AI summaryArgyll and Bute Council noted a forecast overspend of about £1.5m on the Iona Breakwater project and agreed the extra cost would be built into the Marine Asset Management Plan, funded through borrowing and a 2027-28 fee uplift.
Written from the decision and the officer reportPDF Pro
OutcomeNotedExtra costs into Marine Asset Management Plan, 2027-28 fee uplift
MoneyAbout £1.5m overspendOn £16.4m current budget, original contract £14,785,026
What happens nextBuild into Marine Asset Management PlanConsider 2027-28 fee uplift to cover increase
Who it affectsIona harbour users and councilBreakwater works ongoing, completion targeted late summer 2026
What was decided
The Council noted the forecast overspend of about £1.5m on the Iona Breakwater project, driven mainly by weather and seagrass-related delays. Report 1.2
It agreed that the additional cost would be built into the Marine Asset Management Plan, funded through prudential borrowing and a percentage uplift in fees and charges. Report 2.1
It noted the increased cost would be considered as part of the 2027-28 fee uplift.
Why
Main works stopped for winter and have not restarted due to persistent weather disruption, and earlier regulatory delays over seagrass displaced the programme into winter conditions. Report 1.1, 3.1
Without emergency intervention, deferring funding approval to the April Council meeting risked the contractor withdrawing negotiated terms and greater cost escalation. Report 3.1
What happens next
Officers will build the additional cost into the Marine Asset Management Plan and consider the uplift as part of the 2027-28 fee setting process.
The contractor has offered to take on full past and future weather risk for £1.95m, which would cap the Council's liability and target completion by late summer 2026.
The money
£14,785,026 Original contract value at award Report 1.2
£17,961,976 Current worst-case scenario forecast cost Report 1.2
£3,176,950 Uplift from contract award (+20.49%) Report 1.2
£16.4m Current project budget reported to Harbour Board in January 2026 Report 1.2
£1,950,00 Weather Risk Settlement offered by contractor (past and future, +13.19%)
£1,333,000 Marine Directorate standing time related to seagrass matters (+9.02%)
(£509,604) Value engineering savings (-3.45%)
£303,554 Additional works and adjustments (+2.05%)
Options considered
Chosen: Accept contractor offer of full past and future weather risk for £1.95m, capping liability and targeting late summer 2026 completion. Avoids further winter delays and caps Council's exposure to further weather cost escalation
Rejected: Do nothing and continue on current programme. Current estimated completion of November 2026 falls back into a high-risk weather window, risking further delays and cost uplift
Rejected: Defer funding decision to the April Council meeting. Contractor might withdraw negotiated terms, risking even greater costs
Implications
Financial: Overspend of about £1.5m to be absorbed via prudential borrowing and a fee and charges uplift, with the increase considered as part of the 2027-28 fee uplift.
Legal: None identified by the Executive Director at the time of the report.
Risk: Without accepting the contractor's weather risk offer, further winter delays and cost escalation are likely given the November 2026 completion estimate.
Argyll and Bute Council, as project client and funder of last resort Report P7, 3.0
Harbour Board, which previously received the £16.4m budget update in January 2026 Report 1.2
Timeline
Summer 2025: Planned start of works delayed by regulatory issues over seagrass Report 1.1
Over winter 2025-26: Main works ceased and have not yet restarted on site due to weather disruption Report 1.1
January 2026: Current budget of £16.4m reported to the Harbour Board Report 1.2
March 2026: Report by Executive Director with responsibility for Roads and Infrastructure submitted
19 March 2026: Executive Director advised the Leader, Policy Lead, Area Chair and Ward Councillors of emergency measures Report P8
29 April 2026: Argyll and Bute Council considered the report and agreed the recommendations Report P1
Late summer 2026: Targeted completion if the contractor's weather risk offer is accepted
November 2026: Current estimated completion date without intervention, within a high-risk weather window
2027-28: Increased cost to be considered as part of the fee uplift
Plain English for the jargon
Prudential borrowing: Borrowing by a local authority for capital projects, with repayment funded from council income rather than central government grant.
Marine Asset Management Plan: The council's plan for managing its marine infrastructure, into which the additional Iona Breakwater costs will be built.
Breakwater: A coastal structure, usually a wall or jetty, that shelters a harbour or anchorage from waves.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
Decision The Council – 1. noted the forecasted overspend on the Iona Breakwater project of circa £1.5m; 2. agreed that additional costs would be built into the Marine Asset Management Plan which ultimately was funded via prudential borrowing and a percentage uplift in fees and charges; and 3. noted the increased cost would be considered as part of the 2027-28 fee uplift. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated March 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL COUNCIL ROADS AND INFRASTRUCTURE 29 APRIL 2026
IONA BREAKWATER
1.0INTRODUCTION
1.1The main works at Iona Breakwater ceased over the winter break and have not yet restarted on site due to persistent weather disruption. Regulatory delays centred around seagrass matters prevented the works from starting as planned in summer 2025. This displaced the programme into winter conditions, increasing exposure to weather risk, reducing productivity, and affecting the overall commercial position.
1.2The original contract value of £14,785,026 has increased to a current worst-case scenario forecast of £17,961,976 representing an increase of £3,176,950 (+20.49 %) uplift from contract award. The current budget for the project is £16.4m as reported to the Harbour Board at its meeting in January 2026. The current forecast indicates a overspend of circa £1.5m.
1.3Officers utilised a delegation within the Constitution to deal with the emergency situation. The relevant section from the Constitution is Part C, Section 3.2.5 that states:
“The Chief Executive and the Executive Directors of Service are authorised to take such measures as may be required to enable the Council to respond to an emergency situation, subject to advising as appropriate (a) the Leader, (b) the relevant Policy Lead, and where the emergency is likely to affect significantly a particular part of the Council’s area (c) the Chair of the relevant Area Committee and (d) Ward Councillors, reporting to the Council as soon as possible thereafter, on any items of expenditure for which approval would normally be necessary.”
In line with the Constitution the Executive Director advised the Leader, the Policy Lead for Roads, Transport and Amenity Services, the Area Chair and the Ward Councillors on 19 March 2026. 2.0 RECOMMENDATIONS
2.1It is recommended that the Council -
a) Notes the forecasted overspend on the Iona Breakwater project of circa £1.5m; and
b) Agrees that additional costs will be built into the Marine Asset Management Plan which ultimately is funded via prudential borrowing and a percentage uplift in fees and charges – this increased cost will be considered as part of the 2027-28 fee uplift.
3.0DETAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.