Housing and Wellbeing Committee, Thursday 30 September 2021 at 6.00pm

Approval to Appoint a Roofing Contractor

Approved Committee 2 papers

Housing and Wellbeing Committee approved this item on Thursday 30 September 2021. Below is the council's own wording, with the papers it was decided on.

Item321

Resolved

RESOLVED To approve awarding a contract for roofing works for various properties and to approve the virement of £100,000 from the Kitchen and Bathroom programme budget to the Roofing budget to fund the project. Both of these budgets are in the Housing Revenue Account Capital Programme.
Word for word from the decision Arun published for this meeting. Source: democracy.arun.gov.uk

Follow this further

Built from Arun's papers

What the report saysPro

Report to Housing and Wellbeing Committee

Background

Arun District Council needs to maintain its homes, including ensuring roofs are wind and weatherproof. We have identified a number of properties where the roofs have reached the end of their life and require replacement. In total there are 174 properties where the roof requires replacement.

A technical specification outlining what work is required was produced. The tender process was managed by Hampshire County Council Procurement Manager and tenders issued via the Open Portal. Bidders were asked to submit a price for each property and complete a quality questionnaire. Tenders were evaluated on a price per quality point methodology to ensure the bidder who offered the best value for money would be the successful tenderer.

Using price per quality point, quality is always marked out of 100% with weightings suitably divided amongst the quality questions. Once the final quality score for a tenderer is known their price is divided by this quality score. The result will indicate how much you are paying for each point of quality awarded. This essentially combines price and quality in such a way as to determine the best value for money, which the traditional ways of evaluating tenders does not do.

Nine contractors submitted a tender. One was automatically excluded because no quality questionnaire was submitted. Three other bidders were eliminated at the evaluation stage because they did not comply with the tender instructions. The five remaining tenders were evaluated. Approval is sought to award the contract to the bidder who was ranked no.1 following the evaluation.

2. PROPOSAL(S): .

It is proposed that a contract is awarded to carry out roof replacement works to various Arun District Council owned Residential properties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AppendixAppendix 172 KB Download
PDF
Approval to Appoint a Roofing ContractorReport 32 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
JP
Councillor Jacky PendletonChair, present
PG
Councillor Pauline GregoryVice-Chair, present
FC
Councillor Faye CattersonCommittee Member, present
AC
Councillor Alison CooperCommittee Member, present
SD
Councillor Sandra DaniellsCommittee Member, apologies, sent representative
JE
Councillor Joan EnglishCommittee Member, present
JH
Councillor June HamiltonCommittee Member, absent
CH
Councillor Christopher HughesCommittee Member, present
CM
Councillor Claire Marie NeedsCommittee Member, apologies
VR
Councillor Vicky RhodesCommittee Member, absent
ES
Councillor Emily SeexCommittee Member, present as substitute
GY
Councillor Gill YeatesCommittee Member, present

All 14 on the meeting page

More from Arun Housing and Wellbeing Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 Extension of meetngRESOLVED That the meeting be extended by up to 30 minutes in line with Part 5, Section 2, paragraph 8 of the Constitu... Decided Open
6 Jul 2026 Review and Strengthening of Corporate Landlord Services KPIsRESOLVED to 2.1 Approve the proposed revisions to targets and Red, Amber, Green (RAG) tolerances for the following La... Approved Open
6 Jul 2026 Extension of Public Health Wellbeing ProgrammeRESOLVED T hat members support the extension of the current Arun Wellbeing Programme for a further 2 years, securing ... Decided Open
6 Jul 2026 Tenant Satisfaction Measures and Consumer StandardsRESOLVED That consideration of the report on Tenant Satisfaction Measures and Consumer Standards be deferred to the n... Deferred Open
23 Jun 2026 Start Times 2026/27RESOLVED That the start time for meetings of the Committee for 2025-2026 would be 6.00pm. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies