

• Economic impacts and economies of scale. Based on a recent study, climate change could reduce regional GDP by 1.2% to 2.5% each year by 2050. If Argyll & Bute is affected to the same degree, the area could face an annual economic loss of between £35 to £73 million. There are significant opportunities for economies of scale to limit that loss through strategic shared approaches.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21942100-WAT-XX-XX-780001_P03_EXEC SUMMARYReport 922 KB DownloadRead as text
PDF
260320 Climate Action Plan approved by CPP MCReport 151 KB Download
PDF
Argyll and Bute Climate Action: developing a Climate Change Strategy and Action Plan for Argyll and ButeReport 228 KB Download

At this meeting

Whole meeting

Who was there

1 of 4 attended
JB
June BeggSecretary, expected
RK
Councillor Reeni Kennedy-BoyleMember, present
CJ
CI James McArthurPublic, expected
JM
Jean MoffatChair, expected

On this subject at Argyll and Bute

Search all
  1. Argyll and Bute Climate Action: developing a Climate Change Strategy and Action Plan for Argyll and ButeThis decision
  2. Argyll and bute outcomes and improvement plan - priorities updateNoted
  3. Argyll and Bute Climate Action NetworkNoted
  4. Argyll and bute improvement plan - priorities updateNoted
  5. Argyll and bute improvement plan - priorities updateNoted
  6. Argyll and bute harbour board workplanNoted

More from Argyll and Bute Bute and Cowal Area Community Planning Group

All decisions
MeetingDecisionOutcome
3 Nov 2026 Community planning partnership management committee meeting highlightsDecision The Bute and Cowal Area Community Planning Group noted the contents of the report. (Reference: Report by Par... Noted Open
3 Nov 2026 Argyll and bute improvement plan - priorities updateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Verbal update f... Noted Open
3 Nov 2026 Heartstart Cowal and Cowal Peninsula Community First RespondersDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Verbal update f... Noted Open
3 Nov 2026 Police Scotland UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Polic... Noted Open
3 Nov 2026 Scottish Fire and Rescue Service UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Scott... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies