CONSIDER NOTICE OF REVIEW REQUEST: Land North East of Glenmachrie, Glenegedale, Isle of Islay (Ref: 26/0003/LRB)
AgreedCommittee7 papers
AI summaryArgyll and Bute Local Review Body refused retrospective planning permission for a pod at Glenegedale, Isle of Islay, upholding the planning authority. Enforcement action is live and the structure must be removed within 3 months.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedReview request dismissed, original refusal upheld
MoneyNot stated
What happens nextRemove structure within 3 monthsOr face formal enforcement action
Who it affectsApplicant and nearby plotsGlenegedale, Isle of Islay
What was decided
The Local Review Body refused the application de novo, upholding the planning authority's earlier refusal of 9 April 2026 for the retrospective siting of a pod, septic tank and associated works. Report P8
The refusal is on a single ground: the development is contrary to NPF4 Policy 14 and LDP 2 Policies 5, 8, 9, 10 and 35 because it would harm the area's character and appearance and cause unacceptable residential amenity impacts. Report P54, P58
Why
An earlier planning permission in principle (23/00426/PPP) for a dwellinghouse on the site remains extant until 23 July 2026 but no reserved matters have been submitted, so there is no live permission backing a dwellinghouse to justify the pod. Report P25, P26, P33
Officers considered the pod would represent overdevelopment and create unacceptable overlooking, noise and disturbance for the future occupiers of the approved dwellinghouse and for the adjacent two-house plot approved under 24/02085/PPP. Report P53
The pod sits as an isolated, prominent feature within a rough grazing field and visible from the road, harming the character and appearance of this countryside location. Report P11, P12, P53
What happens next
The existing unauthorised structure should be removed within 3 months of the decision date and the ground restored, to avoid formal enforcement action under the live enforcement case. Report P53
The appellant's stated intention to use the pod to visit the island was not treated as a material planning consideration. Report P28
Options considered
Chosen: Refuse the review and uphold the planning authority's refusal. Pod on its own, without a live dwellinghouse permission, harms character and amenity Report P26, P27, P54
Rejected: Grant planning permission for the pod. Would create overdevelopment and unacceptable residential amenity impacts Report P53, P54
Implications
Legal: An enforcement case is live; failure to remove the structure within 3 months risks formal enforcement action. Report P53
Other: The extant permission in principle 23/00426/PPP for a dwellinghouse on the site expires on 23 July 2026 and no reserved matters have been submitted. Report P25, P33
Future occupiers of the dwellinghouse approved in principle under 23/00426/PPP Report P53
Future occupiers of the two dwellinghouses approved on adjoining land under 24/02085/PPP Report P53
Neighbouring land at Glenmachrie, Glenegedale, Isle of Islay Report P33, P53
Timeline
20.07.2023: Planning permission in principle 23/00426/PPP approved for a dwellinghouse on the site Report P33
20.12.2024: Pre-application advice 24/02197/PREAPP given for holiday pod Report P53
30.01.2025: Application advertised in Oban Times Report P34
09.04.2026: Planning Service refused application 25/00032/PP under delegated powers Report P8
30 June 2026: Statement of Case submitted to the Local Review Body Report P6
23 July 2026: Permission in principle 23/00426/PPP expires if no reserved matters submitted Report P25
14 August 2026: Local Review Body considers the review and refuses
Plain English for the jargon
Local Review Body (LRB): A council committee that re-decides certain planning applications that have been refused by officers.
PPP (Planning Permission in Principle): An approval that establishes the principle of a development, with detailed matters reserved for later approval.
NPF4: National Planning Framework 4, the Scottish Government's national planning policy, adopted 13 February 2023.
LDP 2: Argyll and Bute Local Development Plan 2, adopted 2024.
Reserved Matters: Detailed aspects of a development (such as siting, design and appearance) that must be approved after a Planning Permission in Principle is granted.
De novo: A fresh reconsideration of the case on its merits, rather than a review of the original decision.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3
Resolved
Decision The Argyll and Bute Local Review Body, having considered the merits of the case de novo, agreed to refuse the application and uphold the decision of the Planning authority to refuse planning permission for the following reason(s):- The proposed development is contrary to Policy 14 of NPF4 and Policies 5, 8, 9, 10 and 35 of LDP 2 in that it would, if permitted, create a form of development that would have an unacceptable impact on the character and appearance of the area and cause unacceptable impacts upon residential amenity for existing and future occupiers. (Reference: Notice of Review and Supporting Documents and Comments from Interested Parties and Applicant, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
REFUSAL OF PLANNING PERMISSION REFERENCE 25/00032/PP FOR SITING OF POD, INSTALLATION OF SEPTIC TANK AND ASSOCIATED WORKS (RETROSPECTIVE)
LAND NORTH EAST OF GLENMACHRIE, GLENEGEDALE, ISLE OF ISLAY
30 JUNE 2026 STATEMENT OF CASE
The Planning Authority is Argyll and Bute Council (‘the Council’). The appellant is [name removed] (“the appellant”).
Planning permission 25/00032/PP for the siting of a pod, installation of septic tank and associated works (retrospective) on Land North East of Glenmachrie, Glenegedale, Isle of Islay (“the appeal site”) was refused by the Planning Service under delegated powers on the 9 April 2026.
This decision is the subject of referral to a Local Review Body.
DESCRIPTION OF SITE
The site the subject of this Review is situated to the north east of Glenmachrie, Glenegedale, Isle of Islay comprising an area of rough grazing, generally rectangular in shape, measuring approximately 0.114 hectares in area.
The pod, which has been sited, is broadly rectangular shaped in floor area incorporating a barrel-roof design providing a kitchenette/living/bedroom area, a separate bathroom/ensuite and a decking area.
The materials palette includes grey coloured metrotile roof shingles to the side and roof with natural larch cladding to the front and rear gables.
STATUTORY BASIS ON WHICH THE APPEAL SHOULD BE DECIDED
Section 25 of the Town and Country Planning (Scotland) Act 1997 provides that where, in making any determination under the Planning Act, regard is to be had to the development plan, and all other material planning considerations and the determination shall be made in accordance with the plan unless material considerations indicate otherwise. This is the test for this application.
STATEMENT OF CASE
Argyll and Bute Council considers the determining issues in relation to the case are as follows:
• Whether the site represents an appropriate opportunity for development with the pod and whether it complies with National and Local Planning Policy.
The Report of Handing (Appendix A) sets out the Council’s full assessment of the application in terms of these determining issues.
REQUIREMENT FOR ADDITIONAL INFORMATION AND A HEARING
It is not considered that any additional information is required in light of the appellant’s submission. The issues raised were assessed in the Report of Handling which is contained in Appendix 1. As such it is considered that Members have all the information they need to determine the case. Given the above and that the proposal is small-scale, has no complex or challenging issues, and has not been the subject of any significant public representation, it is not considered that a Hearing is required.
COMMENT ON APPELLANT’S SUBMISSION
The case from the Planning Service is set out in the Report of Handling appended to this statement.
With regards to the Appellant’s submission, Officers have the following comments.
Whilst it is acknowledged that the site benefits from an extant planning permission in principle, reference 23/00426/PPP, until 23 July 2026, this permission merely establishes the principle of a dwellinghouse on the site. To date, no detailed siting or design details for the proposed dwellinghouse on the site have been submitted to the Planning Service for consideration.
In the absence of a live planning permission for the development of the site with a dwellinghouse, the proposed pod is not considered to be an appropriate development, which has resulted in the introduction of an incongruous feature within the site and the wider landscape.
The proposed pod should not be granted permission in isolation without being backed up by an associated live planning permission for the development of the site with a dwellinghouse.
The aspiration of the appellant to utilise the site for the proposed pod to allow them to visit the island is not a material planning matter.
CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Argyll and Bute Local Review Body at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.