Planning, Protective Services and Licensing Committee, Tuesday 15 September 2026 at 10.30am

BEAUFORT WIND LIMITED: ERECTION OF 7 TURBINES (UP TO 149.9M TO TIP) AND ANCILLARY DEVELOPMENT AND DECOMMISSIONING OF EXISTING BEINN GHLAS WIND FARM: EXISTING BEINN GHLAS WIND FARM, TAYNUILT (REF: 25/01240/PP)

Agreed Planning 2 papers

AI summaryArgyll and Bute planning committee approves seven turbines up to 149.9m at Beaufort Wind near Taynuilt, with decommissioning of the existing Beinn Ghlas wind farm, subject to a 35 year operational limit.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSeven turbines up to 149.9m, plus Beinn Ghlas decommissioning
MoneyNot stated
What happens nextCommence within 5 yearsPermission runs 35 years from final commissioning
Who it affectsTaynuilt areaWind farm development and decommissioning

What was decided

The committee granted planning permission for seven wind turbines up to 149.9m to tip and ancillary development, with decommissioning of the existing Beinn Ghlas wind farm near Taynuilt (reference 25/01240/PP). Report P3

Conditions require development to be carried out in line with the EIA Report dated 25.07.25, application form dated 21.07.25, and the listed approved drawings.

The permission endures for 35 years from final commissioning, with decommissioning and restoration required within three years of generation ceasing.

Why

Conditions require a decommissioning, restoration and aftercare strategy, including habitat and biodiversity enhancement, to be approved by the planning authority in consultation with SEPA and NatureScot before development begins.

The permission period and decommissioning requirements are set to minimise visual intrusion and ensure satisfactory site reinstatement.

What happens next

The developer must submit and obtain approval of a decommissioning, restoration and aftercare strategy before any development commences.

The developer must notify the planning authority of the intended commencement date at least one calendar month before starting, and confirm first and final commissioning dates within one month of each.

Development must begin no later than five years from the date of consent.

Implications

  • Climate: Existing Beinn Ghlas wind farm must be decommissioned and the site restored, with the strategy to include habitat and biodiversity enhancement opportunities.
  • Legal: The development must be implemented in accordance with the EIA Report and approved details, with any amendments requiring prior written approval under Section 64 of the Town and Country Planning (Scotland) Act 1997.
  • Risk: The 35 year permission period and three year decommissioning window are designed to minimise long term visual intrusion and ensure site reinstatement.

Who and where

  • Beaufort Wind Limited, the applicant
  • Taynuilt area near the application site Report P1, P3

Timeline

  • 21.07.25: Application form dated
  • 25.07.25: Environmental Impact Assessment Report dated
  • 2026-09-15: Planning, Protective Services and Licensing Committee meeting
  • Within 5 years of consent: Development must commence
  • 35 years from final commissioning: Generation must cease
  • Within 3 years of generation ceasing: Decommissioning and restoration to be completed

Plain English for the jargon

  • EIA Report: Environmental Impact Assessment Report
  • FEI submissions: Further Environmental Information submissions
  • SEPA: Scottish Environment Protection Agency
  • NatureScot: Scotland's nature agency
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - Approved Details & Standard Notes – EIA Development The development shall be implemented in accordance with the details specified on the application form dated 21.07.25 and the Environmental Impact Assessment Report dated 25.07.25, supporting information and the approved drawings listed in the table below unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. The developer and subsequent operators shall at all times construct and operate the development hereby permitted in accordance with the provisions of the Environmental Impact Assessment Report (and FEI submissions), accompanying the application with mitigation measures adhered to in full, and shall omit no part of the operations provided for by the permission except with the prior written approval of the Planning Authority. Plan Title. Plan Ref. No. Version Date Received Location Plan Fig 1.1 Rev 05 02.09.25 Site Aerial Context Fig 1.2 Rev 05 02.09.25 Site Layout (Full) Fig 2.5a Rev 05 02.09.25 Site Layout (zoomed) Fig 2.5b Rev 14 10.08.26 Inset 1: Temporary Compound 1 Fig 2.5c - 02.09.25 Inset 2: Temporary Compound 2 Fig 2.5d - 02.09.25 Existing Substation & Indicative Induction Reactor Layout Fig 2.13 Rev 02 02.09.25 Existing Substation & Indicative Induction Reactor Elevation view Fig 2.14 Rev 02 02.09.25 Indicative Wind Turbine Fig 2.6 Rev 03 02.09.25 Indicative Wind Turbine Foundation Fig 2.7 Rev 02 02.09.25 Indicative Crane Hardstanding Fig 2.8 Rev 02 02.09.25 Indicative Permanent Anemometer Mast Details Fig 2.9 Rev 02 02.09.25 Indicative Access Track Details Fig 2.11 Rev 03 02.09.25 Access Junction Design Fig 10.4 Rev 03 02.09.25 Indicative Site Access (A85 to Fearnoch ) Fig 2.10a Rev 03 02.09.25 Indicative Site Access ( Fearnoch Forest Track) Fig 2.10b Rev 04 02.09.25 Indicative Site Access ( Fearnoch Forest Track to C32 Glen Lonan Road) Fig 2.10c Rev 04 02.09.25 Indicative Temporary Construction Compound Access Options -Glen Lonan Road Fig 2.10d Rev 02 02.09.25 Indicative Cable Trench Details Fig 2.12 Rev 02 02.09.25 Reason: For the purpose of clarity, to ensure that the development is constructed and operated in the manner advanced in the Environmental Impact Assessment Report, upon which the environmental effects of the development have been assessed and determined to be acceptable. 2. Notification of Date of First Commissioning and Final Commissioning . (1) Written confirmation of the Date of First Commissioning shall be provided to the Planning Authority no later than one calendar month after that date. (2) Written confirmation of the Date of Final Commissioning shall be provided to the Planning Authority no later than one calendar month after that date. Reason: To allow the Planning Authority to calculate the date of expiry of the consent. 3. Commencement of Development (1) The Development shall be commenced no later than five years from the date of this consent, (2) Written confirmation of the intended date of Commencement of Development shall be provided to the Planning Authority as soon as is practicable after deciding on such a date and in any event no later than one calendar month prior to the Commencement of Development. Reason: To ensure that the consent is implemented within a reasonable period and to allow the Planning Authority to monitor compliance with obligations attached to this consent and deemed planning permission as appropriate. 4. Period of Permission The planning permission hereby granted shall endure for a period of 35 years from the date of final commissioning. Written confirmation of the date of final commissioning shall be provided to the planning authority no later than one calendar month after that date. Reason: In order to define the terms of this permission, to minimise the level of visual intrusion, and to ensure the satisfactory reinstatement of the site. 5. Decommissioning The development shall cease to generate electricity by no later than the date falling 35 years from the date of final commissioning. The decommissioning and restoration of the site shall be completed within three years from the date on which the development ceases to generate electricity unless otherwise agreed in writing with the planning authority. Reason: In order to define the terms of this permission, to minimise the level of visual intrusion, and to ensure the satisfactory reinstatement of the site. 6. Decommissioning, Restoration and Aftercare Strategy No development shall commence unless a decommissioning, restoration and aftercare strategy has been submitted to and approved in writing by the planning authority in consultation with SEPA and NatureScot. The scheme shall detail measures for the decommissioning of the development, restoration and aftercare of the site and will include, without limitation, proposals for the removal of the above ground elements of the development, the treatment of ground surfaces, opportunities for habitat and biodiversity enhancement, the management and timing of the works, and environmental management provision. Reason: To ensure the decommissioning and removal of the Development in an appropriate and environmentally acceptable manner and the restoration and aftercare ... view the full minutes text for item 4.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Application Site

0 405 810 1,620 Meters

Location Plan relative to; 25/01240/PP O © Crown Copyright and database right 2025 All rights reserved. OS license (customer) account number AC0000849384

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25_01240_PPReport 1.8 MB DownloadRead as text
PDF
BEAUFORT WIND LIMITED: ERECTION OF 7 TURBINES (UP TO 149.9M TO TIP) AND ANCILLARY DEVELOPMENT AND DECOMMISSIONING OF EXISTING BEINN GHLAS WIND FARM: EXISTING BEINN GHLAS WIND FARM, TAYNUILT (REF: 25/01240/PP)Report 859 KB Download

At this meeting

Whole meeting

Who was there

9 of 14 attended
KM
Katie McKenzieSecretary, expected
GB
Councillor Gordon BlairChair, present
JB
Councillor Jan BrownMember, apologies
KG
Councillor Kieron GreenVice-Chair, present
DH
Councillor Daniel HampseyMember, apologies
GH
Councillor Graham HardieMember, apologies
FH
Councillor Fiona HowardMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainMember, present
PD
Councillor Paul Donald KennedyMember, apologies
RK
Councillor Reeni Kennedy-BoyleMember, present
LM
Councillor Liz McCabeMember, present

All 14 on the meeting page

On this subject at Argyll and Bute

Search all
  1. BEAUFORT WIND LIMITED: ERECTION OF 7 TURBINES (UP TO 149.9M TO TIP) AND ANCILLARY DEVELOPMENT AND DECOMMISSIONING OF EXISTING BEINN GHLAS WIND FARM: EXISTING BEINN GHLAS WIND FARM, TAYNUILT (REF: 25/01240/PP)This decision
  2. Beaufort wind limited: proposal of application notice for development of up to 7 wind turbines (up to 149.9 metres to tip) and associated infrastructure.Noted

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open
19 Aug 2026 Civic government (scotland) act 1982: taxi fare scale reviewDecision The Committee agreed to proceed with the 5% increase as previously proposed at their meeting on 17 June 2026... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies