INTERNAL AUDIT UPDATE

Noted Finance 1 paper

AI summaryHSCP Audit and Risk Committee noted progress on internal audit recommendations, with 11 actions complete, 10 on track and 8 delayed as at 31 March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted progress on internal audit recommendations
MoneyNot stated
What happens next2026/27 audits beginWork has started on three planned reviews
Who it affectsHSCP servicesAdult Services, Children and Families, Strategic Planning

What was decided

The Committee noted progress on completion of internal audit recommendations, on a report by the Chief Internal Auditor dated 16 June 2026.

Why

The 2025/26 Internal Audit Plan is now complete and all elements have been reported to the Committee. Report P13, 2.4

Internal Audit tracks agreed actions in a database and follows them up quarterly, only closing them once evidence of completion is provided. Report 2.2

What happens next

The 2026/27 plan has three planned reviews: Financial Management Arrangements, Stakeholder Engagement and Risk Management, and work has commenced. Report P13, 2.4

Quarterly follow-up of open audit actions will continue, including eight actions currently recorded as delayed and rescheduled. Report 2.2, P9, P11

Options considered

  • Chosen: Note the progress update. The Committee accepted the report without amendment. Report 10.1

Implications

  • Risk: The audit planning approach is risk-based and individual audit reports provide an overall assessment on the management of risk. Report 8.1
  • Legal: The report states it does not raise any GDPR issues, though GDPR will be considered in audits where appropriate. Report 7.1
  • Equalities: The report records no equality and diversity implications. Report 6.0

Who and where

  • HSCP (IJB) services, including Chief Finance Officer, Adult Services, and Strategic Planning, Performance and Technology Report P7, P8, P9
  • HSCP social work services, including Adult Services, Children and Families and Justice, and Strategic Planning Report P10, P11
  • Lead officers responsible for delayed actions, such as Senior Managers in Adult Services and the Head of Children, Families and Justice Report P36, P37, P38, P40, P42

Timeline

  • 17 February 2026: Date of previous Committee meeting, since which one audit has been completed. Report 1.2
  • 31 March 2026: As-at date for the summary of audit actions in Tables 1 and 2. Report P7, P10, P11
  • 12 May 2026: Workforce planning workshop planned to progress the HSCP workforce plan. Report P49
  • 30 June 2026: Revised date for several rescheduled audit actions, including case notes and external placement actions. Report P36, P37, P38, P39, P41, P42
  • 2026/27: Three planned internal audit reviews: Financial Management Arrangements, Stakeholder Engagement and Risk Management. Report P13, 2.4

Plain English for the jargon

  • HSCP: Health and Social Care Partnership, the integrated body covering Argyll and Bute.
  • IJB: Integration Joint Board, the body that directs integrated health and social care services.
  • JSP: Joint Strategic Plan, the HSCP's planning document covering a set period.
  • KPI: Key Performance Indicator, a measure used to track progress against objectives.
  • RAG: Red, Amber, Green status used in performance reporting.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Audit and Risk committee noted the progress on completion of the internal audit recommendations. (Reference: Report by Chief Internal Auditor dated 16 June 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute HSCP Audit and Risk Committee

Executive summary

1.1This report updates the Audit and Risk Committee (the Committee) on the work carried out by Argyll and Bute Council’s (the Council) Internal Audit Team on audits which are of operational relevance to the Committee.

1.2One audit has been completed since the last meeting of the Committee on 17 February 2026.

1.3In addition, this paper provides an update on the actions from audit reports already presented to the Committee which were still open as at 31 March 2026.

2. DETAIL

2.1The Council’s internal audit team are the appointed internal auditors for the HSCP and also, as part of delivering the Council’s annual internal audit plan, carry out operational audits on services delivered by the social care element of the HSCP. Audits relating to the HSCP internal audit plan are reported to the HSCP Audit and Risk Committee. Social care audits delivered as part of the Council’s internal audit plan are reported to both the HSCP Audit and Risk Committee and the Council’s Audit and Scrutiny Committee. Similarly audits delivered as part of the HSCP Audit Plan are reported to the Council’s Audit and Scrutiny Committee for information.

2.2Internal audit reports include an action plan with a management response which establish the agreed action, timescale and responsible officer. Internal Audit record these in a database and, on a quarterly basis, follow them up to ensure they are being progressed. Internal Audit will only complete actions where evidence can be provided that the agreed action has been fulfilled appropriately.

Table 1: H&SCP (IJB) Summary of Audit Actions as at 31 March 2026

Service Complete On Track Delayed Total H&SCP (IJB) – Chief Finance Officer 2 0 0 2

H&SCP (IJB) – Adult Services (Hospital 1 0 0 1 & Community Services) H&SCP (IJB) – Strategic Planning, 3 7 3 13 Performance & Technology Total 6 7 3 16

Table 2: H&SCP (SW) Summary of Audit Actions as at 31 March 2026

Service Complete On Track Delayed Total H&SCP (SW) – Adult Services 0 0 1 1 (Complex Care & Registered Services H&SCP (SW) – Children and Families 3 0 4 7 and Justice H&SCP (SW) – Strategic Planning, 1 0 0 1 Performance & Technology H&SCP (SW) – Adult Services (Hospital 0 3 0 3 & Community Services) H&SCP (SW) – Chief Finance Officer 1 0 0 1 Total 5 3 5 13

2.4Work in progress / Future work

The approved 2025/26 Internal Audit Plan is now complete and all elements reported to the Committee. The approved plan for 2026/27 has three planned internal audit reviews, specifically, Financial Management Arrangements, Stakeholder Engagement and Risk Management. Work has commenced to progress these reviews.

3.0RELEVANT DATA AND INDICATORS – NONE

4.0CONTRIBUTION TO STRATEGIC PRIORITIES

4.1Audit reports include agreed actions to strengthen internal control. 5.0 GOVERNANCE IMPLICATIONS

5.1Financial Impact - None

5.2Staff Governance - None

5.3Clinical Governance - None

6.0EQUALITY & DIVERSITY IMPLICATIONS - NONE

7.0GENERAL DATA PROTECTION PRINCIPLES COMPLIANCE

7.1This report in itself does not raise any GDPR issues however consideration of GDPR will feature in audits where appropriate.

8.0RISK ASSESSMENT

8.1The audit planning approach is a risk based one and individual audit reports provide an overall assessment on the management of risk.

9.0PUBLIC & USER INVOLVEMENT & ENGAGEMENT - NONE

10.0CONCLUSIONS

10.1Satisfactory progress is being made implementing audit actions

11.0DIRECTIONS

11.1Directions required Directions to: Tick to Council, NHS No Directions Required X Board or both. Argyll & Bute Council NHS Highland Health Board Argyll & Bute Council and NHS Highland Health Board

REPORT AUTHOR AND CONTACT

Author: Paul MacAskill

Email: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT UPDATEReport 496 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 5 attended
KG
Councillor Kieron GreenChair, present
EA
Emily AustinMember, present
RM
Councillor Ross MorelandMember, present
JP
Janice PrestonMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. INTERNAL AUDIT UPDATEThis decision
  2. Internal audit updateNoted
  3. Internal audit report stakeholder engagementDecided
  4. Internal audit report risk managementDecided
  5. Internal audit contractNoted
  6. Internal audit report direct paymentsDecided

More from Argyll and Bute Argyll and Bute HSCP Audit and Risk Committee

All decisions
MeetingDecisionOutcome
10 Nov 2026 Internal audit updateDecision The Audit and Risk Committee: 1. noted the progress on completion of the internal audit recommendations; 2. ... Noted Open
10 Nov 2026 Internal audit report stakeholder engagementDecision The Audit and Risk Committee endorsed the Internal Audit report on Stakeholder Engagement. (Reference: Repor... Decided Open
10 Nov 2026 Internal audit report risk managementDecision The Audit and Risk Committee endorsed the Internal Audit report on Risk Management. (Reference: Report by Ch... Decided Open
10 Nov 2026 Audited annual acounts 2025/26Decision The Audit and Risk Committee – 1. noted that Mazars were close to completing their audit of the Annual Accou... Noted Open
10 Nov 2026 Annual external audit reportDecision The Audit and Risk Committee noted the Annual Audit Report prepared by Mazars and management responses to th... Noted Open