Resolved
Decision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by , dated 1 October 2026, submitted)
AI summaryThe Bute and Cowal Area Community Planning Group noted Transport Scotland's update on maintenance, completed work, safety measures and plans for the A82 and A83. [D] [P1] [P2] [P4] [P5] [P6] [P7] [P16]
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Decision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by , dated 1 October 2026, submitted)
TS Roads Update;
Winter maintenance & monitoring regime commenced on 1st October.
There have been a number of incidents on the A83 & A82 as a consequence of the recent storm over the weekend 24th & 25th October. The incidents were gerally trees falling on the road which in turn were dealy with timeously over the weekend with all routes open for business on Monday morning.
TS/BEAR Scotland have recently completed works;
• A83 – Re-surfacing works at North & South of Arden Roundabout, South of Luss & North of Firkin Point
• A82 – SID has now been installed at Tarbet with additional road markings planned for later this year
Upcoming works planned for next 3 month period;
• A82 – Re-surfacing works at South of Tarbet Isle & North of Inverarnan
• A83 – Further landscape & vegetation on the A82 between Balloch/Tyndrum as well as along the A83 is planned for later this financial year as part of our “Look & Feel” exercise
• A82 – Drainage works at Still Brae, Tarbet
• A82 – The filter material renewal & drainage upgrade works at Stoneymollen to Arden RAB continues this financial yearbon footprint of the scheme
RaBT update;
After a planned pause in traffic management operations at the Rest and Be Thankful, the traffic signals were resumed during mid-October with works initially focused on the lower slopes adjacent to the A83 Trunk Road, with subsequent works including channel maintenance, debris flow barrier maintenance, and westbound drainage improvements. These critical interventions are programmed to continue through to spring 2027, helping to maintain the resilience, safety, and reliability of this key transport corridor. Embankment stabilisation works between Loch Restil & Butterbridge are now complete.
Other Points of Interest;
• A83 - The current road safety works at Cairndow are still on hold as we are still waiting for the energy company to provide final electrical connections. TS/BEAR staff continue to liaise with SSE to ensure connections are carried out as soon as practicable, noting that we have recently been advised that SSEN now have a preferred route option for their connection
• A82 – Ongoing speed monitoring has identified that vehicle speeds within Tarbet remain a concern. As a result, additional measures are currently being investigated to further encourage compliance and improve safety for residents, visitors, and road users. We are developing a package of further interventions subject to the necessary approvals and programming.
• A82 - Temporary Average Speed Cameras (TASC) in place on the A82 between Arden–Tarbet are still in operation
• A82 - Loch Lomond Lay-bys/Rest Area signing strategy & Junctions Improvement scheme design is still ongoing with BEAR progressing designs for introduction of VAS signs at key junctions such as Duck Bay, Cameron House, Luss junctions.
• A82 - Loch Lomond Golf Club VRS design is still ongoing & construction is currently planned for Autumn of this year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transport ScotlandReport | 58 KB | DownloadRead as text |
Follow Bute and Cowal Area Community Planning Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Community planning partnership management committee meeting highlightsDecision The Bute and Cowal Area Community Planning Group noted the contents of the report. (Reference: Report by Par... | Noted | Open |
| 3 Nov 2026 | Argyll and bute improvement plan - priorities updateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Verbal update f... | Noted | Open |
| 3 Nov 2026 | Heartstart Cowal and Cowal Peninsula Community First RespondersDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Verbal update f... | Noted | Open |
| 3 Nov 2026 | Police Scotland UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Polic... | Noted | Open |
| 3 Nov 2026 | Scottish Fire and Rescue Service UpdateDecision The Bute and Cowal Area Community Planning Group noted the information provided. (Reference: Report by Scott... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.