RESOLVED - That (1) Agreement be given to a variation to the existing construction contract with Edburton for the delivery of phase 1 (Terminus Road, Littlehampton) as recommended by a procurement report (appendix 1); subject to Full Council approval of recommendation 2. The Committee also RECOMMEND TO FULL COUNCIL - That (2) It accepts and draws down £1.253m from WSCC to complete the phase 1 (Terminus Road, Littlehampton) works and add the expenditure and funding to the 2022/23 Capital Programme; (3) It approves authority to enter into a collaboration agreement with WSCC that sets out the billing regime for the funds in (1) above and approves the drawdown and expenditure of external funding, and that the terms and conditions are agreed by Legal Services and in consultation with the Monitoring Officer; (4) As per Part 4 – Officers Scheme of delegation (4.3 to 4.7 refers) and under Part 7 of the Council’s Constitution, delegated authority be given to the Director of Place to plan, draw down and make budgetary decisions on the expenditure on this phase in accordance with the ... view the full minutes text for item 781.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
Project: Littlehampton Town Centre Improvements Date: 12 November 2021
01 Introduction The following procurement note has been prepared on behalf of Arun District Council (ADC) in relation to Littlehampton Town Centre Improvements scheme that consists of regeneration to public realm areas in the Littlehampton town centre. The aim of the Improvements is to improve the appearance of the town centre and surrounding public spaces, whilst increasing foot fall and trade to local businesses. The scheme consists of three phases:
Phase 1 (Terminus Road from the railway station to Arundel Road roundabout / The High Street).
Phase 2 (The High Street, east to west, vehicular and pedestrian sections).
Phase 3 (Beech Road, north to south, ending at the War Memorial roundabout).
This report summarises the tender process and evaluation of the two-stage tender relating to the provision of pre-contract design and construction for phases 2 & 3 and analyses the advantages of instructing the phase 1 construction as a compensation event (variation) to the Phase 2 and 3 contract. 02 Original Tender Exercise The design and construction of Phases 2 and 3 were procured through a competitive two-stage design and build procurement route using NEC4 forms of contract. Included within this procurement exercise was the design only for Phase 1 (up to RIBA Stage 4). During the first stage of this tender process, the competitively tendering contractors were asked to price the following: • Overheads and profits (oh&p); • Project preliminaries; • Surveys; • The design of phases 1, 2 and 3; • Construction design fees; • 5Nr key paving type items that made up 50% of the construction costs. The paving costs were obtained as these works could be undertaken direct by the contractors (instead of via subcontractors) and to give an element of overall contract sum cost certainly within the first stage tender returns. Whilst these rates would vary in accordance with further design and inflation, they nevertheless would form the basis of subsequent cost build ups for the paving rates. As well as the cost component of the tender there was a quality questionnaire that accounted for 25% of the tender evaluation.
The contract for the works was awarded to Edburton Contractors Ltd for the following reasons: • Their quality score of 80/100 at PQQ Stage 1 was the highest; • Their anticipated tender sum after normalisation was the lowest and thus offered the best value.
Contains sensitive information 03 Evaluation of Edburton Phase 2 and 3 Submission Following the completion of RIBA Stage 3 and 4 design, Faithful+Gould (F+G) have reviewed the second stage tender submitted by Edburton, and agreed the contract sum for the Phase 2 and 3 construction works. These costs have been assessed to be in accordance with the competitively tendered rates from the first stage tender (see section 02) suitably adjusted for changes in programme duration (preliminaries), inflation to paving costs, and with subcontractor packages competitively tendered and with the agreed oh&p rate then applied to the selected packages.
04 Phase 1 Procurement Strategy Primary options for main contractor procurement:
1. Competitive single stage tender and appointment under NEC4 contract; 2. Instruct as a compensation event (variation) under the Phase 2 and 3 NEC4 contract (construction works).
After review, it has been assessed that the best approach for ADC to procuring a main contractor for the construction of the phase 1 works, would be to instruct the work as a compensation event to the Phase 2 and 3 NEC4 contract.
The following advantages have been identified from this procurement route:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.