The Cabinet RESOLVED – That (1) In view of the timescales involved for this project, to instruct Officers to extend the existing contract with Auditel, for the webcasting of all public meetings for the next twelve months the cost of which is to be met from existing budgets; (2) To note that a further report will be provided to Cabinet setting out the anticipated costs and long-term financial implications of a range of options for webcasting; and (3) In the event of physical meetings becoming possible in the next six months which the public are allowed to attend in the Civic Centre, Officers investigate the ongoing use of Zoom and/or the utilisation of the Council Chamber for both Cabinet and the Overview Select Committee to be webcast alongside Full Council and the Development Control Committee.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
Following the reports that were made to Cabinet on 8 July and 9 December 2019, this report feedbacks to the Cabinet the findings from the corporate officer group that was set up to examine the future webcasting needs of the Council and associated costs but has been amended to reflect the Council’s current financial position.
Recommendation
Cabinet is asked to resolve that:
1) In view of the timescales involved for this project, to instruct Officers to extend the existing contract with Auditel, for the webcasting of all public meetings for the next twelve months the cost of which is to be met from existing budgets; and 2) To note that a further report will be provided to Cabinet setting out the anticipated costs and long-term financial implications of a range of options for webcasting; and 3) If within the next 6 months the public are allowed to attend meetings in the Civic Centre then the webcasting will revert to the Full Council and Development Control Committee meetings only.
Background
1.1As a result of the webcasting issues reported to Cabinet on 8 July and 9 December 2019, a corporate group has been working to specify and prepare a procurement exercise for the purchase of a reliable, fully integrated, fit-for-purpose, and future proof webcasting presentation and conference system. The webcasting service is currently provided by Auditel UK Limited. This company also provide and service the sound system in the Council Chamber.
1.2Cabinet was updated on 9 December 2019 of the problems experienced in using more frequently the webcasting service. The last Civic Suite refurbishment was completed in 2015 having had numerous improvements made to the installed AV facilities, including the addition of the webcasting equipment. Alongside the installed systems, a service and maintenance agreement were entered into with the installer. From November 2018 onwards, webcasting has been used to a much greater extent highlighting deficiencies in the installed system and indicating a number of faults. These problems have prevented Officers from delivering the intended level of service to Councillors, members of the public and the press. 1.3 Separately, a wireless conferencing system was purchased in two phases around 2010 to serve the Public Gallery and Committee Rooms, as well as being available for mobile deployment. This system is battery powered and is now obsolete with batteries being unavailable either from the original manufacturer or aftermarket sources. Batteries for the system are now failing to hold charge and are frequently not lasting the duration of meetings. 1.4 The Committee Services Team; ICT and the Senior Estates Surveyor have worked collaboratively with Auditel’s Senior Management Team in escalating and resolving the Council’s dissatisfaction with the service, the result of which has been a much-improved client relationship. All outstanding issues have been resolved where technologically possible and the working partnership between the Council and Auditel is back on track. Since 9 December 2020, meetings of Full Council and the Development Control Committee have not been livestreamed and only been recorded and published the following day to eliminate any risk of a webcast failure, as agreed by Cabinet on 9 December 2019. 2. PROPOSAL(S): 2.1 The officer group has undertaken a considerable amount of work including a soft market testing exercise to understand the technical requirements of upgrading and extending the current webcasting arrangements to include the committee rooms. Key elements of the draft specification for a fully comprehensive system include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.