Cabinet RECOMMEND TO FULL COUNCIL That the approval of a supplementary estimate of £25,000 for costs associated with defending the appeal in respect of application P/6/17/OUT. These include Counsel costs and costs of appointment of a Planning Consultant to assist Members with defending an appeal in respect of Planning Application P/6/17/OUT. The supplementary estimate equates to a Band D Council Tax of £0.41.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
That Cabinet recommend to Full Council the approval of a supplementary estimate of £25,000 for costs associated with defending the appeal in respect of application P/6/17/OUT. These include Counsel costs and costs of appointment of a Planning Consultant to assist Members with defending an appeal in respect of Planning Application P/6/17/OUT.
The supplementary estimate equates to a Band D Council Tax of £0.41.
1. BACKGROUND: 1.1 Hallam Land Management Ltd submitted to the Council an outline planning application seeking permission for 300 dwellings, care home of up to 80 beds, D1uses (e.g. community facilities) of up to 4000sqm including a 2 form entry Primary School, formation of new means of access onto Hook Lane & Pagham Road, new pedestrian & cycle links, the laying out of open space, new strategic landscaping, habitat creation, drainage features & associated ground works & infrastructure on a site to the north of Hook Lane, Pagham. All detailed matters were reserved other than the means of access into the site. The development site covers 17.5 hectares.
1.2The application was presented to Development Control Committee with a recommendation of approval on 23 January 2019. The application was refused by Development Control Committee. In exercise of its statutory rights under Section 78 of the Town and Country Planning Act 1990, Hallam Land Management Ltd, has appealed the decision to refuse the application. The Planning Inspectorate has decided that the appeal should be heard under the public local inquiry procedure.
1.3The reasons for refusal related to the perceived increased vehicle movements generated by the application exacerbating existing capacity issues on the local highway network and that the mitigation measures proposed being insufficient to overcome the safety concerns resulting from the additional vehicle movements. No indication was provided about what further mitigation measures were required and the decision ran contrary to the advice of officers, the Highway Authority and an independent highways consultant instructed by the Council.
1.4Officer advice on the robustness of this decision is contained on page 288 of the minutes of Development Control Committee on 23 January 2019.
1.5An appeal will be heard into the proposal which is scheduled for 22 – 25 October 2019. It is likely that the appeal will last 4 days; there is a great deal of work involved in preparing the Council’s case for the appeal.
1.6As the appeal is to be heard by way of a public inquiry, the Council will be required to be legally represented by Counsel and fee estimate for this is £7,950 for representation and for the work involved in the preparation and attendance at the appeal.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.