ARUN DISTRICT COUNCIL REPORT TO AND DECISION OF AUDIT & GOVERNANCE COMMITTEE ON 14 FEBRUARY 2019
PART A : REPORT SUBJECT: Annual Internal Audit Plan 2019/20
REPORT AUTHOR: Stephen Pearse, Chief Internal Auditor DATE: February 2019 EXTN: 37561 PORTFOLIO AREA: Corporate Support
EXECUTIVE SUMMARY: Each year Internal Audit is required to develop and annual audit plan for the following financial year, for agreement by the Audit & Governance Committee
RECOMMENDATIONS: Members of the Audit & Governance Committee are requested to agree the outline Annual Internal Audit Plan
1. BACKGROUND: Each year Internal Audit is required to develop an annual audit plan for the following financial year.
This provides the opportunity for the Chief Internal Auditor, in consultation with senior managers within the Authority and with members of the Audit & Governance Committee, to determine where best the limited resources available to Internal Audit should be directed. In order to prepare the plan, consideration has been given to accepted best practice, as promulgated by both CIPFA and the Chartered Institute of Internal Auditors.
The section continues to operate with 2 FTE in the short-term, with the focus on mandatory and high priority work. Now that the Council’s revised structures / operations are largely finalised, consideration can be given to resourcing for the future).
As at the start of 2019, there are still a number of Council strategies (e.g. Customer Access, Digital, etc.) to be progressed that may result in work for the section. There also remains considerable uncertainty regarding a number of areas e.g.:- - the Council’s ongoing financial position, as impacted by central Government policy / funding changes and potential knock-on effects from cuts elsewhere e.g. WSCC - the impact of Brexit arrangements once agreed by central Government and the impact on the requirements for / provision of Council services - potential change to political will as a result of the May 2019 District elections. These may require further operational changes to meet new and changed requirements / legislation.
In view of this, an outline-only plan is attached for the agreement of the Committee and there will again need to be considerable flexibility through the year as to the assignment of resource to specific tasks. (NB - the outline plan has been prepared to be generally in line with the allocations that had been considered for the indicative common plan that had been drafted and included in the shared services business case in 2016). As agree with management, it is currently anticipated that work will be required (timing and scope to be agreed) at some stage in the year on e.g.:- - the Housing service (after the restructure has been completed) - the Office 365 implementation project - the Northgate replacement / upgrade project (Revenues and Benefits software) - the Council’s Medium Term Financial Strategy, giving consideration to resilience and sustainability (linked to the issue of CIPFA’s Financial Management Code which is expected later in 2019). These will be accommodated within the proposed outline plan and reports on the progress of work being undertaken will be provided to meetings of the Audit & Governance Committee through the year, as is currently the case.
Should there be a significant change during the year in the work to be undertaken by the section or in the resource available to it, then a revised Plan will be prepared and advised to the Committee.
2. PROPOSAL(S): It is proposed that the Committee agrees the outline Annual Internal Audit Plan for 2019/20 3. OPTIONS: To agree the outline Annual Internal Audit Plan for 2019/20, or not 4. CONSULTATION:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ANNUAL INTERNAL AUDIT PLANAgenda | 107 KB | DownloadRead as text |
Follow Audit, Governance and Standards Committee at Arun and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Start TimesRESOLVED That its start times for meetings for 2026/27 be 6.00pm. | Decided | Open |
| 13 Jul 2026 | Draft Statement of Accounts 2025-26RESOLVED that a) It notes the draft Statement of Accounts 2025/26 published as at 26 June 2026, contained in Appendix... | Approved | Open |
| 13 Jul 2026 | Treasury Management - Annual Report 2025/26RESOLVED that 2.1. the annual treasury management report for 2025/26 ... view the full minutes text for item 126. | Decided | Open |
| 23 Feb 2026 | Review of Local Assessment ProcedureRESOLVED That the operation of the Local Assessment Procedure (Appendix A) and Hearings (Assessment Panel) Procedure ... | Decided | Open |
| 23 Feb 2026 | Review of Social Media Guidance - February 2026RESOLVED That the Social Media Guidance for Councillors, including the amendments proposed by the Assistant Director ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.