Oban Lorn & The Isles Area Committee, Wednesday 9 September 2026 at 10.30am

Oban PVA Flood Risk Management Update

Noted Committee 1 paper

AI summaryArgyll and Bute councillors note Oban flood risk update and resource limits on seeking further funding, while £1.8m is allocated to wider FRM works.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee considered report, noted funding resource limits
Money£1.8m securedFrom £42m Scottish Government allocation for FY 2026/27
What happens nextInspections and repairsNext Black Lynn Burn inspection March 2027
Who it affectsOban PVA areaResidents, businesses and infrastructure at flood risk

What was decided

The committee considered the contents of the Oban flood risk management update report. Report 3.1

Members noted the lack of resources within the Flood Risk Management team to investigate securing additional funding for Oban PVA flood risk management. Report P8, 3.1, P34

Why

Oban is a SEPA designated Potentially Vulnerable Area where flood risk is made worse by heavier rainfall and the town's topography, and a full scheme would cost tens of millions and depends on an 80% Scottish Government capital grant. Report 1.1, 2.0, 2.1, P34

Audit Scotland found the national funding mechanism for major flood schemes is not fit for purpose, and Cycle 1 scheme costs nationally escalated from about £350m to over £1bn, fully committing the central pot. Report P21

Reports of flooding heard locally are often not passed formally to the Flood Risk Management team, leaving a data gap that hampers identification of low cost, short term remedial works. Report P5, P31, 6.0

What happens next

Quarterly reporting to the Oban, Lorn and the Isles Area Committee will continue, with two in person community sessions per year, the next once technical updates from the flood study review are ready. Report P29, P34

Clearance of trollies, trees and other obstructions and replacement of the most crucial flap valves along Black Lynn Burn will be commissioned before winter 2026/27. Report P28

The Flood Risk Management team will keep making representations to the Scottish Government, including exploring phased delivery of any future scheme, subject to confirmation that this would not jeopardise the 80% capital grant and required benefit to cost ratio. Report P34, 6.0

The money

  • £1.8m Flood resilience allocation from the Scottish Government £42m FY 2026/27 pot, restricted to statutory Local Flood Risk Management Plan actions Report P6, P23
  • ~£350m Original national estimate for Cycle 1 flood protection scheme costs Report P21
  • over £1bn Escalated national estimate for Cycle 1 flood protection scheme costs Report P21

Implications

  • Financial: Lack of a long term funding settlement for Cycle 2 flood protection schemes creates significant budget uncertainty, and no funding is currently identified for a long term Oban solution. Report 6.0, P22
  • Legal: The Council has four key statutory duties under the Flood Risk Management (Scotland) Act 2009 covering maps, assessments, local flood risk management plans and clearance and repair works. Report 6.0
  • Risk: There is a reputational risk if the distinction between protected habitable property and non protected amenity land is not clearly communicated, and a risk of missed mitigation opportunities if flood incident data is not shared with the technical team. Report 6.0
  • Climate: All future modelling for Oban will incorporate the latest SEPA climate change allowances to ensure any proposed scheme is resilient to future conditions. Report 6.0
  • Equalities: An Equalities and Socio Economic Impact Assessment will be required as and when long term solutions can be progressed. Report 6.0
  • Staffing: The Flood Risk Management team has no current resource to explore additional funding avenues, and additional staffing would be needed to do so. Report P34

Who and where

  • Residents and businesses within the Oban Potentially Vulnerable Area Report 1.1, 2.1
  • Vulnerable groups including older residents, disabled people and low income households who are disproportionately affected by flooding Report P21
  • Asset owning council services responsible for car parks and commercial units such as at Lochavullin Report P4, 4.2
  • The Council's Roads and Infrastructure Services operations team Report 4.2, 4.4

Timeline

  • 22nd January 2026: Oban PVA Flood Risk Management Session held, attended by a councillor and two members of the public representing Oban Community Council Report P19, P29
  • March 2026: Inspection of Black Lynn Burn from railway culvert to shore Report P17, P27
  • between June and September 2026: Treatment of non native invasive species around Black Lynn Burn by RIS Operations team Report 4.4
  • 9 September 2026: Area Committee considers this update report Report P9
  • before winter 2026/27: Clearance works and replacement of the most crucial flap valves to be commissioned Report P28
  • March 2027: Next scheduled watercourse inspection of Black Lynn Burn and its tributaries Report P27

Plain English for the jargon

  • PVA: Potentially Vulnerable Area, a SEPA designation for places at significant flood risk
  • FRM: Flood Risk Management
  • FPS: Flood Protection Scheme, a formal capital scheme for flood defence works
  • LFRMP: Local Flood Risk Management Plan, the statutory plan setting out flood risk actions for an area
  • BCR: Benefit to Cost Ratio, used in HM Treasury Green Book to assess value for money of flood schemes
  • SEPA: Scottish Environment Protection Agency, the national flood and environment regulator
  • RIS Operations: Roads and Infrastructure Services operations team within Argyll and Bute Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Decision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the constraints around resources to investigate the securing of additional funding for Flood Risk Management in Oban PVA. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated September 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1The Oban Potentially Vulnerable Area (PVA) continues to face significant flood risk challenges, exacerbated by increasing rainfall intensities and the town’s specific topography. This report provides an update on the strategic, risk-based management approach for this PVA.

1.2The primary focus of the Flood Risk Management (FRM) team is the protection of habitable floor levels and critical infrastructure, in line with national funding criteria. Key takeaways from this update include:

• Infrastructure Optimization: The Lochavullin Car Park pump system has been repaired and optimized. However, it must be recognized as a drainage aid for "nuisance" flooding; it is not a formal Flood Protection Scheme and will be reached by its mechanical capacity during extreme events.

• Asset Responsibility: While the FRM team manages strategic drainage, the operational resilience of specific Council assets (such as car parks and commercial units) remains the responsibility of the respective asset-owning services.

• Data-Driven Mitigation: A critical gap has been identified between localized flooding reports heard by Elected Members and the formal data held by the FRM team. Closing this gap is essential for identifying low-cost, short-term remedial works while long-term capital funding is awaited.

• Funding Realities: A full Oban Flood Protection Scheme (FPS) remains a multi-million pound capital requirement. The £1.8m recently secured by the Council from the Scottish Government will be distributed in accordance with the Local Flood Risk Management Plans. These funds are prioritised for statutory actions and preparatory works for Cycles 2 & 3.

1.3Until such time as large-scale capital funding is secured, the Council will continue to prioritize proactive watercourse inspections, statutory clearance and repair works, and enhanced community engagement to manage residual risk.

Recommendations

It is recommended that the Oban, Lorn and the Isles Area Committee: • Consider the contents of this report. • Note the constraints around resources to investigate the securing of additional funding for Flood Risk Management in Oban PVA. ARGYLL AND BUTE COUNCIL OBAN, LORN & THE ISLES AREA COMMITTEE ROADS AND INFRASTRUCTURE 9 SEPTEMBER

OBAN PVA FLOOD RISK MANAGEMENT UPDATE

2.0INTRODUCTION

2.1Oban has experienced numerous incidents of significant flooding, with the town being designated by SEPA as a “Potentially Vulnerable Area” (“PVA”) in the Highland and Argyll Local Flood Risk Management Plan (2022 – 2028). 2.2 A number of short-medium and medium-long-term actions to mitigate flooding in Oban have been identified by Infrastructure Design’s Flood Risk Management Team. These actions are being progressed where funding and resources allow. 2.3 There is currently no identified funding for the medium-long term actions to design and construct an Oban Flood Protection Scheme and to deliver the larger Surface Water Management Plan actions. In accordance with national funding frameworks, any future capital investment must be strictly prioritized based on a Benefit-Cost Ratio (BCR) that favours the protection of high-value receptors. This includes the preservation of habitable floor levels and the maintenance of critical road and infrastructure networks, which serve as essential lifelines during extreme weather events. It must be noted that these actions will be significant and are likely to run to tens of millions of pounds requiring attenuation/water storage and general climate change adaptation measures aimed at mitigating or minimising disruption from severe weather events. Without a confirmed 80% Capital Grant from the Scottish Government, the delivery of a formal Scheme remains a significant financial risk.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Oban PVA Flood Risk Management UpdateReport 279 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
KC
Karen CampbellSecretary, expected
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainVice-Chair, present
JL
Councillor Jim LynchMember, apologies
LM
Councillor Luna MartinMember, present
JM
Councillor Julie McKenzieMember, present
KM
Katie McKenzieSecretary, expected
AV
Councillor Andrew VennardMember, apologies

On this subject at Argyll and Bute

Search all
  1. Oban PVA Flood Risk Management UpdateThis decision
  2. Oban pva flood risk management updateNoted
  3. Oban pva flood risk management updateDecided

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open
9 Sep 2026 Supporting Communities Fund Applications 2026/27Decision The Oban, Lorn and the Isles Area Committee agreed that the 17 applications, marked as ‘Award’ or ‘Partial A... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies