R/197/20/OUT - Croft Works, 52 Mill Lane, Rustington

Refused Planning 1 paper

Planning Committee refused this item on Wednesday 3 February 2021. Below is the council's own wording, with the papers it was decided on.

Item451

Resolved

RESOLVED That the application be REFUSED and the reasons for refusal was due to t he proposal by virtue of its narrow access lane would endanger pedestrian safety and prevent access by emergency vehicles contrary to policy T SP1 of the Arun Local Plan and paragraph 110 b), c) & d) of the National Planning Policy Framework.
Word for word from the decision Arun published for this meeting. Source: democracy.arun.gov.uk

Follow this further

Built from Arun's papers

What the report saysPro

Report to Planning Committee

R/197/20/OUT

Report following a request for further information, negotiations or consultation

REF NO: R/197/20/OUT LOCATION: Croft Works 52 Mill Lane Rustington PROPOSAL: Outline application with some matters reserved for the demolition of existing dilapidated storage buildings & erection of 2 No. detached 3-bedroom chalet bungalows with associated car barns, gardens, car parking & landscaping (resubmission following R/117/20/OUT).

This application was deferred from the DC Committee meeting on 06-01-2021 to check that the width of the access road complies with building regulations for access by fire service vehicles. This is set out in Approved Document - B (AD-B) Volume 1 2019 section 13 Table 13.1 on page 98. It is expected that vehicles will travel in a straight line, not need to make a turn whilst passing through and there should be 3.7 metres between curbs.

The agent has subsequently visited the site and measured the width of the access at several points along the access road and taken photographs of where the measurements are taken from. A revised drawing showing these dimensions has been received and the case officer has visited the site to verify the measurements given.

In summary, there are some small discrepancies between the OS/Title plans used and the dimensions on the ground. This appears to result from fences being placed in different positions to the legal title over time, with the neighbours to the south seemingly encroaching slightly onto these title plans.

Following the case officer site inspection it was found that the width of the entrance point is very close to the previously noted 4.65m at around 4.4- 4.5m. There is a pinch point at around the centre of the access driveway where this reduces to 3.3m wide. At the end of the driveway the dimension measures 3.8m which is slightly less than the 4.1m on the title plan.

Based on the measurements determined by the case officer it would appear that the access way would not be capable of complying with the above stated Building Regulations.

The agent has advised that appropriate Building Regulations will be met by way of the provision of sprinklers and/or a fire hydrant. This can be secured by way of a condition.

West Sussex County Council have been consulted regarding the veracity of complying with the relevant Building Regulation with the following:

'County Water and Access have viewed the plan and agent's e-mail and confirm the current intentions do not meet with the requirements of Approved Document - B Volume 1: 2019 edition B5 section 13 for Fire Appliance access. The minimum access width for a fire appliance is 3.7 metres between curbs and 3.1 metres through a gateway in a straight line, so there is adequate access width, there is also a need for suitable space to turn and make an exit, which may also be possible.

However for houses fully sprinklered in accordance with British Standard (BS) 9251: 2014 or BS EN 12845, BS 9991:2015 para 50.1.2 does allow the distance between the fire appliance and any point within all houses to be up to 90 metres. The distance from the main road to the furthest point is R/197/20/OUT

approximately 80 metres so within this required distance.

If access to the properties is not suitable for a fire appliance there is no reason to have a fire hydrant along the access driveway. Fire hydrants provide water to the fire appliance not the scene of the fire; there is an existing fire hydrant within 30 metres of the access point. The preference would be to gain access to the properties, if this cannot be achieved each property will need to be fully sprinklered.'

The Council's Building Control Department has advised that a suppression system, such as sprinklers would be acceptable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
R/197/20/OUT: Croft Works, 52 Mill Lane, RustingtonReport 73 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 19 attended
JB
Councillor Jamie BennettChairman, present
MI
Councillor Ms Isabel ThurstonVice-Chair, present
BB
Councillor Billy Blanchard-CooperCommittee Member, present
RB
Councillor Richard BowerCommittee Member, present
JC
Councillor John CharlesCommittee Member, present
HC
Councillor Hugh CosterCommittee Member, present
DE
Councillor David EdwardsCommittee Member, present
MJ
Councillor Mrs June HamiltonCommittee Member, present
PK
Councillor Paul KellyCommittee Member, present
ML
Councillor Martin LuryCommittee Member, present
MJ
Councillor Mrs Jacky PendletonCommittee Member, present
GR
Councillor Grant RobertsCommittee Member, present

All 19 on the meeting page

More from Arun Planning Committee

All decisions
MeetingDecisionOutcome
26 Aug 2026 BN/52/26/S73 The former Croft Surgery, Barnham Road, Eastergate PO20 3RPRESOLVED That the application be APPROVED CONDITIONALLY. Approved Open
26 Aug 2026 Former Merry England Nursery (Now Swallows Gate), Angmering and non-provision of footpath.RESOLVED 2.1 that the council will take no action regarding the breach, inform Swallows Gate residents and any other ... Decided Open
26 Aug 2026 F/19/25/OUT Land to the south of Ford Lane, Arundel BN18 0DFRESOLVED That the application be DEFERRED for a period of one month to enable the drainage information to be fully re... Deferred Open
26 Aug 2026 AL/44/26/S73 Laurel Rise and Grey Gables (Former Plot 1), Fontwell Avenue, Eastergate PO20 3RURESOLVED That the application be APPROVED CONDITIONALLY. Approved Open
26 Aug 2026 AL/45/26/S73 Pip Pen and House not completed yet (Plot 2), Fontwell Avenue, Fontwell PO20 3RURESOLVED That the application be APPROVED CONDITIONALLY. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies