RESOLVED That the proposed alternative routes be noted and that there were no additional comments specific to those proposals, and that the resolution of the Committee in September 2021 [Minute 238] remained unchanged. The Chair informed the Committee that the meeting would then be adjourned and a date to finish the business of the meeting to take place within 10 working days would be communicated to Committee Members as soon as available. The meeting was then adjourned.
Word for word from the decision Arun published for this meeting.Source: democracy.arun.gov.uk
1.1To consider the proposed amendments to the onshore elements of the Rampion2 Wind Farm proposals.
Recommendations
2.1That the Committee notes the proposed alternative routes and confirms that there are no additional comments that are specific to these proposals and that the resolution on the Committee in September 2021 remains unchanged.
Executive summary
3.1This is an amended consultation process (following that carried out in summer 2021) due to amended proposals for the onshore cable corridor to a newly proposed substation at Cowfold in Horsham District. The proposals now consist of up to 90 turbines (reduced from 116). This is not a re-run of the previous consultation but is a targeted consultation on the proposed changes to the scheme. An updated Statement of Community Consultation accompanies this targeted consultation process. 4. DETAIL
4.1Planning Committee consider the Council’s response to the initial pre-application consultation on 8 September 2022. The response to that consultation was agreed at the meeting.
4.2A new consultation is being carried out as a result of the proposed change to the on-shore cable route as a result of a different site being selected for a substation – this being Cowfold instead of Bolney. This is a targeted consultation only in respect of the proposed changes and any comments on the amendments will be supplementary to previous comments. A Preliminary Environmental Impact Report Supplementary Information Report (SIR), which includes more detailed preliminary environmental information about our proposed alternatives and modifications has been produced as part of this consultation.
4.3Off-shore changes now include the reduction from up to 116 turbines previously proposed to up to 90.
4.4The proposed new onshore cable route to the new substation location involves some additional areas of land that were not contained within the original Preliminary Environmental Impact Report (PIER) in summer 2021.
4.5For Arun, the amended proposals include an alternative cable route, two modified routes (MR), two new trenchless crossings (TC) and three alternative accesses (AA). The first modification relates to where landfall is taken. This is now proposed to be approximately 300m east of the previous proposal. This has been proposed as a result of comments during consultation in respect of coastal erosion and flood risk. There may be a need for a temporary drilling compound approximately 400m back from the beach. There is also a very slightly modified route immediately north of Ferry Road. An alternative access to link construction compounds to the cable is proposed off Church Lane, Climping.
4.6A slightly amended cable route is also proposed where it crosses the railway at Arundel Junction (to the north of Kingley Gate. The proposed route would run parallel to the railway line on the western side.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.