Resolved
RESOLVED - That (1) the application be approved as detailed in the report and the officer report update; and (2) if, after four months of the date of the resolution, the s106 has not been completed and signed, authority be delegated to the Group Head of Planning to refuse the application for the following reason:- “The proposed development makes no contribution towards local infrastructure and is thereby contrary to the Policy INF SP1 of the Arun Local Plan and the National Planning Policy Framework.” (During the course of discussion on the following item, Councillor Haymes declared a personal interest as comment was made relating to licensing regulations, which came under his remit as Cabinet Member for Technical Services.)
Word for word from the decision Arun published for this meeting.
Source: democracy.arun.gov.uk