ARGYLL AND BUTE EDUCATION SERVICE - PROGRESS AND IMPACT REPORT 2025-2026 AND STRATEGIC PLAN 2026-2029

Noted Committee 2 papers

AI summaryArgyll and Bute's Community Services Committee approved the Education Service Progress and Impact Report 2025-2026 and Strategic Plan 2026-2029, and agreed to publish them and submit them to the Scottish Government.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTo be published and submitted to Scottish Government
Money132,809,3292026-27 Education Service Budget grand total
What happens nextPublish and submit to governmentBoth documents on the Council website
Who it affectsArgyll and Bute school pupils9,583 pupils across schools and ELC settings

What was decided

Noted progress made on the 2024-2026 Education Strategic Plan in the 2025-2026 update.

Approved the Education Service Progress and Impact Report 2025-2026 and Strategic Plan 2026-2029, attached at appendix 1 of the report.

Approved publication of both documents on the Council website and submission of them to the Scottish Government.

Why

The plan continues the council's education vision and strategy, Our Children, Their Future - Thriving Together, which sets priorities around equity, wellbeing, attainment and positive destinations. Report P8, P15, P32, P35

The Strategic Plan is informed by the independent review Connecting for Success - Shaping the Future, which highlighted themes of collaboration, sustainability and system-wide improvement. Report P10, P16

The plan's priorities are aligned with the Scottish Government's National Improvement Framework outcomes and priorities. Report P36, P38, P50, P81

What happens next

Publish the Education Strategic Plan 2026-2029 and the Education Service Progress and Impact Report 2025-2026 on the Council website.

Submit both documents to the Scottish Government.

Take forward the strategic priorities across schools, ELC settings and education services through the 2026-2029 plan period. Report P9, P10, P15, P16

The money

  • 132,809,329 Education Service Budget 2026-27 grand total Report P31
  • 125,703,472 Education Service Budget 2025-26 grand total Report P31
  • 44,220,760 Secondary Education budget 2026-27 Report P31
  • 42,675,456 Primary Education budget 2026-27 Report P31
  • 20,054,464 Early Learning and Childcare budget 2026-27 Report P31
  • 15,168,988 Additional Support for Learning budget 2026-27 Report P31

Options considered

  • Chosen: Approve the Education Service Progress and Impact Report 2025-2026 and Strategic Plan 2026-2029 as recommended. Committee accepted the report and plan, including publication and submission to Scottish Government

Implications

  • Financial: Education Service Budget rises from 125,703,472 in 2025-26 to 132,809,329 in 2026-27, with the largest growth in Additional Support for Learning and Early Learning and Childcare. Report P31
  • Equalities: Plan priorities include equity, closing the attainment gap and targeted support for care experienced children and young people, with 348 such pupils identified. Report P28, P50, P77, P81
  • Staffing: Workforce development and system capacity are highlighted as continuing priorities across the education service. Report P15, P79
  • Legal: Both documents are to be formally submitted to the Scottish Government following approval.
  • Other: The Strategic Plan responds to themes from the independent Connecting for Success - Shaping the Future review of Education Services. Report P10, P16

Who and where

  • 9,583 pupils across primary, secondary and special schools in Argyll and Bute Report P28
  • 231 children attending 98 Early Learning and Childcare settings Report P28
  • 348 Care Experienced Children and Young People Report P28
  • Pupils with Additional Support Needs, with 53% of pupils having recorded ASN Report P28
  • 450 pupils with English as an additional language and 197 learners from refugee and asylum-seeking backgrounds Report P28
  • Learners in Gaelic Medium Education across 7 primary GME settings and 5 secondary schools delivering Gàidhlig Report P28
  • Parents and carers engaged through the Parental Advisory Group and parental survey Report P29
  • Communities across the 28 inhabited islands and rural mainland areas of Argyll and Bute Report P20

Timeline

  • 2025-2026: Reporting period for the Progress and Impact Report Report P2, P3
  • 2026-2029: Period covered by the new Strategic Plan Report P2, P3
  • 2023-2026: Period covered by the provisional 3 Year Stretch Aims in the appendix Report P4
  • June 2026: Provisional attendance and attainment data used in the report Report P70, P72
  • 2026-2029: New stretch aims to be applied following approval Report P4

Plain English for the jargon

  • NIF: National Improvement Framework (Scottish Government)
  • OCTNE: Our Children, Their Nurturing Education
  • ASN: Additional Support Needs
  • ELC: Early Learning and Childcare
  • SIMD: Scottish Index of Multiple Deprivation
  • ACEL: Achievement of a Curriculum for Excellence Level
  • GIRFEC: Getting it Right for Every Child
  • HMIE: His Majesty's Inspectorate of Education
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Community Services Committee: 1. noted the progress made with respect to priority actions within the 2024-2026 Education Strategic Plan (2025-2026 update) outlined in the Education Service Progress and Impact Report 2024-2026; 2. approved the Education Service Progress and Impact Report 2025-2026 and Strategic Plan 2026-2029, attached at appendix 1 of the report; 3. approved the publication of the Education Strategic Plan 2026-2029 and The Education Service Progress and Impact Report 2025-2026 on the Council Website; and 4. approved the submission of the Education Strategic Plan 2026-2029 and The Education Service Progress and Impact Report 2025-2026 to Scottish Government. (Reference: Report by Executive Director with responsibility for Education dated July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Community Services Committee

Appendix 1

Education Service Progress and Impact Report 2025-2026 and Strategic Plan 2026-2029 1 Education Service Progress and Impact Report and Strategic Plan 2025–2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1 b Education Service Progress Report 2025-2026 and Strategic Plan 2026-2029Report 3.8 MB DownloadRead as text
PDF
ARGYLL AND BUTE EDUCATION SERVICE: PROGRESS AND IMPACT REPORT 2025-2026 AND STRATEGIC PLAN 2026-2029Report 201 KB Download

At this meeting

Whole meeting

Who was there

12 of 26 attended
KM
Katie McKenzieSecretary, expected
GI
Gary I'AnsonPublic, expected
AM
Anthony McGloinPublic, expected
AM
Anthony MallonPublic, expected
FG
Fraser GrantPublic, expected
JM
Joe McKayPublic, expected
FM
Fiona McCallumSecretary, expected
JB
Councillor Jan BrownMember, apologies
MC
Councillor Maurice CorryMember, present
AF
Councillor Audrey ForrestMember, present
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyMember, apologies

All 26 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ARGYLL AND BUTE EDUCATION SERVICE - PROGRESS AND IMPACT REPORT 2025-2026 AND STRATEGIC PLAN 2026-2029This decision
  2. Argyll and bute outcomes and improvement plan - priorities updateNoted
  3. Argyll and Bute Climate Action NetworkNoted
  4. Argyll and bute improvement plan - priorities updateNoted
  5. Argyll and bute improvement plan - priorities updateNoted
  6. Argyll and bute harbour board workplanNoted

More from Argyll and Bute Community Services Committee

All decisions
MeetingDecisionOutcome
27 Aug 2026 Police scotland argyll & bute performance summary report - reporting period: april 2026 - june 2026Decision The Community Services Committee reviewed and noted the contents of the report. (Reference: Report for April... Noted Open
27 Aug 2026 Scottish fire and rescue service - argyll & bute performance and scrutiny group 2026-27 q1 scrutiny reportDecision The Community Services Committee reviewed and noted the contents of the report. (Reference: Q1 2026/27 Repor... Noted Open
27 Aug 2026 Argyll & bute health & social care partnership - performance report - fq4 2025/26 (january - march)Decision The Community Services Committee: acknowledged performance for FQ4 2025/26 (January - March) against latest ... Decided Open
27 Aug 2026 Qualification scotland school examination results 2026Decision The Community Services Committee: 1. noted the guidance from QS, detailed at paragraph 4.3 of the report, ab... Noted Open
27 Aug 2026 Developing the young workforce - 2025-2026Decision The Community Services Committee: 1. noted the scope, variety and impact of DYW initiatives and activities a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies