CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 2 September 2026 at 10.30am

LOCHGILPHEAD CONSERVATION AREA REGENERATION SCHEME (CARS) - FINAL PROJECT REPORT

Noted Committee 1 paper

AI summaryThe Mid Argyll, Kintyre and the Islands Area Committee noted the completion of the Lochgilphead CARS heritage regeneration scheme, which ran from April 2020 to March 2026 with a final budget of £2.3 million.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMembers recorded successful delivery of Lochgilphead CARS
Money£2.3 million final budgetUp from £1.6 million originally, £1,368,429.92 paid in grants
What happens nextFinal report to HESRegeneration Outputs Report and Final Accounts to be submitted
Who it affectsLochgilphead town centreHistoric buildings, businesses, residents and visitors

What was decided

The committee noted the successful delivery of Lochgilphead CARS as set out in section 4 of the report. Report 1.1, 4.0

The committee noted additional building projects delivered beyond the original CARS plan, as set out in paragraph 4.5. Report 4.5

The committee noted the critical funding role played by Historic Environment Scotland in supporting the regeneration of Lochgilphead. Report 4.1

Why

The scheme aimed to safeguard historic buildings, support economic and social enhancement, and provide training in traditional skills. Report 1.2, 4.1

Additional funding from the council and the Place Based Investment Programme allowed six priority building projects to be delivered instead of the three originally planned. Report 4.4, 4.5, P14

A public survey of 188 responses found 80% of respondents said the scheme had improved the town. Report 4.12

What happens next

Officers will finalise and submit a Regeneration Outputs Report and Final Accounts to Historic Environment Scotland. Report 4.11

Historic Environment Scotland retains 10% of its £969,700 grant award until the final reporting and evaluation has been reviewed and signed off. Report P34, 6.2

Some legal support will be required for up to fifteen years to deal with third party grant related matters. Report 6.3

The money

  • £1,606,065 Original total common fund including owner contributions Report P12, P31
  • £2,298,431 Final common fund after additional funding from ABC and PBIP Report P12, P32
  • £1,368,429.92 Total grant funding committed and paid Report P33
  • £969,700 Historic Environment Scotland original grant award Report P12
  • over £90,000 Total of further grants to local businesses from other funds Report 4.10
  • £1.36 million Total of 32 grants awarded through the scheme Report 4.13

Implications

  • Financial: All grant funding has been committed and paid, with Historic Environment Scotland retaining 10% of its grant until final reporting and evaluation is signed off. Report 6.2, P33, P34
  • Legal: Ongoing legal support will be needed for up to fifteen years to deal with third party grant related matters. Report 6.3
  • Staffing: Project staff are now employed in other roles, with limited resource still required for CARS related enquiries and third party grant matters. Report 6.4
  • Risk: The release of the retained 10% of the Historic Environment Scotland grant depends on submission and sign off of the final reporting and evaluation. Report P34, 4.11
  • Other: The grant is expected to improve the socio-economic status of the town by making it a more attractive place to visit. Report 6.8

Who and where

  • Owners and tenants of six priority tenement buildings, safeguarding 21 flats and 12 commercial premises Report 4.13, P14
  • Local businesses that received shopfront grants or other regeneration support Report 4.7, 4.10
  • Lochgilphead High School pupils, UHI Argyll students and local tradespeople who took part in training Report 4.8, P19
  • Town centre workers, with 85 jobs reported as safeguarded Report 4.13
  • Mid Argyll residents and visitors to Lochgilphead town centre Report 4.12

Timeline

  • April 2020: Lochgilphead CARS scheme started Report 1.2, 4.1
  • 31st March 2026: Scheme ended with all agreed outcomes delivered or exceeded Report 1.1, 1.2
  • 22 July 2026: Final project report dated
  • 2nd September 2026: Area committee meeting considered the final report

Plain English for the jargon

  • CARS: Conservation Area Regeneration Scheme, a grant programme for historic building repair
  • HES: Historic Environment Scotland, a public body that funds heritage regeneration
  • PBIP: Place Based Investment Programme, a Scottish Government fund
  • PSHG: Private Sector Housing Grant
  • CIC: Community Interest Company, a type of social enterprise
  • NOCN: National Open College Network, an awarding organisation for vocational qualifications
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Decision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lochgilphead CARS had been successfully delivered as detailed in section 4 of the report; 2. the additional building projects that had been delivered in addition to the original CARS projects as detailed in paragraph 4.5 of the report; 3. the critical funding role that Historic Environment Scotland had played supporting the regeneration of Lochgilphead. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 22 July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Executive summary

1.1This report provides members with an update and review of the Lochgilphead Conservation Area Regeneration Scheme (CARS). The project ended on 31st March 2026 with all agreed outcomes delivered or exceeded.

1.2Lochgilphead Conservation Area Regeneration Scheme (CARS) was a grant programme that started in April 2020 and ended in March 2026. The scheme focused on the regeneration of historic buildings as well as traditional skills training and educational activities and was funded by Historic Environment Scotland (HES), private owners, and Argyll and Bute Council. 1.3 During the delivery of Lochgilphead CARS, the original budget of £1.6 million was increased to £2.3 million. This enabled stakeholders to deliver six Priority Building projects instead of the planned three projects, together with other associated heritage improvements. 1.4 Lochgilphead CARS was a successful heritage led regeneration project that has significantly enhanced the built fabric and appearance of Lochgilphead town centre. Building on the success of previous investments in Lochgilphead, the CARS project has provided further evidence that town centre regeneration can yield improvements in the infrastructure, help retain and attract new businesses, and enhance the fabric of our towns providing attractive and vibrant town centres for businesses and residents, assisting the local economy and improving the quality of life for our local communities and visitors.

Recommendations

It is recommended that the Mid Argyll, Kintyre and the Islands Area Committee: a) Consider the the content of the report and note that Lochgilphead CARS has been successfully delivered as detailed in section 4. b) Note the additional building projects that have been delivered in addition to the original CARS projects as detailed in paragraph 4.5. c) Note the critical funding role that Historic Environment Scotland has played supporting the regeneration of Lochgilphead. ARGYLL AND BUTE COUNCIL MID ARGYLL, KINTYRE AND THE ISLANDS AREA COMMITTEE DEVELOPMENT AND ECONOMIC 2nd SEPTEMBER 2026 GROWTH

LOCHGILPHEAD CONSERVATION AREA REGENERATION SCHEME (CARS) – FINAL PROJECT REPORT

2.0INTRODUCTION

2.1This report provides members with an update and review of the Lochgilphead Conservation Area Regeneration Scheme (CARS). The project ended on 31st March 2026 with all agreed outcomes delivered or exceeded.

3.1It is recommended that the Mid Argyll, Kintyre and the Islands Area Committee:

a) Consider the the content of the report and note that Lochgilphead CARS has been successfully delivered as detailed in section 4. b) Note the additional building projects that have been delivered in addition to the original CARS projects as detailed in paragraph 4.5. c) Note the critical funding role that Historic Environment Scotland have played supporting the regeneration of Lochgilphead.

4.0DETAIL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LOCHGILPHEAD CONSERVATION AREA REGENERATION SCHEME (CARS): FINAL PROJECT REPORTReport 217 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
JA
Councillor John ArmourChair, present
JB
Councillor Jan BrownMember, present
IC
Iona CampbellSecretary, expected
GC
Councillor Garret CornerMember, present
AH
Councillor Anne HornMember, present
JK
Councillor Jennifer KeanMember, apologies
TM
Councillor Tommy MacPhersonMember, present
DM
Councillor Dougie McFadzeanVice-Chair, present
KM
Katie McKenzieSecretary, expected
JS
Julieann SmallSecretary, expected
AR
Councillor Alastair RedmanMember, present

On this subject at Argyll and Bute

Search all
  1. LOCHGILPHEAD CONSERVATION AREA REGENERATION SCHEME (CARS) - FINAL PROJECT REPORTThis decision
  2. Lochgilphead conservation area regeneration scheme (cars) - final project reportNoted
  3. Conservation area regeneration scheme (cars) project 15-19 argyll street, lochgilpheadApproved
  4. Conservation Area Regeneration Scheme (CARS) Projects - 2-4 and 6-10 Argyll Street, LochgilpheadApproved
  5. Conservation area regeneration scheme (cars) project: 3-17 colchester square, lochgilpheadApproved
  6. Lochgilphead Conservation Area Regeneration Scheme (CARS) GovernanceAgreed

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open
2 Sep 2026 Draft mid argyll, kintyre and the islands area committee workplanDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the workplan. (Reference: Mid A... Noted Open