RESOLVED to (i) Note the Member Recommendations/Action Plan (Appendix C) (ii) Note the Officer Recommendations/Action Plan (Appendix B) (iii) Approve a virement of £130k (from the Covid-19 catch up reserve) to enable the Officer recommendations from the report to be implemented. (iv) Support the need for continued Member training on planning matters, as outlined within the Planning Review (Appendix D) (v) Agree that the Planning Review recommendations should be reviewed, by the Planning Committee, initially six monthly (if the Recommendations are agreed by Full Council), to satisfy themselves that the actions are being followed through. The Committee RECOMMEND THAT FULL COUNCIL (vi) Agree the Review’s recommendations for the Council (as a whole).
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
The Hannaby Planning Review was completed in November 2020. The recommendations were split into actions for Members, Officers and both Members and Officers. The Member actions, and the Officer actions, have been dealt with separately. This report brings the recommendations and actions together so that the Planning Committee, and then Full Council, can consider the report and the outcomes as a whole.
Recommendations
The Planning Committee is requested to:
(i) Note the Member Recommendations/Action Plan (Appendix C) (ii) Note the Officer Recommendations/Action Plan (Appendix B) (iii) Approve a virement of £130k (from the Covid-19 catch up reserve) to enable the Officer recommendations from the report to be implemented. (iv) Support the need for continued Member training on planning matters, as outlined within the Planning Review (Appendix D) (v) Agree that the Planning Review recommendations should be reviewed, by the Planning policy Committee, initially six monthly (if the Recommendations are agreed by Full Council), to satisfy themselves that the actions are being followed through.
The Planning Committee is also requested to recommend that Full Council:
(vi) Agree the Review’s recommendations for the Council (as a whole).
Background
1.1The Planning Review was determined necessary following a variety of issues that arose in various Development Control Committee meetings late 2019. It was agreed by the (then) four Group Leaders that the Council needed to review how it approached planning as a whole.
1.2It was agreed that the review would focus on People (leadership/management, relationships, staff structures and resources), Performance (quality, consistency and speed of decision-making), Procedures (efficiency and effectiveness) and the Development Control Committee itself (relationships, effectiveness, decision- making and procedures).
1.3As part of the review, it was agreed that an Improvement/Action Plan would also be drawn up to identify what improvements were necessary and how to tackle them. A Member and Officer Training Plan was also requested.
1.4In February 2020, Sean Hannaby, of Hannaby Planning Solutions Ltd was appointed to undertake this work. Unfortunately, the Coronavirus has not only slowed progress on this review, but it also hampered the originally intended process. However, a robust process of interviews, observations and desktop analysis fed into the review process, although this took longer due to the Coronavirus pandemic. Written observations by Members also formed part of the review.
1.5The aim of the review was to learn from the experience and advice of an independent expert. The Council may not accept all the findings, but it will need to examine each of the recommendations from the review and consider what approach it wants to take to each of the recommendations.
1.6The final report from Hannaby Planning Solutions Ltd included recommendations and improvement plans. The recommendations were presented to a Members Working Party on 24.11.20. The recommendations and suggested improvements within the report are divided into sections, some for Members only, some for Members and Officers and some for Officers only. The recommendations for Officers are staffing matters which have been progressed by the Chief Executive (in liaison with the Director of Place) as the Constitution gives authority for this. A presentation to officers was made on 1 December 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.