Argyll and Bute Climate Action: a Climate Change Strategy and Action Plan for Argyll and Bute
NotedPlanning4 papers
AI summaryMid Argyll, Kintyre and the Islands Area Community Planning Group noted progress on a draft climate Action Plan and a business case for an Argyll and Bute Climate Ready Region, seeking five-year funding of £443,000.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFive-point noting and endorsement with feedback by mid-June
Money£443,000 over 5 yearsPhase 1 £71,500/year, Phase 2 £100,000/year
What happens nextReturn feedback on draft Action PlanBy end of mid-June to CPP Climate Change Project Manager
Who it affectsNot stated
What was decided
The group noted overall progress and the timeline to the end of the CPP funded period in July 2026 and beyond.
The group agreed to return any feedback on the draft climate Action Plan by the end of mid-June to the CPP Climate Change Project Manager.
The group noted the CPP Management Committee's approval of the Action Plan and that a sub meeting may be needed to identify leads for cross-organisation actions.
Why
The business case identifies a potential annual economic loss of between £35 million and £73 million for Argyll and Bute by 2050 from climate change, against a five-year programme cost of £443,000. Report P17, P21
Existing regional structures, the Community Planning Partnership, ACT and ABCAN, provide a platform for a Climate Ready Region without duplicating effort. Report P18
A phased Status Quo approach minimises setup costs, protects prior investment and allows early delivery of quick-win adaptation actions. Report P19, P20
What happens next
Members to send feedback on the draft Action Plan to Andy Macpherson, CPP Climate Change Project Manager, by end of mid-June.
The CPP Management Committee supports recommendations in the business case for an Argyll and Bute Climate Ready Region, submitted to the Scottish Government.
Members to return suggestions of priority groups or actions for community resilience plans in Mid Argyll, Kintyre and the Islands.
The money
£443,000 Total five-year cost of establishing and operating the Partnership Report P21
£71,500 per annum Phase 1 (Years 1-2) partnership costs Report P21
£100,000 per annum Phase 2 (Years 3-5) partnership costs Report P21
£35 to £73 million Possible annual economic loss to Argyll and Bute by 2050 Report P17, P21
1.2% to 2.5% Annual regional GDP reduction by 2050 from climate change Report P17
Options considered
Chosen: Status Quo (Preferred for Phase 1). Minimises setup costs, protects prior investment and allows early delivery of quick-win actions Report P19, P20
Chosen: Status Quo+ (Ambition for Phase 2). Offers additional benefits through wider partner engagement and funding in later years Report P19
Rejected: New Partnership. Not selected as preferred way forward Report P19
Implications
Financial: No identified regional financial contribution in Phase 1, so core funding is sought primarily from the Scottish Government, supplemented by competitive grants. Report P21
Financial: All partnership costs are operational; there is no capital expenditure. Report P21
Risk: Commercial risks are described as low and manageable through phased delivery, flexible contracts and clear accountability. Report P21
Legal: Procurement routes can use existing public sector processes and frameworks, remaining compliant with procurement regulations. Report P21
Climate: Business case supports the Scottish National Adaptation Plan ambition to establish regional adaptation partnerships in all regions of Scotland by 2029. Report P14
Other: Six high priority areas for climate action were identified in the CPP's Climate Change Strategy for the region. Report P15
Who and where
Communities in Mid Argyll, Kintyre and the Islands
Argyll and Bute Community Planning Partnership Report P18
Argyll Countryside Trust (ACT) Report P18, P21
Argyll and Bute Climate Action Network (ABCAN) Report P18
Argyll and Bute Council, via its Climate Change Board Report P21
Timeline
13/03/2026: Final version of the business case issued by Waterman Report P10
27 May 2026: Area Community Planning Group meeting considers the report
By end of mid-June 2026: Deadline for member feedback on the draft Action Plan
July 2026: End of the current CPP funded period
By year 3: Ambition to progress from Phase 1 to Phase 2 of the Route Map Report P21
By 2029: Scottish Government target for regional adaptation partnerships across Scotland Report P14
By 2050: Projected annual climate-related economic impact of 1.2% to 2.5% of regional GDP Report P17
Plain English for the jargon
ABCAN: Argyll and Bute Climate Action Network, an existing regional climate partnership.
ACT: Argyll Countryside Trust, which hosts the CPP Climate Change Project Manager.
CPP: Community Planning Partnership, the existing regional body for Argyll and Bute.
Climate Ready Region: A proposed regional climate change adaptation partnership for Argyll and Bute, aligned with Scottish Government policy.
SNAP3: Scottish National Adaptation Plan, the third iteration, which sets the ambition for regional adaptation partnerships by 2029.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8a
Resolved
Decision The Mid Argyll, Kintyre and the Islands Area Community Planning Group: 1. noted overall progress and timeline to the end of the CPP funded period (July 2026) and beyond; 2. agreed to return any feedback on the draft climate Action Plan by the end of mid June to Andy Macpherson, CPP Climate Change Project Manager andy@act_now.org.uk ; 3. noted that the CPP Management Committee had approved the Action Plan for the CPP Climate Change Strategy and that a sub meeting may be necessary to identify leads for actions that fall across the remits of member organisations; 4. noted that the CPP Management Committee supports the recommendations in the business case for an Argyll and Bute Climate Ready Region which had been submitted to the Scottish Government; and 5. noted progress and limitations with supporting communities in developing resilience (emergency) plans and agreed to return suggestions of priority groups or actions for Mid Argyll, Kintyre and the Islands. (Reference: Report by Climate Change Project Manager, Argyll & the Isles Coast and Countryside Trust, dated 27 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre and the Islands Area Community Planning Group
Argyll & Bute Climate Ready Region
Business Case – Executive Summary
March 2026 Waterman Infrastructure & Environment Ltd 180 St Vincent Street, 6th Floor (South), Glasgow G2 5SG www.watermangroup.com Client Name: Argyll Countryside Trust (ACT) Document Reference: 21491100-WAT-XX-XX-RP-N-780001_P03 Project Number: WIE21942
Quality Assurance – Approval Status This document has been prepared and checked in accordance with Waterman Group’s IMS (BS EN ISO 9001: 2015, BS EN ISO 14001: 2015 and BS EN ISO 45001:2018)
Revision Status Date Prepared by Checked by Approved by
P01 DRAFT 17/2/2026 Cara Labuschagne; Richard White Dave Allen Nancy Unger
Comments First draft issued for review by ACT
PO2 DRAFT 19/2/2026 Cara Labuschagne Dave Allen Dave Allen
Comments Minor edits incorporated, issued for review to wider stakeholders
P03 FINAL 13/03/2026 Cara Labuschagne Dave Allen Dave Allen
Comments Final version addressing stakeholder comments
Revision Status
Pnn Preliminary (shared; non-contractual) S1 Coordination Cnn Contractual S2 Information S3 Review & Comment S4 Review & Authorise S5 Review & Acceptance A0, A1, An Authorised & Accepted (n=work stage if applicable) Disclaimer This report has been prepared by Waterman Infrastructure & Environment Ltd, with all reasonable skill, care and diligence within the terms of the Contract with the client, incorporation of our General Terms and Condition of Business and taking account of the resources devoted to us by agreement with the client. We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above. This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies on the report at its own risk. Executive Summary This report sets out the Business Case for establishing a regional climate change adaptation partnership in Argyll & Bute, in line with the Scottish Government aspiration to see Climate Ready Regions established throughout Scotland. It defines a clear case for securing long-term support and funding for the Partnership and sets out the actions required over the next five years to implement an effective and sustainable partnership. The Business Case has been developed in collaboration with Argyll Countryside Trust and has been supported with widespread engagement with key stakeholders in the region. The Business Case has been prepared in accordance with HM Treasury Green Book Guidance following the five-case (dimensions) model, and the report is structured around the five dimensions, with the key findings as follows: Strategic Dimension The strategic case and rationale for the Partnership is clear:
• Strong policy drivers. Clearly supports the Scottish National Adaptation Plan (SNAP3) ambition to establish regional adaptation partnerships in all regions of Scotland by 2029, and statutory duties on public bodies to help deliver national adaptation plans.
• Regional climate challenges. The Argyll and Bute Community Planning Partnership’s Climate Change Strategy for the region identified six high priority areas for climate action. The scale of response required will necessitate collaboration to share expertise, tools, approaches and resources for a climate resilient Argyll and Bute region.
• Evidenced success of place-based approaches. Place-based approaches recognise that localised climate impacts, risks and responses will be different. Existing partnerships are already demonstrating the power of regional adaptation approaches.
• Economic impacts and economies of scale. Based on a recent study, climate change could reduce regional GDP by 1.2% to 2.5% each year by 2050. If Argyll & Bute is affected to the same degree, the area could face an annual economic loss of between £35 to £73 million. There are significant opportunities for economies of scale to limit that loss through strategic shared approaches.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre and the Islands Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Scottish ambulance service updateDecision The Mid Argyll, Kintyre and the Islands Area Community Planning Group noted the information provided. (Refer...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.