Following consideration of the Minutes, the Cabinet Minute 11 – Safer Arun Partnership Annual Review RESOLVED – That 1. The work of the Safer Arun Partnership be endorsed and the importance of partnership working in contributing to reducing anti-social behaviour and addressing crime and disorder in Arun be recognised; and 2. Recognition be given to the work of the Safer Arun Partnership in contributing to the delivery of the Council’s strategic priority “supporting you if you need help”. Minute 12 – Climate Change RESOLVED - That 1. Arun District Council declares a Climate Emergency; 2. the impact and mitigation of climate change is considered and incorporate into all policy and key decision making; 3. officers work through the Environment & Leisure Working Group to produce an action plan with milestones to make the activities of Arun District Council carbon neutral by 2030.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
Public Document Pack Subject to approval at the next Environment & Leisure Working Group meeting
ENVIRONMENT & LEISURE WORKING GROUP
7 November 2019 at 6.00 pm
Present: Councillors [name removed] (Chairman), Brooks (Vice-Chair), Bicknell, [name removed], Chapman, Clayden, Dixon, Edwards (Substitute for Kelly), Gunner, Huntley, [name removed] and [name removed] Yeates was also in attendance for all or part of the meeting.
Apologies: Councillor Kelly
7. DECLARATIONS OF INTEREST
Councillor Dixon declared a personal interest in agenda item number 4 as a member of the Bognor Regis Civic Society.
8. MINUTES
The minutes of the last meeting held on 4 July 2019 were approved and signed by the Chairman as a correct record.
9. URGENT ITEM - BOGNOR REGIS DISC PARKING SCHEME
The Members received an urgent report from the Customer & Parking Services Manager in relation to the Bognor Regis Disc Parking Scheme that operated in Hothamton, Lyon Street and Fitzleet car parks. It was explained that the scheme was due to finish on 31 December 2019, but a request had been made from The Bid Board and Bognor Regis Town Council that the scheme continues and a long-term agreement be agreed for the scheme.
A full discussion was had by all Members who were all in full support of the scheme being continued consideration was given to the following points:
Cost implication to Arun District Council Possible Sponsorship options to be suggested to The Bid
The Working Group then,
Agreed to recommend to Full Council the extension of the Bognor Regis Disc Parking Scheme up to the 31 December 2022. Subject to approval at the next Environment & Leisure Working Group meeting
2 Environment & Leisure Working Group - 7.11.19
10. LITTLEHAMPTON WAVE UPDATE
The Principal Landscape Officer provided the Members with a final update on the completion of the Littlehampton Leisure Centre project. She highlighted that the project objectives that had defined the scope of the project in 2016, had been met and the total project expenditure was on target to be maintained within the allocated budget. She further explained that as well as providing the new leisure centre for the district, the project had also created a range of wider opportunities that had and continued to add extra value for local people during and after its delivery.
All Members of the Working Group expressed their satisfaction with the project and the completed addition of an excellent leisure and sport provision in the District. Key points that were highlighted throughout the discussion were:
A request for specific feedback from the leisure centres customers to be provided to Members Confirmation was sought to ensure that light pollution measures were considered when the lights for the new path were installed and it was confirmed that grey caps had been included in the design to provide downward light. Praise was given by Members for working in conjunction with Willmott Dixon that assisted with a careers initiative at HMP Ford Attention was drawn to the figures that had been detailed in a report that was presented to the Overview Select Committee on 22 October 2019 showed a significant reduction to the new buildings carbon footprint in comparison to the old building. It was confirmed that the technology was proving to be successful during its first year of use. Tree planting on the west and north side of the site had been completed, and it was confirmed that further planting of trees was planned.
The Chairman thanked the Principal Landscape Officer and the Group Head of Community Wellbeing for the update which was then noted by the Working Group.
11. SAFER ARUN PARTNERSHIP ANNUAL REVIEW
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.